ANNEXURE-III
ANNEXURE-III
Restriction to erect Telecommunication Infrastructure Towers.
(1) Water Bodies: (i) No Telecommunication Infrastructure Tower shall be
allowed in the bed of water bodies like river or nala and in the Full Tank
Level (FTL) of any lake, pond, kunta lands. Unless and otherwise stated, the
area and the Full Tank Level (FTL) of a Lake or Kunta shall be reckoned as
measured and as certified by the Revenue/ Minor Irrigation/ Water
Resources Department.
¨sÁUÀ 4J , 19 2025 3347
(ii) The buffer to be maintained from various water bodies including rivers,
takns, Kuntas, Canals, Nalas, Storm Water Drains, for installation of
Telecommunication Infrastructure Tower shall be as prescribed by
Government from time to time.
(2) Railways: The distance between the Railway Property Boundary and the
Telecommunication Infrastructure Tower shall be 30m as per Indian
Railways Works Manual or as per no objection certificate given by the
Railway Authorities.
(3) Electrical Lines: The Right -of-way widths recommended for Electrical
lines of various Transmission Voltage are as indicated in the table below:-
(i) Right-of –way (ROW) for Electrical lines.-
Sl.
No.
Transmission voltage Width of the Right-of-way
(ROW) in meters
01 11 kV 7.0
02 33 kV 15.0
03 66 kV 18.0
04 110 kV 22.0
05 132 kV 27.0
06 220 kV 35.0
07 400 kV 52.0
(ii) Distance of site from Electric Lines.- No Telecommunication
Infrastructure Tower shall be allowed to be erected or re-erected or any
additions or alterations made to Telecommunication Infrastructure Tower in
a site within the distance quoted below in accordance with the current
Electricity Rules and its amendments from time to time between the
building and any overhead electric supply line;
Vertically in
mtrs.
Horizontally in
mtrs.
i Low and medium voltage
lines and service lines
2.5 1.2
ii High voltage lines upto and
including 33,000 V.
3.7 2.0
iii Extra high voltage lines
beyond 33000 V.
3.7 (plus 0.3m
for every
additional
33,000 V. or
part thereof )
2.0 (plus 0.3m
for every
additional
33,000 V. or
part thereof )
(4) In the reserved forest or forest areas: for erecting the Towers, NOC from
the Forest Department shall be submitted.
(5) Heritage, Religious and Other Structures: (i) In case of Sites located
within the distance up to 100meters from protected monuments as notified
3348 , 19 2025 ¨sÁUÀ 4J
under the Ancient Monuments and Archaeological sites and Remains Act
1958 (central Act 24 of 1958) or the Karnataka Ancient and Historical
Monuments and Archaeological sites and Remains Act, 1961 (Karnataka Act
7 of 1962) no building or Telecommunication Infrastructure Tower is
allowed;
(ii) For the Sites located within distance of above 100meters and up to
200meters from the protected monuments, the construction of one
Telecommunication Infrastructure Tower is allowed only after obtaining
prior permission from the concerned appropriate authority.
Provide that CoW/micro sites/IBS/Boosters etc may allowed with prior
intimation to the Chief officer/PDO.
(iii) In case of Wall Mounted or Pole mounted Antenna, the antenna shall be
mounted at least 5 meters above ground level or road level on flyovers.
Previous and next
Questions people ask
Is annexure III of the Karnataka Town and Country Planning (Development of Land in areas other than Local Planning Areas) Regulations, 2025. still in force?
No repeal of the Karnataka Town and Country Planning (Development of Land in areas other than Local Planning Areas) Regulations, 2025. is recorded.