Regulation 9, The Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018: Additional charges for crossing Deviation Volume Limits

The Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018 - Regulation 9

Text of regulation 9

Additional charges for crossing Deviation Volume Limits

9. Additional charges for crossing Deviation Volume Limits.—(1) In addition to charges for Deviation as stipulated under Regulation 7 of these regulations, additional charge for Deviation shall be applicable for incremental over-drawal as well as under-injection of electricity for each slab in respect of each time block in excess of the volume limit specified in regulation 8 above, when average grid frequency of the time block is 2 [49.85 Hz] and above but upto 50.05 Hz” at the rates specified in the Table-2 below. 1 Sub. for regulation 8 in sub-regualtion (1) & (2) and provisio for words and figures “49.70Hz” for vide not. No. HPERC/428 dated 29th June, 2019, published in R.H.P. dated 3rd July, 2019 at p. 3131- 3137. 2 Sub. for regulation 9 in sub-regualtion (1) for words and figures “49.70Hz” for vide not. No. HPERC/428 dated 29th June, 2019, published in R.H.P. dated 3rd July, 2019 at p. 3131-3137. 14 Compendium of HPERC Regulations, March 2021 Table-2 Additional Charges for Deviation beyond the limits on Deviation Volume 1. For over drawal of electricity by any buyer in excess of 12% and up to 15% of the schedule in a time block Equivalent to 20% of the charge for Deviation corresponding to average grid frequency of the time block. 2. For over drawal of electricity by any buyer in excess of 15 % and upto 20% of the schedule in a time block Equivalent to 40% of the charge for Deviation corresponding to average grid frequency of the time block. 3. For over drawal of electricity by any buyer in excess of 20 % of the schedule in a time block Equivalent to 100% of the charge for Deviation corresponding to average grid frequency of the time block. 4. For under injection of electricity by any seller in excess of 12% and upto 15% of the schedule in a time block Equivalent to 20% of the charge for Deviation corresponding to average grid frequency of the time block. 5. For under injection of electricity by any seller in excess of 15% and upto 20% of the schedule in a time block Equivalent to 40% of the charge for Deviation corresponding to average grid frequency of the time block. 6. For under injection of electricity by any seller in excess of 20% of the schedule in a time block Equivalent to 100% of the charge for Deviation corresponding to average grid frequency of the time block. Provided that any drawal of power by a generating station prior to COD of a unit for the start up activities shall be exempted from the levy of additional charges of Deviation. (2) In addition to the Charges for Deviation as specified under regulation 7 of these regulations, additional charge for Deviation shall be payable for the over-injection and/or under drawal of electricity for each time block by a seller and/or buyer, as the case may be, 1 [when grid frequency is “50.10 Hz and above” at the rate of Deviation charges applicable for the frequency range of 50-50.01 Hz for that day as per the Table-1 under regulation 7.] (3) In addition to the charges for Deviation as stipulated under regulation 7 of these regulations, additional charge for Deviation shall be payable for over-drawal and/or under injection of electricity for each time block by a buyer and/or seller, as the case may be, when grid frequency is “below 2 [49.85] and the rate for the same shall be equivalent to 100% of the charge for Deviation corresponding to the grid frequency of “below 49.85 Hz” i.e. 2 [800 Paise/kWh]. 3

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018

Questions people ask

Is regulation 9 of the Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018 is recorded.