Additional Charges for not meeting the requirements for Change in sign of deviations
[9A. Additional Charges for not meeting the requirements for Change in sign of
deviations.—
"In the event of sustained deviation from schedule in one direction (positive or
negative) by any State Entity (buyer or seller), such entity shall correct its position in the
manner as specified in following clauses (a) and (b) of this Regulation.
1 Sub. for regulation 9 in sub-regualtion (2) vide not. No. HPERC/428 dated 29
th
June, 2019, published in
R.H.P. dated 3
rd
July, 2019 at p. 3131-3137 and before its substitution read as under:
“ when grid frequency is ‟50.10 Hz and above” at the rate of 178 paise per kWh.”
2 Sub. for regulation 9 in sub-regualtion (3) for words and figures “49.70Hz and 824.04 Paise/kWh” for
vide not. No. HPERC/428 dated 29
th
June, 2019, published in R.H.P. dated 3
rd
July, 2019 at p. 3131-3137.
3
Ins. regulation 9A vide not. No. HPERC/428 dated 29
th
June, 2019, published in R.H.P. dated 3
rd
July,
2019 at p. 3131-31373.
Compendium of HPERC Regulations, March 2021 15
(a) on or before 31-03-2020, if the sustained deviation from schedule continues for 12
time blocks, the State Entity (buyer or seller), shall correct its position either by
changing the sign of its deviation from schedule or by restricting the sustained
deviation to the permissible limits as specified in Table-3 below with reference to
its schedule for the time block to be reckoned for violation, at least once, latest by
13
th
time block.
Table-3
Maximum permissible limits for Sustained Deviation from Schedule
Sl.
No.
Schedule for relevant time
block to be reckoned for
violation
Maximum permissible limits (in one
direction of sustained deviation) in
MW
1. Up to 10 MW 0.5
2. Upto 25MW 1.0
3. Upto 100MW 2.00
4. Above 100 MW 10.00
Provided that each violation of the requirement under this clause shall attract an
additional charge of 10% on the time block DSM payable/ receivable as the case
may be;
(b) on or after 01-04-2020, if the sustained deviation from schedule continues for 6
time blocks, the State Entity (buyer or seller), shall correct its position, either by
changing the sign of its deviation from schedule or by restricting the sustained
deviation to the permissible limits as specified in Table-3 above with reference to
its schedule for the time block to be reckoned for violation, at least once, latest by
7th time block:
Provided that violation of the requirement under this clause shall attract an
additional charge as specified in the table-4 below:
Table-4
Additional Charge for Violation in Sustained Deviation from Schedule:
No. of Violation in a Day Additional Change Payable
From first to fifth violation For each violation, an additional charge @ 3% of
daily base DSM ayable/receivable.
From sixth to tenth violation For each violation, an additional charge @ 5% of
daily base DSM payable/receivable.
From eleventh violation
onwards
For each violation, an additional charge @ 10% of
daily base DSM payable/receivable.
Provided further that counting of number of sign change violations under clauses
(a) & (b) of this Regulation shall start afresh at 00.00 Hrs. for each day:
Provided further also that payment of additional charge for failure to adhere to sign
change requirement as specified under clauses (a) & (b) of this regulation shall not
be applicable to—
(i) any infirm injection of power by a generating station prior to CoD of a
unit during testing and commissioning activities, in accordance with the
Connectivity Regulations; and
16 Compendium of HPERC Regulations, March 2021
(ii) any drawal of power by a generating station for the start-up activities of a
unit.
Explanation.—For the purpose of this Regulation, sustained deviation means
continuous deviation outside the maximum permissible limit as specified in
Table-3 above, such range being a subset of the volume limit as specified in
sub-regulations (1) and (2) of regulation 8. In other words, if the deviation is
brought within the range as specified in Table-3 or it remains within the range
specified in Table-3, it will not be considered as sustained deviation, even if
the change in sign of deviation has not taken place.
Illustrations:—
(i) Illustration to clause (a) of this regulation.—A State Entity having
a sustained deviation from time blocks t1 to t12, should correct its
position either by changing the sign of its deviation (from positive to
negative or negative to positive as the case may be) or come back in
the permissible limits as specified in Table-3 above with reference to
its schedule latest in the end of time block t13. In case, such sign
change does not take place or it fails to come back in the range as
specified in Table-3 above in the end of time block t13, but such
correction of position takes place from time block t14 up to time
block t24, then the additional charge shall be levied equivalent to one
violation.
The above violation shall attract an additional charge at the rate of
10% of the time block DSM for t13. Further, in case, sign change
does not take place or it fails to come back to the range as aforesaid
even latest in the end of t25, but correction of position takes place
from time block t26 up to time block t36, then the additional charge
shall be levied equivalent to two violations. The above violation shall
attract an additional charge at the rate of 10% of the time block DSM
for t13 & t25, and so on.
(ii) Illustration to clause (b) of this regulation.—On or after 01-04-
2020, if a State Entity having a sustained deviation from time blocks
t1 to t7, should correct its position either by changing the sign of its
deviation (from positive to negative or negative to positive as the case
may be) or come back in the range as specified in Table-3 above with
reference to its schedule latest in the end of time block t7. In case,
such sign change does not take place or it fails to come back in the
aforesaid range in the end of time block t7, but such correction of
position takes place from time block t8 up to time block t12, then
additional charge shall be levied equivalent to one violation. Further,
in case, sign change does not take place or it fails to come back in the
range as aforesaid latest in the end of t13, but correction in position
takes place from time block t14 up to time block t18, then the
additional charge shall be levied for two violations and so on.
The additional charge shall be at the rate as specified in Table-4 above of this
Regulation.
(iii) In case the State Entity effects change in the sign of its deviation from
the schedule, or otherwise restricts the deviation to the permissible
Compendium of HPERC Regulations, March 2021 17
limit as per Table-3, before the expiry of latest time block in which it
was required to do so, the violations, if any, for the remaining period
of the day shall be counted with reference to the time block in which
it has actually complied the said requirement prior to the expiry of
that time block.
(iv) The additional charge as per this regulation shall be computed on the
sum total of the mode values (i.e. by ignoring the sign) of the amount
payable and receivable for that day under regulation 7.]
Previous and next
Questions people ask
Is regulation 9A of the Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018 is recorded.