Limits on Deviation Volume

8. Limits on Deviation Volume.—(1) The over-drawal/under-drawal of electricity by any buyer during the time block shall not exceed 12% of its scheduled drawal, when grid frequency is 1 [49.85Hz] and above” but “below 50.05 Hz”: Provided that no over-drawal of electricity by any buyer shall be permissible when grid frequency is “below 1[49.85Hz]” and no under-drawal of electricity by any buyer shall be permissible when grid frequency is “50.05 Hz and above”. (2) The under-injection/over-injection of electricity by a seller during a time-block shall not exceed 12% of the scheduled injection of such seller, when frequency is 1 [49.85Hz] and above but below 50.05 Hz”: Provided that no under injection of electricity by a seller shall be permissible when grid frequency is "below 1[49.85Hz]" and no over injection of electricity by a seller shall be permissible when grid frequency is "50.05 Hz and above”: Provided further that any injection of infirm power by a generating station prior to COD of a unit during testing and commissioning activities shall be exempted from the volume limit specified above for a period not exceeding 6 months or the extended time allowed by the Commission: Provided further that any drawal of power by a generating station prior to COD of a unit for the start up activities shall be exempted from the volume limit specified above when grid frequency is “[49.85Hz] and above".

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018

Questions people ask

Is regulation 8 of the Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018 is recorded.