Regulation 9, Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017: Tariff Structure
Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 - Regulation 9
Text of regulation 9
Tariff Structure
9. Tariff Structure.—The tariff for renewable energy technologies shall
be single part tariff consisting of the following fixed cost components:
(a) Return on equity;
(b) Interest on loan capital;
(c) Depreciation;
(d) Interest on working capital;
(e) Operation and maintenance expenses;
Provided that for renewable energy technologies having fuel cost
component, like RDF fuel based Waste to Energy projects, biomass
power projects and non-fossil fuel based cogeneration, Biomass gasifier
projects, single part tariff with two components, fixed cost component
and fuel cost component, shall be determined.
10. Tariff Design
(1) The generic tariff shall be determined on levellised basis for the
Tariff Period.
Provided that for renewable energy technologies having single
part tariff with two components, tariff shall be determined on levellised
basis considering the year of commissioning of the project for fixed cost
component while the fuel cost component shall be specified on year of
operation basis.
(2) For the purpose of levellised tariff computation, the discount
factor equivalent to Post Tax weighted average cost of capital
shall be considered.
(3) Levellisation shall be carried out for the ‘useful life’ of the
Renewable Energy project while Tariff shall be specified for the
period equivalent to ‘Tariff Period’.
11. Despatch principles for electricity generated from Renewable
Energy Sources:
(1) All renewable energy power plants except for biomass power
plants with installed capacity of 10 MW and above, and non-
8 BIHAR GAZETTE (EXTRA) 24TH OCTOBER 2017
fossil fuel based cogeneration plants shall be treated as ‘MUST
RUN’ power plants and shall not be subjected to ‘merit order
despatch’ principles.
(2) The biomass power generating station with an installed capacity
of 10 MW and above and non-fossil fuel based co-generation
projects shall be subjected to scheduling and despatch code as
specified under Indian Electricity Grid Code (IEGC) and Central
Electricity Regulatory Commission (Deviation Settlement
Mechanism and Related Matters) Regulations, 2014 including
amendments thereto.
(3) Scheduling of wind and solar energy shall be governed as per
the aforesaid provisions of Central Electricity Regulatory
Commission (Indian Electricity Grid Code) (Third Amendment)
Regulations, 2015 and Central Electricity Regulatory
Commission (Deviation Settlement Mechanism and related
matters) (Second Amendment) Regulations, 2015 as amended
from time to time.”
Previous and next
Questions people ask
Is regulation 9 of Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 still in force?
No repeal of Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 is recorded.