Regulation 12, Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017: Capital Cost
Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 - Regulation 12
Text of regulation 12
Capital Cost
12. Capital Cost—The norms for the Capital cost as specified in these
Regulations shall be inclusive of all capital work including plant and
machinery, civil work, erection and commissioning, financing and interest
during construction, and evacuation infrastructure up to inter-connection
point.
Provided that for project specific tariff determination, the generating
company shall submit the break-up of capital cost items along with its petition
in the manner specified under Regulation 8.
13. Debt Equity Ratio
(1) For generic tariff to be determined based on suo-motu proceeding,
the debt equity ratio shall be 70:30.
(2) For Project specific tariff, the following provisions shall apply:-
If the equity actually deployed is more than 30% of the capital cost,
equity in excess of 30% shall be treated as normative loan.
Provided that where equity actually deployed is less than 30% of the
capital cost, the actual equity shall be considered for determination of tariff:
Provided further that the equity invested in foreign currency shall be
designated in Indian rupees on the date of each investment.
Previous and next
Questions people ask
Is regulation 12 of Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 still in force?
No repeal of Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 is recorded.