Regulation 15, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017: Project specific levellised tariff
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 - Regulation 15
Text of regulation 15
Project specific levellised tariff
15. Project specific levellised tariff.—(1) Where the parties to a power purchase
agreement
2
[for a project] have mutually agreed, in such power purchase agreement for which
joint petition is filed before the Commission on or after commencement of these
Regulations, and is thereafter approved by the Commission, and executed thereafter by the
parties, opted for a project specific levellised tariff, the Commission shall determine such
tariff taking into consideration—
(i) prudent capital cost as may be admitted by the Commission duly keeping in
view normative capital cost under these Regulations, the cost approved in the
Detailed Project Report, the actual expenditure incurred as per auditor’
scertificate, the information furnished under regulation 19:
Provided that in case of delay in execution of the project, the
Commission shall consider the time over run cost as follows—
(a) where the delay is due to factors entirely attributable to the renewable
energy generator, the entire cost shall be borne by the renewable energy
generator;
(b) where the delay is due to force majeure, the Commission may allow the
net additional cost incurred on this account to the renewable energy
generator; and
(c) in a situation not covered under clauses (a) and (b), the Commission may
allow the additional cost, not exceeding 50% of the net additional cost
incurred due to time overrun:
Provided further that the renewable energy generator shall be deemed
to have subscribed to the requisite insurance policies covering the risks
during construction stage and also to have stipulated provisions for the
liquidated damages in the contracts relating to the construction of the project,
awarded by him, as per the prudent practices, and accordingly, in case of any
time and cost over runs, the Commission shall not allow any amount which is
or would have been recoverable by him on account of such deemed
provisions for Insurance and liquidated damages:
1
Added proviso vide Not. No. HPERC/428 dated 11
th
November, 2019, published in R.H.P. dated 18
th
November, 2019 at p. 7983-7995.
2
Subs. for the words “, for a project, other than the small hydro projects covered in sub-regulation
(1) of regulation 11” vide Not. No. HPERC/428 dated 28
th
January, 2019, published in R.H.P. dated 30
th
January, 2019 at p. 7835-7843.
18 Compendium of HPERC Regulations, March 2021
Provided further that any cost pertaining to allotment of the project,
including upfront premium and any other amount charged by the State
Government while granting extension or capacity enhancement or/and any
liquidateddamages/penalty
1
[imposed by the State Government in accordance
with the implementation agreement and/or those imposed by the licensee in
accordance with the power purchase agreement] will not form part of the
capital cost;
(ii) the normative annual capacity utilisation factor specified under Chapter-V
2
[,
or in case of small hydro projects upto 100 kW capacity fixed in the orders
issued under Regulation 14] of these Regulations for the small hydro projects
or the annual capacity utilisation factor worked out on the basis of data for
75% dependable year as per the approved/concurred Detailed Project Report,
whichever is higher;
(iii) the technology specific parameters as specified for the small hydro projects in
Chapter V
3
[, or in case of small hydro projects upto 100 kW capacity fixed
in the orders issued under Regulation 14,] of these Regulations and as may be
laid down by the Commission for the other renewable technologies as per
regulation 18;
(iv) financial norms/principles, in relation to the renewable energy technologies
based power projects, as specified in Chapter-IV of these Regulations, which
shall except for capital cost, be considered as ceiling norms; and
(v) the ceiling tariff (s), if any, fixed by the Commission for the respective
categories of the renewable energy technologies based power projects:
Provided that if the licensee and renewable energy generator have, in
accordance with regulations 32 or 32-A or 32-B and 42, agreed in the power
purchase agreement executed by them after prior approval of the Commission
to any improved norms, including operation and maintenance norms, which
smay lead to overall reduction in the levellised tariff, such improved norms
shall apply for determination of the project specific levellised tariff.
(2)Where the project specific levellised tariff, as determined under sub-regulations
(1)—
(i) exceeds 105% of the corresponding generic levellised tariff, duly adjusted for
permissible rate of free power if any, determined by the Commission in
relation to the control period or other provisions under which the power
purchase agreement was approved by the Commission, the distribution
licensee shall have the option to exit from the power purchase agreement,
provided that this option shall not be available to the distribution licensee if
1
Sub. for words “imposed in accordance with the power purchase agreement executed with the
licensee,” vide not. No. HPERC/428 dated 11
th
November, 2019, published in R.H.P. dated 18
th
November,
2019 at p. 7983-7995.
2
Added the words, signs and figures vide Not. No. HPERC/428 dated 20
th
November, 2020, published
in R.H.P. dated 24
th
November, 2020 at p. 5421-5423.
3
Added the words, signs and figures vide Not. No. HPERC/428 dated 20
th
November, 2020, published
in R.H.P. dated 24
th
November, 2020 at p. 5421-5423.
Compendium of HPERC Regulations, March 2021 19
the renewable energy generator agrees to keep the tariff within the aforesaid
limit;
(ii) is less than 95% of the corresponding generic levellised tariff, duly adjusted
for permissible rate of free power if any, determined by the Commission in
relation to the control period or other provisions under which the power
purchase agreement was approved by the Commission, the renewable energy
generator shall have the option to exit from the power purchase agreement,
provided that this option shall not be available to the renewable energy
generator if the distribution licensee agrees to keep the tariff within the
aforesaid limit.
(3) Where the exit option is exercised by any party under sub-regulation (2) and
the interconnection point for that project falls under the control of the distribution licensee, it
shall, on request from the renewable energy generator, provide open access through its
system to the renewable energy generator as per the open access regulations.
Previous and next
Questions people ask
Is regulation 15 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.