Regulation 14, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017: Generic levellised tariff

The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 - Regulation 14

Text of regulation 14

Generic levellised tariff

[14. Generic levellised tariff.—(1) The Commission, from time to time and at such intervals as it may consider appropriate in line with the duration of respective control periods as per Regulation 9, shall— (i) specify the financial norms to be used for determination of tariffs for various RE technologies; (ii) specify the technological specific parameters for the small hydro projects; and (iii) fix the technological specific parameters for the various RE technologies, other than SHPs, in accordance with Regulation 18: Provided that the financial parameters for all the renewable energy technologies and the technological specific parameters for the SHPs already specified under PART-I 1 Sub. vide Not. No. HPERC/428 dated 28 th January, 2019, published in R.H.P. dated 30 th January, 2019 at p. 7835-7843 and before its substitution read as under- “14. Generic levellised tariff.—(1) The Commission shall for each category, mentioned in regulation 33 of small hydro projects, other than those covered in sub-regulation (1) of regulation 11, determine separate generic levellised tariffs and associated terms and conditions, within 90 days from the date of commencement of these Regulations by taking into account the norms specified under these Regulations: Provided that in case of renewable energy technologies, other than small hydro projects, the Commission may fix the generic levellised tariffs in accordance with the regulation 18. (2) The tariff being normative, any shortfall or gain due to performance or any other reasons is to be borne/retained, as the case may be, by the renewable energy generator and no true up of any parameter, including additional capitalisation for whatsoever reasons, shall be taken up during the validity of the tariff except for the specific provisions in these Regulations. (3) Save as provided under sub-regulations (1) of regulation 11, where the parties have, as per the power purchase agreements executed by them, opted for generic levellised tariff or the same is otherwise applicable under regulation 16, the generic levellised tariff determined in relation to the control period under sub-regulations (1) shall be applicable for all the projects of that category for which the power purchase agreements are approved by the Commission in that control period.” 16 Compendium of HPERC Regulations, March 2021 of Chapter-IV and PART-I of Chapter-V respectively, shall remain in force upto 30 th September, 2019: Provided further that the technological specific parameters already fixed by the Commission for Solar PV technology in respect of the financial years 2017-18 and 2018-19 shall also continue to be in force till the expiry of the respective periods for which the same were fixed. (2) The Commission shall, within 90 days from the date on which the norms in relation to the respective control periods are notified/fixed under these regulations, determine separate generic levellised tariffs and associated terms and conditions, for each category of small hydro projects, as mentioned in regulation 33 or 33-A or 33-B, by taking into account the norms specified under these Regulations for the respective control periods: 1 [Provided that for Small Hydro Projects upto and including 100kW, the Commission may determine the Generic Levellised Tariff for the balance period of the 3rd Control period ending on 30-09-2023 by taking into account the financial parameters specified for the RE technologies as per Chapter-IV and the technology specific parameters as may be fixed by it in the tariff determination Order in a manner as it may find appropriate:] Provided 2 [further] that in case of renewable energy technologies, other than small hydro projects, the Commission may fix the generic levellised tariffs in accordance with the Regulation 18: Provided further that the generic levellised tariffs already determined for the SHPs, in relation to the first control period under these Regulations, shall remain in force upto 30th September, 2019: Provided further that the generic levellised tariffs determined, for the solar PV technology in respect of the financial years 2017-18 and 2018-19 shall also remain in force until the expiry of the respective periods for which the same had been fixed. (3) The tariff being normative, any shortfall or gain due to performance or any other reasons is to be borne/retained, as the case may be, by the renewable energy generator and no true up of any parameter, including additional capitalisation for whatsoever reasons, shall be taken up during the validity of the tariff except for the specific provisions in these Regulations. (4) Where the parties have, as per the power purchase agreements executed by them, opted for generic levellised tariff or the same is otherwise applicable under regulation 16, the generic levellised tariff determined in relation to the control period under sub-regulation (2) shall be applicable for all the projects of that category for which the power purchase agreements are approved by the Commission under the provisions applicable for that control period.] 1 [Provided that the generic levellised tariff determined, or to be determined, by the Commission in accordance with the provisions of the RE Tariff Regulations/practice 1 Added first proviso vide Not. No. HPERC/428 dated 20 th November, 2020, published in R.H.P. dated 24 th November,, 2020 at p. 5421-5423. 2 Added the word vide Not. No. HPERC/428 dated 20 th November, 2020, published in R.H.P. dated 24 th November, 2020 at p. 5421-5423. Compendium of HPERC Regulations, March 2021 17 followed by it in relation to such control period or any other period, not forming the part of any control period, as the case may be, may be considered appropriate by the Commission in accordance with under the clause (a), or clause (aa), as the case may be, of the subregulation (1) of regulation 13 of these regulations, shall be applicable in the following cases, namely:— (i) cases covered under the proviso to clause (b) of sub-regulation (1) of regulation 16 of these regulations; or (ii) where any specific provisions have been made in the PPA approved by the Commission pursuant to clauses (a) or clause (aa), alongwith the provisions thereto, as the case may be, under sub-regulation (1) of regulation 13 of these regulations.]

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017

Questions people ask

Is regulation 14 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.