Text of regulation 16

Tariff for residual period after sale/purchase under REC mechanism

16. Tariff for residual period after sale/purchase under REC mechanism.— (1) In cases where, after sale/purchase of net saleable energy to/by the licensee as per the power purchase agreement approved by the Commission, under REC mechanism in the 1 [mutually agreed initial period(s) starting from the date of commencement of operation of the project] or even if the project has not commenced its operation during such initial period(s), the net saleable energy for the residual period of the useful life of the project is to be sold to the distribution licensee under long term power purchase agreement, the tariff for sale/purchase of net saleable energy during such residual period shall, save as provided in sub-regulations (2) and (3), be regulated as under:— (a) If the first power purchase agreement for sale/purchase of power under REC mechanism from a small hydro projects was executed by the parties and/or approved by the Commission before the commencement of these Regulations,the provisions of Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012, shall be applicable irrespective of the fact whether the project has, or has not, commenced its operation, in the same manner as if the power purchase agreement for the residual life of the project would have been approved prior to commencement of these Regulations; (b) Save as provided in succeeding clause (c), if the joint petition for the approval of first power purchase agreement for sale/purchase of power to/by the licensee under REC mechanism from a small hydro project, 2 [xxx] is filed before the Commission on or after the commencement of these Regulations and is approved by the Commission thereafter, the generic levellised tariff, as determined 3 [by the Commission for the relevant category of small hydro projects, in relation to the control period in which such joint petition for approval of the first PPA under REC mechanism for the SHP 1 Sub. for the word “mutually agreed initial period(s)” vide Not. No. HPERC/428 dated 11th November, 2019, published in R.H.P. dated 18th November, 2019 at p. 7983-7995. 2 Ommitted for the word “other than the small hydro projects covered in sub-regulation(1) of regulation 11” vide Not. No. HPERC/428 dated 28th January, 2019, published in R.H.P. dated 30th January, 2019 at p. 7835-7843. 3 Sub. for the words “by the Commission for the relevant category of small hydro projects under these Regulations,” vide Not. No. HPERC/428 dated 11th November, 2019, published in R.H.P. dated 18th November, 2019 at p. 7983-7995. 20 Compendium of HPERC Regulations, March 2021 is filed or the control period in which the renewable energy generator commenced operation at his project, whichever is earlier, under these regulations] as per regulation 14 and regulations 20 and 21 to 39 or 21-A to 39-AA or 21-B to 39-BB, and 41 shall be applicable; 1 [Provided that if, in relation to a SHP, all of the following milestones, namely.— (i) submission of the joint petition for approval of the first PPA under REC mechanism; and (ii) signing of the first PPA under REC mechanism; and (iii) commencement of operation of the SHP; are achieved on or after the first day of October 2019 and no joint petition for approval of PPA for sale/purchase of power for the residual useful life of the project has been filed before the Commission prior to the said date (i.e. 1-10-2019), the Commission may, upon receipt of joint petition for sale/purchase of power for the residual useful life of the SHP, allow the generic levellised tariff determined by it for such control period, or any other past period, as it may consider appropriate in accordance with the clause (aa) read with the provisos thereto, of sub-regulation (1) of regulation 13 of these regulations; and] (c) In case of small hydro projects, 2 [xxx] where the project had commenced its operation, prior to the commencement of these Regulations, the provisions of Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 shall be applicable even if the joint petition for approval of the first power purchase agreement for sale/purchase of power under REC mechanism from such small hydro projects is filed before the Commission on or after the commencement of these Regulations; (d) In case of projects based on renewable energy technologies, other than small hydro projects, the terms and conditions as may be incorporated by the Commission, to address such situations, in the terms and conditions to be fixed in accordance with regulation 18 shall be applicable. (2) Save as provided in sub-regulation (3), in cases where any specific conditions in relation to the rate/tariff applicable for the residual period, referred to in subregulation (1), have been stipulated while approving the power purchase agreement under REC mechanism, such conditions shall also be applicable. 3 [xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx] (3) If the circumstances so warrant, the Commission may, even after the commencement of these regulations, on the merit of a case, approve the rate/tariff prevailing in any of the earlier time frames prior to the commencement of Himachal Pradesh Electricity 1 Proviso added for vide Not. No. HPERC/428 dated 11th November, 2019, published in R.H.P. dated 18th November, 2019 at p. 7983-7995. 2 Ommitted for the words and figure “covered under-subregulation(1) of regulation 11” for vide Not. No. HPERC/428 dated 28th January, 2019, published in R.H.P. dated 30th January, 2019 at p. 7835-7843. 3 Corrigendum vide Not. No. HPERC/428 dated 28th November, 2020 published in R.H.P. dated 1st December, 2020 at p. 5512-5513. and before the omitted proviso read as under- “Provided further that the SHP developer shall, before executing the long term agreement for sale of power to the licensee for the residual period, have to discharge his obligations, if any, under the power purchase agreement approved and/or signed for the relevant period under REC mechanism.” Compendium of HPERC Regulations, March 2021 21 Regulatory Commission (Power Procurement from Renewable Sources and Cogeneration by Distribution Licensee), Regulations, 2007 or the commencement of Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012 or these Regulations, as the case may be, for sale/purchase of the net saleable energy during the residual period referred to in sub- regulation(1).

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017

Questions people ask

Is regulation 16 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.