Regulation 13, Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017: Conversion of single point connection to individual connection
Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 - Regulation 13
Text of regulation 13
Conversion of single point connection to individual connection
13. Conversion of single point connection to individual connection:-
(1) The concerned developer or registered association opting for Conversion of Single Point Connection to
Individual Connection shall submit to the Licensee, a certified copy of the resolution regarding the
surrender of existing Single Point Delivery connection. In such cases, the procedure specified for full
conversion at Regulation 14 shall apply.
(2) In case, applications are received by the Licensee from individual consumers for direct supply of
electricity, the Licensee shall undertake a joint survey with the concerned developer or registered
association within 15 (fifteen) days of the date of receipt of the first application for direct supply. During
the survey, the Licensee shall explore the possibility of additional applicants who may like to opt for
direct supply through a written consent for proper planning and to provide the supply.
(3) In case, after conducting joint survey, it is found that the number of members of the society, opting for
direct supply from Licensee is 2/3rd or more of the total number of members of the society, the complete
society shall be converted for taking direct supply, and the procedure specified for full conversion at
Regulation 14 shall apply.
(4) In case, after conducting joint survey, it is found that the number of members of the society opting for
direct supply is less than 2/3rd of the total number of members of the society, the procedure specified for
partial conversion at Regulation 15 shall apply.
(5) Notwithstanding the above, no further applications for direct supply of power shall be entertained from
such members who did not opt for direct supply during the joint survey mentioned as above, for the next 5
(five) years from the date of energisation of other applicants,. This condition shall be clearly mentioned
in the survey form.
(6) The Licensee shall seek and the developer or the registered association, as the case may be, shall provide
the list of all the beneficiary members of the single point connection.
(7) The developer or the registered association shall provide access to the premises to the Licensee or its
authorized representatives for the purpose of any activity related to conversion of single point connection
72 DELHI GAZETTE : EXTRAORDINARY PART III]
into individual connection and other services such as maintenance, inspection of the network, reading of
the meters etc.
Previous and next
Questions people ask
Is regulation 13 of Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 still in force?
No repeal of Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 is recorded.