Regulation 11, Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017: New Electricity Connection
Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 - Regulation 11
Text of regulation 11
New Electricity Connection
11. New Electricity Connection:-
The Licensee shall process the application for new connection, within the time frame as specified in these
Regulations
(1) Submission of application along with all documents:-
(i) The Applicant shall make application for new connection to the Licensee in the form notified in
the Commission’s Orders:
Provided that a non-refundable registration cum processing fee as notified in the Commission’s
Orders shall be levied on the applicant applying connection at Extra High Tension or High Tension
voltage level.
(ii) The applicant can also make application for new connection online on the website of Licensee:
Provided that the applications for new connection for 50 kVA and above, unless any other lower
value as may be notified by the Commission from time to time, shall be submitted through online
system only.
(iii) If the Applicant wishes to provide his own meter of approved specifications, he shall explicitly
inform the same to the Licensee at the time of making the application.
(iv) The Licensee shall indicate all the deficiencies in the application form to the applicant in one go
only and shall not raise any new deficiency subsequently.
(v) In case the Licensee fails to intimate the applicant about any deficiencies in his application on the
spot or within the stipulated 2 (two) days in case of online application, as the case may be, the
application shall be deemed to have been accepted by the Licensee on the date of receipt of the
application.
66 DELHI GAZETTE : EXTRAORDINARY PART III]
(vi) In case the applicant fails to remove such defects or fails to inform the Licensee about removal of
deficiencies within 30 (thirty) days from the date of receipt of intimation of deficiencies, the
application shall stand lapsed and the applicant will have to apply afresh.
(vii) The application shall be considered to be accepted only on removal of deficiencies as indicated
under this Regulation.
(2) Field Inspection:-
(i) In case the application form is complete, the Licensee shall, at the time of receipt of application
form, stipulate a date and time for inspection of applicant’s premises in mutual consultation with
the applicant, giving a written acknowledgement.
(ii) The date of inspection shall be scheduled within 2 (two) days from the date of acceptance of the
application:
Provided that if the applicant wishes to have a different date and time for field inspection, which is
beyond the stipulated date & time, the excess time taken by the applicant shall neither be
considered for computation of total time taken for release of connection nor for the purpose of
compensation:
Provided further that if the applicant wishes, he can get the inspection scheduled on a holiday
for the Licensee, on payment of an inspection fee as notified in the Commission’s Orders.
(iii) The Licensee shall conduct field inspection of the premises in the presence of the applicant or his
representative on the appointed date and time.
(iv) The Licensee shall not sanction the load, if upon inspection, the Licensee finds that;
a. the information as furnished in the application is at variance to the actual position, or
b. the installation is defective or
c. the energisation would be in violation of any provision of the Act, Electricity Rules,
Regulations or any other requirement, if so specified or prescribed by the Commission or
Authority under any of their Regulations or Orders.
(v) The Licensee shall give intimation to the applicant on the spot in writing about the
defects/deficiencies, if any, observed during the field inspection.
(vi) The applicant shall ensure that all defects/deficiencies are removed within 30 (thirty) days from
receipt of intimation of defects/ deficiencies.
(vii) On receipt of information from the applicant about removal of defects/deficiencies, the Licensee
shall intimate the applicant about date for re-inspection of the premises of the applicant which
shall not be later than 2 (two) days of receipt of information from the applicant about removal of
defects/deficiencies.
(viii) In case the applicant fails to remove such defects/deficiencies or fails to inform the Licensee about
removal of defects/deficiencies within 30 days from the date of receipt of intimation of
defects/deficiencies, the application shall stand lapsed and the applicant will have to apply afresh:
Provided that the Licensee may grant additional time to the applicant for completion of works, in
case the applicant submits a written request for the same, within 30 (thirty) days from the date of
receipt of intimation of defects/deficiencies.
[PART III DELHI GAZETTE : EXTRAORDINARY 67
(ix) In case the Licensee fails to carry out field inspection/re-inspection within 2 (two) days from the
date of acceptance of application or from the date of receipt of intimation of removal of site
defects/deficiencies, the load applied for connection shall be deemed to have been sanctioned
after 2 (two) days from the date of acceptance of the application or the date of receipt of
information for removal of defects/deficiencies, as the case may be.
(3) Load Sanction and Demand Note:-
(i) Save as otherwise provided in the Act or these Regulations, the Licensee shall sanction the load as
requested by the applicant.
(ii) The Licensee shall raise the demand note to the applicant, within 2 (two) days of the field
inspection subject to rectification of defects/deficiencies, for applicable charges, giving its breakup
under the heads such as Service Line cum Development (SLD) charges, Security deposit, security
towards pre-payment meter, road restoration charges, reconnection charges, etc. after giving due
adjustment for the registration cum processing fee collected, if any, at the time of submission of
the application:
Provided that in cases where consumer contribution is required for augmentation of network, the
demand note shall be raised by the licensee within 10 (ten) days of the field inspection.
(iii) The applicant shall make payment within 2 (two) days of the receipt of the demand note.
(iv) In case the applicant finds difficulty in making the payment within 2(two) days, the applicant may
request the Licensee, in writing, for an extension of time for a maximum period of 15 (fifteen)
days.
(v) The Licensee shall be under obligation to energise the connection on receipt of full payment
against the demand note subject to the condition that the time extended under sub-regulation (iv)
above shall not be counted in working out the total time taken for energisation of connection by
Licensee nor the consumer shall be entitled to seek any compensation for such extended period.
(4) Energisation of Connection:-
(i) Where connection is to be provided from existing distribution system in electrified areas:-
a. In cases where road cutting permission or right of way is not required, the Licensee shall
energize the connection within 1(one) day from the date of receipt of full payment.
b. In cases where road cutting permission or right of way is required, the Licensee shall
energize the connection within 9(nine) days from the date of receipt of full payment:
Provided that if delay in road cutting permission or right of way is beyond 2(two) days from
the date of submission of request by the distribution licensee, such delay shall not be
counted in working out the total time taken for energisation of connection by Licensee nor
the consumer shall be entitled to seek any compensation for such period.
c. The total time for providing connection from existing distribution system shall not exceed
the time schedule specified under these Regulations.
d. For the purpose of illustration, the total time taken for release of connection in electrified
area from the existing distribution system, where there is no deficiency in the application or
during field inspection, shall be as under:
Sl. No. Description Time period
(i) Acceptance of Application Zero date
(ii) Field Inspection Within 2 days of Acceptance of
Application
68 DELHI GAZETTE : EXTRAORDINARY PART III]
(iii) Load Sanction and demand note Within 2 days of Field Inspection
(iv) Payment of demand note Within 2 days of raising demand
note
(v) Release of connection, where no RoW or road cutting
permission is required
Within 1 day of receipt of payment
(vi) Total time for release of connection where no RoW or road
cutting permission is required
Within 7 days of acceptance of
application
Total time for release of connection where RoW or road
cutting permission is required
Within 15 days of acceptance of
application
(ii) Connection where system augmentation is required in electrified areas:-
a. The Licensee shall not deny new connection as long as the peak load including the load
capacity of the new connection on the applicable distribution transformer falls within and
up to 90% of the rated capacity of the transformer.
b. The Licensee shall take appropriate action for augmentation of the capacity, as soon as the
peak load on the existing applicable distribution transformer(s) reaches about 70% of its
rated capacity.
c. Subject to sub-clause (a) above, if giving of new connection requires augmentation of
distribution system, the Licensee shall inform the applicant about the approximate time
frame by which the applied load can be energized. Such time frame shall not exceed the
time schedule specified as under:
(i) Electrified Areas (where
extension of line upto five
poles is required)
Within 15 days from the date of
receipt of full payment against
demand note.
(ii) Electrified Areas (Where
extension of lines or
augmentation of
Distribution
Transformation
capacity,where peak load
of transformer has
reached 90% of its rated
capacity)
Within 2 months from the date of
receipt of full payment against
demand note.
(iii) Electrified Areas (Where
new Distribution
Transformer is required)
Within 4 months from the date of
receipt of payment against demand
note
(iv) Electrified Areas (Where
existing 11 KV network
needs to be augmented)
Within 6 months from the date of
receipt of payment against demand
note
(v) Electrified Areas (Where
existing 66/33 kV grid
sub-station needs to be
augmented)
Within 8 months from the date of
receipt of payment against demand
note
Provided that the Licensee may approach the Commission for extension of time specified in
specific cases, where magnitude of electrification works is such that it requires more time, duly
furnishing the details in support of such request for extension.
(iii) Connection in Un-electrified areas:-
a. The licensee shall upload the updated details of un-electrified areas as on 31st March of every year
alongwith the geographical map clearly indicating the boundaries of such areas under its licensed
area of supply by the end of April of that year:
[PART III DELHI GAZETTE : EXTRAORDINARY 69
Provided that the Licensee for the first time shall upload the details of un-electrified areas as on
31.7.2017 alongwith the geographical map clearly indicating the boundaries of such areas under its
licensed area of supply:
Provided further that the details of un-electrified areas as on 31.7.2017 shall be uploaded by the
Licensee on its website by 31.8.2017 and shall remain on its website unless reviewed by the
Commission.
b. The Licensee shall submit in the Business Plan, details of un-electrified areas under its area of
supply and proposal for its electrification during the control period.
c. The Licensee shall submit alongwith the filing of tariff petition, the detailed plan for electrification
of these areas duly taking into account the number of pending applications for service connections,
potential for load growth etc.
d. The Licensee shall ensure that all relevant laws of the land are complied with.
e. The Licensee shall complete the electrification of un-electrified areas and release the connection
within the time schedule specified as under:
(i) Where connection from nearby
existing network is possible
Within 4 months from the date of receipt of
approval from the Commission, wherever
required, subject to:
(i) receipt of service line cum development
charges under Regulation 21 from the
developer or the applicant as the case may
be; and
(ii) availability of right of way & land,
wherever required.
(ii) Where new network is to be laid or
grid station needs to be established
Within 12 months from the date of receipt
of approval from the Commission, wherever
required, subject to:
(i) receipt of service line cum development
charges under Regulation 21 from the
developer or the applicant as the case may
be; and
(ii) availability of right of way & land,
wherever required.
Provided that on request of the licensee, the Commission may allow extension of time for
electrification works in specific cases, based on the justification and the details furnished by the
Licensee:
Provided further that once electrification of such area is completed, the timelines for energisation
of connection shall be in accordance with the provisions of these Regulations for energisation of
connection in electrified areas.
(iv) All connections to be energized using bus-bars:-
a. If more than one connection in a premises/complex are energized using a single service line
or a cable, all such connections shall be energized using the bus-bars only without looping
with other meters.
b. Any existing connection, provided through loop connections, energized prior to 18th April,
2007 (date of notification of Delhi Electricity Supply Code and Performance Standards
Regulations, 2007), shall be rectified and re-energized using bus-bars within 6 (six) months
from the date of applicability of these Regulations.
70 DELHI GAZETTE : EXTRAORDINARY PART III]
c. The consumer shall have the right to check / verify that the neutral of its meter is connected
directly from the bus bar and not in any other manner.
d. Subject to Sub-Clause (b) above, if it is found that the consumer's meter is energized
through neutral looping and not directly from the bus bar, the Licensee shall be liable to pay
compensation as specified in Schedule-I of the Regulations.
(v) Compensation for delay in energizing connection:-
a. In case the Licensee fails to provide the connection to an applicant within the prescribed
time lines, the Licensee shall be liable to pay the applicant, compensation as specified in
Schedule-I of the Regulations.
b. For determination of compensation, the time taken for release of connection shall not be
considered on account of the following:-
(i) If at any stage, additional time period is sought by the applicant for reasons to be
recorded in writing; or
(ii) If the same is on account of reasons such as right of way, acquisition of land, delay
in permission for road cutting etc., or occurrence of any force majeure event, over
which Licensee has no control and the reasons for the delay are communicated to the
applicant within the period specified for energisation; or
(iii) If additional time is allowed by the Commission for completion of work.
c. In case the Licensee fails to provide connection to an applicant after raising a demand note,
the Licensee shall pay the applicant, compensation as per Schedule-I of the Regulations:
Provided that the Licensee shall also refund the amount deposited by the applicant against
the demand note along with interest as applicable in case of Security Deposit, within 30
(thirty) days from the date load is not sanctioned:
Provided further that if the connection could not be provided after issuance of the demand
note for the reasons attributable to the applicant, no compensation shall be payable and the
Licensee shall refund the amount deposited by the applicant against the demand note.
(vi) Electricity Connection based on occupancy as per Regulation 10 (3)(v & vi):-
a. The Licensee shall provide the electricity connection to such applicant only through pre-
payment meter by charging a refundable security also as notified in the Commission’s
Orders towards pre-payment meter:
Provided that if the load demanded by the applicant is more than 45kW, the Licensee may
provide the connection through post-paid meter:
b. The electricity connection shall be valid during the currency of said lease agreement or
mutually extended period of lease by the occupier and the owner.
c. The Licensee shall disconnect the electricity connection on expiry of lease agreement, unless
extended.
d. In case the proof of occupancy is rent receipt alongwith undertaking that the rent receipt is
signed by the owner or his authorized representative, the electricity connection shall be
disconnected on the request of the owner or his authorized representative:
Provided that notice of at least one month period shall be given by the owner or his
authorized representative to the Licensee and the occupier .
e. At the time of disconnection, if the pre-payment meter is not defective/damaged, the
Licensee shall refund the security collected towards pre-payment meter alongwith the
balance within 7 (seven) days of disconnection through demand draft or electronic clearance
system.
12. Single point supply:
(1) The Licensee shall, if so requested, give single point supply, to the premises with multiple
consumers/beneficiaries such as:
(i) Multi-storey buildings.
[PART III DELHI GAZETTE : EXTRAORDINARY 71
(ii) Residential complex developed by any developer.
(iii) Residential-cum-commercial complex developed by a developer and approved by an appropriate
authority
(iv) Group Housing Societies
(v) Commercial or Industrial Complex.
(vi) Residential Complex constructed by any employer for his employees:
Provided that the provisions of this Regulation shall not in any way affect the right of a person
residing/occupying any part/unit in such premises, sold or leased by the developer, to demand
supply of electricity directly from the Licensee of the area.
(2) Supply shall be provided by the developer or registered association to the individual beneficiaries and for
common service by installing separate meters.
(3) The developer or registered association shall collect the charges as per applicable Tariff Order and the
cost of energy from individual beneficiaries and shall remit the charges for the entire electricity availed at
such single point of supply as per the bill within such time as indicated in the bill.
(4) The tariff charged from individual beneficiaries shall be as per applicable tariff for relevant category as
notified in Tariff Order.
(5) Providing of connection to individual beneficiaries in such premises with multiple consumers and sharing
of expenses of consumption of electricity as per the above provisions shall not be construed as
unauthorized extension of supply or resale of energy.
(6) The maintenance of internal distribution network and providing services to individual beneficiaries shall
be the responsibility of the developer or registered association, as the case may be.
(Explanation: - Registered Association means the Residents Welfare Association or any other similar
body registered with Registrar, Co-operatives Societies, Delhi/ Societies Act, 1860 which deals with the
management of various common facilities/services within the complex.)
Previous and next
Questions people ask
Is regulation 11 of Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 still in force?
No repeal of Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 is recorded.