Regulation 7, Joint Electricity Regulatory Commission” (Distribution Code) Regulations, 2010.: Distribution lines
Joint Electricity Regulatory Commission” (Distribution Code) Regulations, 2010. - Regulation 7
Text of regulation 7
Distribution lines
7. Distribution lines: - All the 33 kV, 22 kV and 11 kV lines at Connection Points /
Interface Points shall be provided with a minimum of over current and earth fault
relays as follows:
a) Plain radial feeders: Non-directional time lag over current and earth fault relays
with suitable settings to obtain discrimination between adjacent relay settings.
b) Parallel/ring feeders: Directional time lag over current and earth fault relay.
6.6 FIRE PROTECTION:
All adequate precaution shall be taken and protection shall be provided against fire
hazards to all apparatus in the System conforming to the relevant Indian Standard
Specifications and/or provisions of under other relevant rules as amended from
time to time.
29 | P a g e
Chapter - 7
CROSS BOUNDARY SAFETY CODE
7.1 OBJECTIVE:
The objective of this section is to achieve an agreement on the principles of safety
when working across a control boundary between the Distribution Licensee and the
Users.
This chapter specifies the requirements for safe working practices for maintenance
of equipment associated with cross boundary operations and lays down the
procedure to be followed when the work is carried out on electrical equipment
connected to another User's System. User may mean another Licensee so that this
Code applies for safety across the boundary between two Licensees also, by
substituting “another Licensee” for User.
7.2 CONTROL PERSONS AND THEIR RESPONSIBILITY:
The Distribution Licensee and all the Users (comprising Generation Companies,
Transmission Licensees and consumers having load above 1MW or dedicated line)
shall nominate suitably authorized and technically qualified persons to be
responsible for the co-ordination of safety across their boundary. These persons
shall be referred to as "Control Persons".
7.3 PROCEDURE:
1. The Distribution Licensee shall issue a list of Control Persons with their names,
designations, addresses and telephone numbers, to all the Users having direct
control boundary with him. This list shall be updated promptly whenever there is
any change of name, designation or telephone number of any Control Person
named in the list.
2. All the Users such as mentioned in 8.3.1 having a direct control boundary with the
Distribution Licensee shall issue a similar list of their Control Persons to the
Licensee. This list shall be updated promptly whenever there is any change of
name, designation or telephone number of any Control Person named in the list.
3. Whenever any work across a cross boundary is to be carried out by the User or the
Distribution Licensee, the Control Person of the User or the Licensee as the case
may be, who has to carry out the work, shall directly contact his counterpart. Code
words shall be agreed to at the time of work to ensure correct identification of both
the parties. Contact between Control Persons shall normally be made by direct
telephone.
4. If the work extends beyond one shift, the Control Person shall hand over charge to
31 | P a g e
the relief Control Person and fully brief him on the nature of work and the code
words in the operation.
5. The Control Persons shall co-operate to establish and maintain the precautions
necessary to be taken for carrying out the required work in a safe manner. Both the
established isolation and the established earth shall be kept in the locked positions
wherever such facilities exist, and these shall be clearly identified.
6. The Control Person in charge of the work shall satisfy himself that all the safety
precautions to be taken are established before commencing the work. He should
issue the safety documentation to the working party to allow the work to
commence.
7. After the completion of the work, the Control Person in charge of the work being
carried out should satisfy himself that the safety precautions taken are no longer
required, and shall make a direct contact with his counterpart Control Person and
request removal of the safety precautions. The equipment shall be declared as
suitable for return to service only after confirmation of removal of all the safety
precautions, by direct communication, using the code word contact between the
two Control Persons, and the return of agreed safety documentation from the
working party.
8. The Distribution Licensee shall develop an agreed written procedure for Cross
Boundary Safety and continuously update the same.
9. Any dispute concerning Cross Boundary Safety shall be resolved at the level of
transmission licencee, if transmission licencee is not a party. In case where
transmission licencee is a party, the dispute shall be referred to the Commission for
resolution of the dispute.
7.4 SPECIAL CONSIDERATIONS:
1. All the equipment on Cross Boundary Circuits, which may be used for the purpose
of safety co-ordination and establishment of isolation and earthing, shall be
permanently and clearly marked with an identification number or name being
unique to the particular sub-station. These equipments shall be regularly inspected
and maintained in accordance with the manufacturer's specifications.
2. Each Control Person shall maintain a legibly written safety log, in chronological
order, of all operations and messages relating to the safety co-ordination sent and
received by him. All these safety logs shall be retained for a period of not less than
ten years.
3. As far as possible each of the Distribution Licensees shall maintain an updated map
of his system pertaining to the area fed by each substation. Otherwise the schematic
diagram of the system for 11kV and above shall be maintained and exhibited in the
concerned area offices of the Distribution Licensee.
32 | P a g e
Chapter - 8
INCIDENT/ACCIDENT REPORTING
8.1 OBJECTIVE
This Chapter covers procedure of major incident / accident reporting (which occur
in Distribution System) by User to Licensee and Licensee to User and
Commission.
8.2 MAJOR INCIDENT OR ACCIDENT REPORTING:
1. The Distribution Licensee shall send a preliminary report to Commission all the
significant Incidents in the Licensee's Area of Supply, which results in interruption
to service, substantial damage to equipment or loss of life or significant injury to
human beings within one week of its occurrence followed by a detailed report
within one month.
2. The Distribution Licensee and the Users shall establish a format and procedure for
exchange of information.
3. The Users shall furnish information to the Distribution Licensee regarding any
major incident occurring in their Systems promptly.
8.3 REPORTING PROCEDURE
1. All reportable incidents occurring in the lines and equipments of 11 kV and above
substations shall be promptly reported orally by the Licensee whose equipment has
experienced the incident, to all other significantly affected Users identified by the
Distribution Licensee and the Transmission Licensee. The reporting Distribution
Licensee should submit a written report to the Transmission Licensee within one
hour of such oral report. If the reporting incident is of major nature, the written
report shall be submitted within two hours duly followed by a comprehensive
report within 48 hours of the submission of the initial written report. In other cases,
the reporting Distribution Licensee shall submit a report within five working days
to the Transmission Licensee.
2. The Transmission Licensee shall call for a report from any Distribution Licensee
on any reportable incident affecting other Users and particularly in case such User
whose equipment might have been a source of the reportable incident does not
report the same. However this shall not relieve any User from the obligation to
report Events in accordance with Rules framed under relevant provision made
under Electricity Act, 2003. The format for such a report shall be as per the
approval of the Distribution Code Review Panel and shall typically contain the
following:
a) Location of the incident,
b) Date and time of the incident,
c) Plant or Equipment involved,
33 | P a g e
d) Supplies interrupted and the duration wherever applicable,
e) Amount of Generation lost, wherever applicable,
f) System Parameters before and after the incident, (Voltage, Frequency,
Load, Generation, etc.)
g) Network configuration before the incident,
h) Relay indications and performance of protection,
i) Brief description of the incident,
j) Estimated time of return to service,
k) Any other relevant information,
l) Recommendations for future improvement,
m) Name and designation of the reporting person.
3. The report shall contain sufficient detail to describe the event to enable the
recipient to assess the implications and risks arising out of the same. The recipient
may ask for clarifications and additional information wherever necessary and it is
obligatory that the reporting User shall put his best efforts and provide all the
necessary and reasonable information.
4. In case of a request by either party, the oral report shall be written down by the
sender and dictated by way of a telephone message or sent by Fax/e-mail to the
recipient. In case of an emergency the report can be given only orally and followed
by written confirmation.
5. Reporting of accidents shall be in accordance with the rules framed under relevant
provision made under Electricity Act, 2003 or other applicable rules. Till such
rules are made, the Distribution Licensee shall follow reporting of accidents as
mentioned in Power System Safety Standard (Indian Electricity Rule 1956) as per
Annexure 4 to these regulations.
34 | P a g e
ATTACHMENT - 1
DISTRIBUTION SYSTEM PLANNING AND SECURITY STANDARD
1. OBJECTIVE
1 The Distribution System Planning and Security Standard specifies the guidelines for
planning methodology of the Distribution System. The scope of this standard covers:
(a) Quality of power supply
(b) Load forecast
(c) Planning procedure.
(d) Service area of a distribution network.
(e) Planning standards.
(f) Reliability analysis.
(g) Standardisation of design of distribution transformer
(h) Standardisation of substation layouts
(i) Reactive Compensation
(j) Service Mains
(k) Metering Cubicles
(l) Security Standards
2. QUALITY OF POWER SUPPLY
1. Frequency: The rated frequency shall be 50 Hz. All the constituents of the Power
System shall make all possible efforts to ensure that the grid frequency remains
within the bandwidth of 49.0 -50.5 Hz.
2. Voltage: - The voltage at any point of the system under normal operating
conditions shall not depart from the declared voltage by more than the values
specified under IS Specification.
3. Harmonic content: - As per IEEE recommendations, the total harmonic content in
the supply voltage for sensitive loads shall not exceed 5 percent, with any single
harmonic content not exceeding 3 percent. The respective User responsible for
generating harmonics and affect the distribution system shall be responsible for
corrective action.
3. LOAD FORECAST:
1 The Distribution Licensee shall prepare a rolling short - term load forecast annually
for a period of five years in his Area of Supply duly estimating the probable load
growth and the consumption pattern of the Consumers. The forecast thus made
shall be updated every year depending on the actual load that has come in that year
and the changes in assumption, if any, required for the next years.
2 Preliminary Load Estimation/Assessment:
1. Domestic and Commercial Loads: The consumption in domestic and commercial
sectors shall be estimated on the basis of the number of Consumers and their
35 | P a g e
specific consumption. The past growth rate in the number of Consumers in the
area shall be studied. In cases where power shortages have been experienced in
the recent past, the growth rate to be adopted shall take into consideration the
appropriate demand making due allowance in the growth rate to account for
increased tempo of household electrification envisaged in the future. The higher
level of electrification planned in the area should be kept in view. Energy
consumption per Consumer shall be estimated after studying the past trends and
taking into account the anticipated improvements in the standard of living.
(a) Public Lighting and Water Works: The estimates of electricity consumption in
public lighting and water works shall be based on the average consumption per
kilowatt of connected load, projected on the basis of trends, keeping in mind the
likely increase in public lighting and water supply facilities. The number of
hours of operation shall be estimated taking into account the past trends and the
power cuts if any effected in the area.
(b) Agricultural Loads: The power requirement for irrigation pump sets shall be
based on the program of energisation of pump sets in the plan period, available
resources and the ultimate ground water potential. The average capacity of pump
sets shall be worked out considering the mid-year figures for connected load and
the number of pump sets. The consumption per IP set per year shall be estimated
by means of representative sample studies till all the IP sets are metered.
(c) Industrial Loads: The power requirements for industrial sector shall be
estimated under following three categories, viz.
(a) L.T. Industries;
(b) H.T. Industries with a demand of less than 1 MW;
(c) H.T. Industries with a demand of 1 MW & above.
The consumption in category (a) & (b) shall be on the basis of historical data
duly considering the developments in future. In case of category (c), projection
shall be made separately for each industrial unit on the basis of the information
furnished by the industrialists and the Department of Industries.
3 Non-industrial Bulk Supply: The available data regarding the consumption of bulk
supply to non-industrial Consumers such as research establishments, port trusts,
military engineering services, supply to power projects etc., and the probable future
developments in these areas, shall be considered for the forecast.
4. Other Loads: For other loads, the projections shall be based on the best Judgment.
4. LOAD FORECAST PROCEDURE
1. Load forecasting methods using the above data and relevant indices by adopting
one of the suitable methods applicable to specific locations and prevailing
conditions shall be adopted.
36 | P a g e
2. In addition to the above, the effects of demand side management, requirement of
power for pending applications, the increase in demand due to improvement in the
operating frequency close to 50 Hz shall also be estimated. The Distribution
Licensee shall work out Peak Demand for each of the succeeding five years
relating to Connection Point/ Interface Point with the Transmission System as well
as the annual Energy Demand and Peak Demand for each of the succeeding five
years for overall Area of Supply on the basis of Load forecast. However, if the
Distribution Licensee receive power at a number of Connection Points / Interface
Points in a compact area, which are interconnected in a ring, then such Distribution
Licensee shall forward the overall short term Demand forecast at each Connection
Point / Interface Point with the variation or tolerance as mutually discussed and
agreed upon with the Transmission Utility or SLDC.
3. The diversity factor of each category of Consumers fed in the Area of Supply shall
be worked out by installation of load survey meters at selected typical locations. A
record of such data shall be maintained and continuously updated. The short-term
load forecast for a period of five years, based on these data shall be prepared.
5. PLANNING PROCEDURE
The Distribution System shall be planned and developed in such a way that the
system should be capable of catering the requirement of all categories of Consumers
with a safe, reliable, economical and quality supply of electricity as indicated in
clause 2.0 of this section. However the Consumer shall extend full support to the
Distribution Licensee to enable the Distribution Licensee for quality supply of
electricity. The Distribution System shall conform to the statutory requirements of
all the relevant code, standards and acts in force.
6. PLANNING STANDARDS
6.1 Standardization of Sizes and Ratings: Adequate provision for future load
development shall be made while selecting the sizes of power conductors and
rating of distribution transformers. The sizes of power conductors, insulators,
lightning arresters, transformers, switchgear, etc. used in the Distribution System
shall be standardized with the objective of reducing inventory and standard
specifications shall be prepared.
Design Criteria for Distribution Lines
1. Radial system of distribution can be adopted in rural areas and as far as possible
loop system with provision for feeding from at least one alternate source shall
be adopted in urban areas.
2. The HT and LT distribution lines shall be any of the following types according
to the necessity at the required area.
(a) Over-head line with bare conductors;
(b) Over-head line with Aerial Bunched Cables;
(c) Under-ground Cables.
37 | P a g e
3. In thickly populated cities, in areas having heavy traffic densities, underground
cable installation shall be considered to the extent possible. Wherever a number
of trees are encountered, either in residential locations or in gardens and forests,
over-headlines with aerial bunched cables shall be adopted. In other places over-
headlines with bare conductors shall be adopted. The following standards shall
be adopted for planning and design purposes:
(a) The design and construction of over-headlines with bare conductors shall be
generally in accordance with IS 5613 Part I, sections 1 and 2.
(b) Vertical configuration of conductors for LT distribution lines, to prevent
accidental short circuit due to galloping of conductors, shall preferably be
adopted in rural areas since the spans are large in such areas.
(c) The maximum length of LT and HT lines shall be maintained within the
prescribed limit so as a safe and quality power may be delivered.
(d) The design and construction of over-headlines with aerial bunched cables shall
be generally in accordance with REC Specifications 32 and IS 14255.
(e) The design and construction of under-ground cables shall be generally in
accordance with IS 1255.
4. The line supports can be of steel, wood, RCC or PCC. The RCC and PCC poles
are preferred over the other two considering their cost and longer life. The
choice of the size of conductor for a line shall be made based on the following
criteria:
(a) Power to be transmitted and the techno-economic studies conducted for
selecting the size of conductor according to the cost of loss of power and the
interest and depreciation charges on the cost of the conductor thus selected;
(b) Length of Line;
(c) Line Voltage;
(d) Permissible voltage regulation;
(e) Mechanical strength;
(f) In coastal areas and other areas where severe corrosion is expected due to
heavy rainfall and/or salinity in atmosphere and theft prone areas, appropriate
conductors only shall be used.
6.2 Standardisation of Design and Rating of Distribution Transformers
1. The design and rating of distribution transformers shall be standardised. As an
initial step, the various technical parameters required for the design shall be
incorporated in the specifications based on the experience on performance
gained among the various designs so far adopted. Later, standard designs of the
transformers and their detailed construction drawings shall be evolved based on
the performance of these transformers. These shall be adopted for future
procurement. This also ensures the inter-changeability of components of similar
transformers manufactured by any manufacturer.
2. A good quality assurance plan shall be aimed at the following:
38 | P a g e
(a) Good quality of raw materials;
(b) Quality control during manufacturing and routine tests;
(c) Acceptance tests at the time of taking delivery;
(d) Inspection and tests on transformers received at stores on random sampling;
(e) Thorough test on one transformer in a lot selected at random. The transformer
should be completely dismantled. The qualities of core, coil, insulation etc are
physically inspected and samples of insulation and other components used etc.,
are tested.
(f) Ensuring performance guarantee for all distribution transformers for a
minimum period of 3 years.
6.3 Standardisation of Sub-Station Layouts
The Distribution Licensee shall develop standard layouts following relevant
standards, manuals and provisions of Electricity Act, 2003. The Licensee shall
also adopt latest technology as well as feedback from the experience gained.
6.4 Reactive Compensation
1 Shunt capacitors un-switched/switched type, shall be installed at the appropriate
places in the Distribution System for power factor improvement, maintaining
satisfactory voltage profile and reduction of sub-transmission and Distribution
losses. The size and location of the capacitor installations shall be determined
using an appropriate program, with reliable field data. Suitable precautionary
measures, such as automatic switching etc., shall be adopted to avoid over
voltages at light load periods.
2 Optimization studies of shunt compensation shall be conducted by the
Distribution Licensee to determine the most appropriate sizes and locations for
shunt capacitor installations.
6.5 Service Area of a Distribution Network
1. The service area of a distribution network is an area in which the load is supplied
by a substation by one or more number of feeders, as required. The distribution
network fed from the distribution transformers and the substations from which
the 11 kV feeders emanate shall be initially planned as independent networks
within their respective service area. Further, wherever possible, provision shall
be made for interconnection with adjacent networks and/or substations for an
alternate supply in case of failure. The design of distribution lines shall
incorporate features to enable their augmentation in future, with minimum
interruption to power supply. The existing right of way shall be fully exploited.
2. The Distribution Licensee shall take suitable measures, sufficiently in advance,
to augment the capacity of the feeders in the event the voltage regulation limit is
exceeded within the area.
3. Appropriate software to compute the design of the distribution network shall be
39 | P a g e
used to obtain lowest possible energy losses for different loading conditions for
the following:
(a) The location and the capacity of the distribution transformers;
(b) Routing of LV and HV networks;
(c) The sizes of conductors;
(d) The ratio of the lengths of HT and LT distribution lines for the new lines
planned shall be optimized and the existing Distribution System shall be
modified in a phased manner to reduce the distribution losses.
(e) The voltage regulation limits for all loading conditions.
6.6 Service Mains
The service mains to Consumers shall be laid in accordance with relevant REC
Construction Standards for 230 V single phase and 400 V three phase supply and
shall conform to the provisions of Relevant Rules under Electricity Act, 2003.
6.7 Metering Cubicles
1. The metering for 230 V single-phase supply shall be provided on a suitable
board, located in such a place protected from sun and rain and shall be in a
convenient position for taking readings. The terminals of the meter shall be made
tamper-proof and sealed. For 400 Volts three phase supply, the meters and
associated metering equipment including connections shall be enclosed in a
suitable tamper-proof box. The tamper-proof box shall be of sufficient strength
and design with locking and sealing devices and shall have adequate provision
for heat dissipation with the required electrical clearances. The design shall
permit readings to be taken without access to the meter or its connections.
2. For HT Consumers the meters, maximum demand indicators, and secondary
connections, shall be housed in a separate compartment and other secondary
apparatus such as instrument transformers and connections required shall be
housed in a separate metering compartment, which shall be locked / sealed to
prevent tampering.
3. The HT metering cubicle shall be suitable for cable entry on both sides or at
least on one side. No fuses are permitted in the secondary circuits of the
instrument transformers. The metering cubicle shall be painted with suitable
epoxy paint for installation in coastal areas and other areas experiencing heavy
rainfall. The instrument transformers shall be of fixed ratio and shall not have
any taps. The primary current rating of the current transformers shall match with
the normal full load current and the saturation point of the core shall be higher
than the maximum current that may occur due to simultaneous full load
operation of all the connected equipment and machinery.
40 | P a g e
4. For EHT Consumers, the secondary terminals of the instrument transformers
shall be locked and sealed and the secondary wires brought out in a suitable GI
conduit pipe upto the metering panel. There shall be no joints in the conduit
pipes. The meters shall be as close to the instrument transformers as possible
and in no case shall exceed ten (10) meters. The metering panel shall be housed
in a weatherproof and tamperproof box and sealed.
7. RELIABILITY ANALYSIS
1. The planning of the extension and improvement to a Distribution System shall
also take into consideration the improvement in reliability of power supply to
Consumers. The appropriate reliability indices of power supply in the area fed
by the Distribution System before and after the implementation of the extension
and improvement program shall be estimated. The planning of the distribution
system shall also take into consideration the improvement in reliability and
efforts should be made to collect the data in this regard.
2. The following factors, which affect reliability indices, shall be considered
subject to availability of data:
(a) Momentary incoming supply failures
(b) Momentary interruptions on 22 and 11 kV feeders
(c) Breakdown on LT feeders
(d) Prearranged shutdowns on lines and feeders
(e) Blowing out of distribution transformer fuses
(f) Individual fuse off calls
Previous and next
← Regulation 6Distribution SystemRegulation 8 →STANDING COMMITTEE FOR DESIGN, CONSTRUCTION AND MAINTENANCE PRACTICES
All provisions of Joint Electricity Regulatory Commission” (Distribution Code) Regulations, 2010.
Questions people ask
Is regulation 7 of Joint Electricity Regulatory Commission” (Distribution Code) Regulations, 2010. still in force?
No repeal of Joint Electricity Regulatory Commission” (Distribution Code) Regulations, 2010. is recorded.