Text of rule 114A

Allotment of land for setting up of Solar Monitoring Station

114A. Allotment of land for setting up of Solar Monitoring Station.- (1) Notwithstanding anything contained in these rules, the Solar Power Producer may apply for allotment of Government land in Form “AA” to the R.R.E.C. for setting up of solar monitoring station to carry out studies for formulation of the project. After receiving application, the R.R.R.C. may send it to the Collector with its recommendation. 12[(2) The Collector may, on recommendation of the R.R.E.C., allot Government land upto 100X100m for setting up of solor monitoring station on temporary basis for a maximum period of three years on payment market value of the land assessed on the basis of rates recommended by the DLC. (3) After completion of studies or three years from the date of temporary allotment of land, whichever is earlier, the solor monitoring station shall be dismantled by the Solor Power Produceror on his own cost and land shall be revert back to the State Government free from all encumbrances.]]

Previous and next

All provisions of Rajasthan Land Revenue (Allotment of Land for setting up of Power Plant based on Renewable Energy Sources) Rules, 2007

Questions people ask

Is rule 114A of Rajasthan Land Revenue (Allotment of Land for setting up of Power Plant based on Renewable Energy Sources) Rules, 2007 still in force?

No repeal of Rajasthan Land Revenue (Allotment of Land for setting up of Power Plant based on Renewable Energy Sources) Rules, 2007 is recorded.