Rule 2A, Rajasthan Land Revenue (Allotment of Land for setting up of Power Plant based on Renewable Energy Sources) Rules, 2007: Maximum area to be allotted
Rajasthan Land Revenue (Allotment of Land for setting up of Power Plant based on Renewable Energy Sources) Rules, 2007 - Rule 2A
Text of rule 2A
Maximum area to be allotted
10[2A. Maximum area to be allotted.- For setting up of renewable energy power plant, the
maximum area to be allotted shall be as under:-
S. No. Nature of power plant Maximum area to be
allotted
1.
Wind Farm/Wind Power Project
2.50 Hectare per MW
5a Substitited by Notification no. F9(90)Rev.6/2021/139, dated-24-08-2022.
5b Inserted by Notification No F.9(26) Rev-6/2024/16 dated 26-07-24.
6 Inserted by Notification dated 01-07-13.
7 Inserted by Notification no. F6(28)Rev.6/201401/9, dated-04-08-14.
8 Substituted by Notification dated 01-07-13.
9 Added by Notification dated 01-07-13.
10 Added by Notification dated 01-07-13 & Substituted by Notification no. F6(28)Rev.6/2014/part/4,
dated-22- 02-17 & again substituted by notification dated 18-01-21 and again again substituted by
notification dated 26.07.2024
2.
Solar Power Plant using-
(i) Solar Photo Voltaic (SPV) on
Crystalline Technology
(ii) Solar Photo Voltaic (SPV) on
Crystalline Technology with
tracker
(iii) Solar Photo Voltaic (SPV) on thin
film/Amorphous Technology with
or without tracker
(iv) Solar Thermal [Concentrate Solar
Power (CSP)] Parabolic
Trough/Tower/ other technology
with and without storage
2.0 Hectare per MW
2.5 Hectare per MW
2.5 Hectare per MW
2.25 Hectare per MW
(a) upto Plant Load Factor
(PLF) of 21% 3.0
Hectare per MW.
(b) for every 1%increase in
Plant Load Factor (PLF),
0.15 Hectare per MW
additional land shall be
alloted .
3.
4.
10d[5.
Biomass Power Plant
Wind Solar Hybrid Power Plant using,-
(i) Solar Photo Voltaic (SPV) on
Crystalline Technology
(ii) Solar Photo Voltaic (SPV) on
Crystalline Technology with tracker
(iii) Solar Photo Voltaic (SPV) on thin
film/Amorphous Technology with or without
tracker
(i) Compressed Bio Gas Plant
(ii) Bio Coal Plant
(iii) Bio-Ethanol Plant
2.5 Hectare per MW
2.50 Hectare per MW
2.50 Hectare per MW
3.00 Hectare per MW
for 1MTPD capacity 1
acre for plant and 2.5
acre for feedstock storage
and for other capacity, in
proportionate to this
criteria
for 100 MTPD capacity 2
acre and for other
capacity, in proportionate
to this criteria
for 100 kilo litre capacity
1.5 acre and for other
capacity, in proportionate
to this criteria.]
Provided that in case of requirement of extra land beyond above
maximum limit, not more than 10% of the maximum limit variation may be
allowed for allotment on recommendation by the RREC on the basis of
technical grounds, as per Grid Code Government Rules, Guidelines, Land
locations and Layout etc.]
3 Application for allotment: - (1) The Power Producer shall select appropriate
site of land available in the area where [the Renewable Energy Power Plant/RE
Park] is proposed to be set up.
(2) The application for allotment of Government land for setting up Renewable
Energy Power Plant/RE Park shall be submitted by the Power Producer to the
Rajasthan Renewable Energy Corporation.
(3) Deleted by Notification Dated 22.2.2017.
(4) The application shall be proposed and recommended by the RREC to the
District Collector, if the applicant fulfils all the requirements for allotment of
land as per the Policy for promoting generation of electricity through non-
conventional energy sources declared by the Energy Department, Government
of Rajasthan, from time to time.
(5) If the Collector after considering the application is satisfied that the proposals
are complete in all respects, he shall send the application with his comments to
the State Government.
4 Period of allotment and terms and conditions of lease:- (1) After receiving
the proposal from the District Collector under sub- rule (5) of rule 3, allotment of
land for setting up of Renewable Energy Power Plant/RE Park may be made by
the State Government.
(2) Land for Renewable Energy Power Plant /RE Park shall be initially allotted
on lease hold basis for a period of 30 years from the date of allotment. The lease
may be renewed for a further period of 10 years:
10c (Provided further that in case of Repowering of the existing Wind
power Project, lease period of land may be extended, on recommendation of the
RREC for the useful life of the project i.e. upto 25 years form the date of
Repowering but is shall not be more than 20 years after the expiry of existing
lease period in any case.)
(3) On the expiry of lease period the land allotted under these rules shall revert
back free from all encumbrances to the State Government.
(4) The lease shall abide by all the terms and conditions prescribed in the lease
Deed.
(5) Energy Power Producer shall abide by all the terms and conditions of
allotment and directions issued by the State Government and R.R.E.C. from
time to time.
(6) The Lease holder shall have limited rights in the land allotted to him for the
purpose of setting up Renewable Energy Power Plant/RE Park.
(7) The Lease-holder in the lease period, may assign his interest to any financial
institution for the purposes of taking loan for establishing or developing the
Renewable Energy Power Plant/RE Park, such assignment shall be subject to first
charge of the Government.
Previous and next
Questions people ask
Is rule 2A of Rajasthan Land Revenue (Allotment of Land for setting up of Power Plant based on Renewable Energy Sources) Rules, 2007 still in force?
No repeal of Rajasthan Land Revenue (Allotment of Land for setting up of Power Plant based on Renewable Energy Sources) Rules, 2007 is recorded.