54. Declared voltage of supply to consumer. - Except with the written consent
of the consumer or with the previous sanction of the State Government a supplier
shall not permit the voltage at the point of commencement of supply as defined
under rule 58 to vary from the declared voltage-
(i) In the case of low or medium voltage, by more than 6 per cent, or;
(ii) In the case of high voltage, by more than 6 per cent on the higher side or by
more than 9 per cent on the lower side, or;
(iii) In the case of extra-high voltage, by more than 10 per cent on the higher
side or by more than 12.5 per cent on the lower side.
55. Declared frequency of supply to consumer- Except with the written consent
of the consumer or with the previous sanction of the State Government a supplier
shall not permit the frequency of an alternating current supply to vary from the
declared frequency by more than 3 per cent.
56. Sealing of meters, and cut-outs-
(1) A supplier may affix one or more seals to any cut-out and to any meter,
maximum demand indicator, or other apparatus placed upon a consumer’s
premises in accordance with section 26, and no person other than the supplier
shall break any such seal.
(2) The consumer shall use all reasonable means in his power to ensure that
no such seal is broken otherwise than by the supplier.
(3) The word ‘supplier’ shall for the purpose of this rule include a State
Government when any meter, maximum demand indicator or other apparatus is
placed upon a consumer’s premises by such Government.
57. Meters, maximum demand indicators and other apparatus on consumer’s
premises-
(1) Any meter or maximum demand indicator or other apparatus placed upon a
consumer’s premises in accordance with section 26 shall be of appropriate
capacity and shall be deemed to be correct if its limits of error are within the limits
specified in the relevant Indian Standard Specification and where no such
specification exists, the limits of error do not exceed 3 per cent above or below
absolute accuracy at all loads in excess of one tenth of full load and up to full load.
1[Provided that for extra high voltage consumers the limit of error shall be 1 per
cent.]
(2) No meter shall register at no load.
(3) Every supplier shall provide and maintain in proper condition such suitable
apparatus as may be prescribed or approved by the Inspector for the examination,
testing and regulation of meters used or intended to be used in connection with the
supply of energy.
Provided that the supplier may with the approval of the Inspector and shall, if
required by the Inspector, enter into a joint arrangement with any other supplier for
the purpose aforesaid.
(4) Every supplier shall examine, test and regulate all meters, maximum
demand indicators and other apparatus for ascertaining the amount of energy
supplied before their first installation at the consumer’s premises and at such other
intervals as may be directed by the State Government in this behalf.
(5) Every supplier shall maintain a register of meters showing the date of the
last test, the error recorded at the time of the test, the limit of accuracy after
adjustment and final test, the date of installation, withdrawal, reinstallation, etc., for
the examination of the Inspector or his authorised representative.
2[(6) Where the supplier has failed to examine, test and regulate the meters and
keep records thereof as aforesaid, the Inspector may cause such meters to be
tested and sealed at the cost of the owner of the meters in case these are found
defective.]
1. Added by GSR 218, dt. 18.4.1995, w.e.f. 29.4.1995.
2. Added by GSR 844, dt. 31.7.1985, w.e.f. 7.9.1985.
1[58. Point of commencement of supply- The point of commencement of supply of
energy to a consumer shall be deemed to be the point at the incoming terminal of
the cut-outs installed by the consumer under rule 50.]
1. Subs. by GSR 45, dt. 1.1.1993, w.e.f 23.1.1993.
59. Precautions against failure of supply: Notice of failures-
(1) The layout of the electric supply lines of the supplier for the supply of
energy throughout his area of supply shall under normal working conditions be
sectionalised and so arranged, and provided with cut-outs or circuit-breakers so
located, as to restrict within reasonable limits the extent of the portion of the
system affected by any failure of supply.
(2) The, supplier shall take all reasonable precautions to avoid any accidental
interruptions of supply, and also to avoid danger to the public or to any employee
or authorised person when engaged on any operation during and in connection
with the installation, extension, replacement, repair and maintenance of any works.
(3) The supplier shall send to the Inspector 1[or any officer of a specified rank
and class appointed to assist the Inspector] notice of failure of supply of such kind
as the Inspector 1[or any officer of specified rank and class to assist the Inspector]
may from time to time require to be notified to him, and such notice shall be sent
by the earliest practicable post after the failure occurs or after the failure becomes
known to the supplier and shall be in such form and contain such particulars as
Inspector may from time to time specify
2[(4) For the purpose of testing or for any other purpose connected with the
efficient working of the undertaking, the supply of energy may be discontinued by
the supplier for such period as may be necessary, subject (except in cases of
emergency) to not less than 24 hours notice being given by the supplier to all
consumers likely to be affected by such discontinuance:
Provided that the supply of energy shall be discontinued during such hours as are
likely to interfere the least with the use of energy by consumers and the energy
shall not be discontinued if the Inspector so directs.]
1. Ins. by GSR 466, dt. 18.7.1991, w.e.f. 17.8.1991.
2. Subs. by GSR 732, dt. 18.6.1985, w.e.f. 3.8.1985.
CHAPTER VI
ELECTRIC SUPPLY LINES, SYSTEMS
AND APPARATUS FOR LOW AND
MEDIUM VOLTAGES
60. Test for resistance of insulation-
(1) Where any electric supply line for use at low or medium voltage has been
disconnected from a system for the purpose of addition, alteration or repair, such
electric supply line shall not be reconnected to the system until the supplier or the
owner has applied the test prescribed under rule 48.
(2) The provision of sub-rule (1) shall not apply to overhead lines except,
overhead insulated cables unless the Inspector otherwise directs in any particular
case.
61. Connection with earth-
(1) The following provisions shall apply to the connection with earth of systems
at low voltage in cases where the voltage normally exceeds 125 volts and of
systems at medium voltage: -
1[(a) Neutral conductor of a phase, 4 wire system and the middle conductor of a
2 phase, 3-wire system shall be earthed by not less than two separate and distinct
connections with a minimum of two different earth electrodes of such large number
as may be necessary to bring the earth resistance to a satisfactory value both at
the generating station and at the sub-station. The earth electrodes so provided,
may be interconnected to reduce earth resistance. It may also be earthed at one
or more points along the distribution system or service line in addition to any
connection with earth which may be at the consumer’s premises.]
(b) In the case of a system comprising electric supply lines having concentric
cables, the external conductor of such cables shall be earthed by two separate
and distinct connections with earth.
(c) The connection with earth may include a link by means of which the
connection may be temporarily interrupted for the purpose of testing or for locating
a fault.
(d) (i) In a direct current three wire system the middle conductor shall be
earthed at the generating station only, and the current from the middle conductor
to earth shall be continuously recorded by means of a recording ammeter, and if
any time the current exceeds one-thousandth part of the maximum supply-current
immediate steps shall be taken to improve the insulation of the system.
(ii) Where the middle conductor is earthed by means of a circuit breaker with a
resistance connected in parallel, the resistance shall not exceed 10 ohms and on
the opening of the circuit breaker, immediate steps shall be taken to improve the
insulation of the system, and the circuit-breaker shall be reclosed as soon as
possible.
(iii) The resistance shall be used only as a protection for the ammeter in case of
earths on the system and until such earths are removed. Immediate steps shall be
taken to locate and remove the earth.
(e) In the case of an alternating current system, there shall not be inserted in
the connected with earth any impedance (other than that required solely for the
operation of switch-gear of instruments), cut-out or circuit-breaker, and the result
of any test made to ascertain whether the current (if any) passing through the
connection with earth is normal shall be duly recorded by the supplier.
(f) No person shall make connection with earth by the aid of, nor shall be keep
it in contact with, any water main not belonging to him except with the consent of
the owner thereof and of the Inspector.
(g) Alternating current systems which are connected with earth as aforesaid
may be electrically interconnected.
Provided that each connection with earth is bonded to the metal sheathing and
metallic armouring (if any) of the electric supply lines concerned.
(2) The frame of every generator, stationary motor, portable motor, and the
metallic parts (not intended as conductors) of all transformers and any other
apparatus used for regulating or controlling energy and all medium voltage energy
consuming apparatus shall be earthed by the owner by two separate and distinct
connections with earth.
2[(3) All metal castings or metallic coverings containing or protecting any electric
supply-line or apparatus shall be connected with earth and shall be so joined and
connected across all junction boxes and other openings as to make good
mechanical and electrical connection throughout their whole length.
Provided that where the supply is at low voltage, this sub-rule shall not apply to
isolated wall tubes or to brackets, electroliers, switches, ceiling fans or other
fittings (other than portable hand lamps and portable and transportable apparatus)
unless provided with earth terminal and to class-II apparatus/ appliances.
Provided further that where the supply is at low voltage and where the installations
are either new or renovated all plug sockets shall be of the three-pin type, and the
third pin shall be permanently and efficiently earthed.
Explanation- The words “Class-II apparatus/appliance” will have the same
meaning as assigned to these words in the relevant ISS.]
3[(4) All earthing systems shall-
(a) Consist of equipotential bonding conductors capable of carrying the
prospective earth fault current and a group of pipe/rod/plate electrodes for
dissipating the current to the general mass of earth without exceeding the
allowable temperature limits as per relevant Indian Standards in order to maintain
all non-current carrying metal works reasonably at earth potential and to avoid
dangerous contact potentials being developed on such metal works;
(b) Limit earth resistance sufficiently low to permit adequate fault current for the
operation of protective devices in time and to reduce neutral shifting;
(c) Be mechanically strong, withstand corrosion and retain electrical continuity
during the life of the installation. All earthing systems shall be tested to ensure
efficient earthing, before the electric supply lines or apparatus are energised.]
(5) All earthing systems belonging to the supplier shall in addition, be tested for
resistance on dry day during the dry season not less than once every two years.
(6) A record of every earth test made and the result thereof shall be kept by the
supplier for a period of not less than two years after the day of testing and shall be
available to the Inspector or any officer appointed to assist the Inspector and
authorised under sub-rule (2) of rule 4A when required.
1. Subs. by GSR 1051, dt. 25.10.1985, w.e.f. 9.11.1985.
2. Subs. by GSR 256, dt. 28.2.1983, w.e.f 26.3.1983.
3. Subs. by GSR 358, dt. 30.4.1987, w.e.f. 9.7.1987.
1[61A. Earth leakage protective device- The supply of Energy to every electrical
installation other than low voltage installation below 5 KW and those low voltage
installations which do not attract provisions of section 30 of the Indian Electricity
Act, 1910, shall be controlled by an earth leakage protective device so as to
disconnect the supply instantly on the occurrence of earth fault or leakage of
current.
Provided that the above shall not apply to overhead supply lines having protective
devices which are effectively bonded to the neutral of supply transformers and
conforming to rule 91 of 1,E. Rules, 1956.]
1. Ins. by GSR 844, dt. 31.7.1985, w.e.f. 7.9.1985.
62. Systems at medium voltage- Where a medium voltage supply system is
employed, the voltage between earth and any conductor forming part of the same
system shall not, under normal conditions, exceed low voltage.
CHAPTER VII
ELECTRIC SUPPLY LINES, SYSTEMS
AND APPARATUS FOR HIGH AND
EXTRA-HIGH VOLTAGES
63. Approval by Inspector-
(1) Before making an application to the Inspector for permission 1[to commence
or recommence supply after an installation has been disconnected for one year
and above] at high or extra-high voltage to any person, the supplier shall ensure
that the high or extra-high voltage electric supply lines or apparatus belonging to
him are placed in position, properly joined and duly completed and examined. The
supply of energy shall not be commenced by the supplier unless and until the
Inspector is satisfied that the provisions of rules 65 to 69 both inclusive have been
complied with and the approval in writing of the Inspector have been obtained by
him.
Provided that the supplier may exercise the aforesaid electric supply lines or
apparatus for the purpose of tests specified in rule 65.
(2) The owner of any high or extra-high voltage installation shall, before making
application to the Inspector for approval of his installation or additions thereto, test
every high or ext.-a-high voltage circuit or additions thereto, other than an
overhead line, and satisfy himself that they withstand the application of the testing
voltage set out in sub-rule (1) of rule 65 and shall duly record the results of such
tests and forward them to the Inspector.
Provided that an Inspector may direct such owner to carry out such tests as he
deems necessary or, if he thinks fit, accept the manufacturer’s certified tests in
respect of any particular apparatus in place of the tests required by this sub-rule.
(3) The owner of any high or extra-high voltage installation who makes any
additions or alterations to his installation shall not connect to the supply his
apparatus or electric supply lines, comprising the said alterations or additions
unless and until such alterations or additions have been approved in writing by the
Inspector.
1. Subs. by GSR 256, dt. 28.2.1983, w.e.f. 26.3.1983.
64. Use of energy at high and extra-high voltage-
1[(1) The Inspector shall not authorise the supplier to commence supply or where
the supply has been discontinued for a period of one year and above, to
commence the supply at high or extra-high voltage to any consumer unless,]
(a) All conductors and apparatus situated on the premises of the consumer are
so placed as to be inaccessible except to an authorised person and all operations
in connection with the said conductors and apparatus are carried out by an
authorised person;
(b) The consumer has provided and agrees to maintain a separate building or a
locked weather-proof and fire-proof enclosure of agreed design and location, to
which the supplier at all times have access for the purpose of housing his
apparatus and metering equipment, or where the provision for a separate building
or enclosure is impracticable, the consumer has segregated the aforesaid
apparatus of the supplier from any other part of his own apparatus;
Provided that such segregation shall be by the provision of fire proof walls, if the
Inspector considers it to be necessary;
Provided further that in the case of an out-door installation consumer shall suitably
segregate the aforesaid apparatus belonging to the supplier from his own to the
satisfaction of the Inspector;
(c) All pole type sub-stations are constructed and maintained in accordance
with rule 69.
(2) The following provisions shall be observed where energy at high or extra-
high voltage is supplied, converted, transformed or used: -
2[(a) (i) Clearances as per Indian Standard Code shall be provided for
electrical apparatus so that sufficient space is available for easy operation and
maintenance without any hazard to the operating and maintenance personnel
working near the equipment and for ensuring adequate ventilation.
(ii) The following minimum clearances shall be maintained for bare conductors
or live parts of any apparatus in out-door substations, excluding overhead lines, of
HV and EHV installations: -
Voltage Class Ground clearance
(Metres)
Sectional
clearance (Metres)
Not exceeding
-do-
-do-
-do-
-do-
-do-
11KV
33KV
66KV
132KV
22OKV
40OKV
2.75
3.7
4.0
4.6
5.5
8.0
2.6
2.8
3.0
3.5
4.3
6.5]
(b) The windings of motors or other apparatus within reach from any position in
which a person may require to be shall be suitably protected so as to prevent
danger.
(c) Where transformer or transformers are used, suitable provision shall be
made, either by connecting with earth a point of the circuit at the lower voltage or
otherwise, to guard against danger by reason of the said circuit becoming
accidentally charged above its normal voltage by leakage from or contact with the
circuit at the higher voltage.
(d) A sub-station or a switch station with apparatus having more than 2000
litres of oil shall not 3[***] be located in the basement where proper oil draining
arrangement cannot be provided.
(e) Where a sub-station or a switch station with apparatus having more than
2000 litres of oil is installed, whether indoor or out-doors, the following measures
shall be taken, namely: -
(i) The baffle walls 4[of 4 hour fire rating] shall be provided between the
apparatus in the following cases: -
(A) Single phase banks in the switch-yards of generating stations and sub-
stations;
(B) On the consumer premises;
(C) Where adequate clearance between the units is not available.
(ii) Provisions shall be made for suitable oil soakpit and where use of more
than 9000 litres of oil in any one oil tank, receptacle or chamber is involved,
provision shall be made for the draining away or removal of any oil which may leak
or escape from the tanks receptacles or chambers containing the same, special
precautions shall be taken to prevent the spread of any fire resulting from the
ignition of the oil from any cause and adequate provision shall be made for
extinguishing any fire which may occur. Spare oil shall not be stored in an such
sub-station or switch station.
5[(f) (i) Without prejudice to the above measures, adequate fire protection
arrangement shall be provided for quenching the fire in the apparatus;
(ii) Where it is necessary to locate the sub-station/switch station in the
basement following measures shall be taken:-
(a) The room shall necessarily be in the first basement at the periphery of the
basement;
(b) The entrances to the room shall be provided with fire resisting doors of 2
hours fire rating. A curb (sill) of a suitable height shall be provided at the entrance
in order to prevent the flow of oil from a ruptured transformer into other parts of the
basement. Direct access to the transformer room shall be provided from outside.
(c) The transformer shall be protected by an automatic high velocity water
spray system or by carbon dioxide or BCF (Bromochlorodifeuromethane) or BTM
(Bromotrifluromethane) fixed installation system; and
(iii) Oil filled transformers installed indoors shall not be on any floor above the
ground or below the first basement.]
(g) Cable trenches inside the sub-stations and switch stations containing
cables shall be filled with sand, pebbles or similar non-inflammable materials or
completely cover with non-inflammable slabs.
(h) Unless the conditions are such that all the conductors and apparatus may
be made dead at the same time for the purpose of cleaning or for other work, the
said conductors and apparatus shall be so arranged that these may be made dead
in sections, and that work on any such section may be carried on by an authorised
person without danger.
(i) Only persons authorised under sub-rule (1) of rule 3, shall carry out the
work on live lines and apparatus.]
6[(3) All EHV apparatus shall be protected against lightning as well as against
switching over voltages. The equipment used for protection and switching shall be
adequately coordinated with the protected apparatus to ensure safe operation as
well as to maintain the stability of the inter-connected units of the power system.]
1. Subs. by CSR 843, dt. 23.7.1983, w.e.f. 7.9.1985
2. Subs. by GSR 358, dt. 30.4.1987, w.e.f. 9.5.1987.
3. The word ‘ordinarily’ omitted by GSR 358, dt. 30.4.1987, w.e.f. 9.5.1987.
4. Ins. by GSR 358, dt. 30.4.1987, w.e.f. 9.5.1987.
5. Subs. by GSR 358, dt. 30.4.1987, w.e.f. 9.5.1987.
6. Ins. by GSR 336, dt. 20.3.1988, w.e.f. 23.4.1988.
Previous and next
← Rule 46Periodical inspection and testing of consumer’s installationRule 64A →Additional provisions for use of energy at high and extra-high voltage- The following additional provisions shall be observed where energy at high or extra- high voltage is supplied, converted, transferred or used, namely
Questions people ask
Is rule 54 of THE INDIAN ELECTRICITY RULES, 1956 still in force?
No repeal of the INDIAN ELECTRICITY RULES, 1956 is recorded.