FORMAT - 59
FORMAT - 59
Periodicity- Monthly
Submission-by 20th day
2.0 Design parameters for the Station:
HEAT RATE DATA OF COMBINED CYCLE GAS TURBINE POWER STATIONS FOR MONTH ………….YEAR…………20…………..20
1.0 General:
i) Station Name: -------------------------------------------------------------
ii) Station Capacity: (No. of units with size)
NAME OF THERMAL POWER STATION :
UNIT NO. DATE SPM (mg/Nm3) SO
2
(mg/Nm3) NO
X
(mg/Nm3)
(AS PER CPCB NOTIFICATION No. S.O.384E dt. 11.4.94)
LOCATION-I LOCATION-II LOCATION-III
(POWER STATION) (COLONY) (OUTSIDE THE
PLANT WITHIN 20
KM.)
SPM (µg/m3)*
SO2 (µg/m3)*
NOX (µg/m3)*
RPM (µg/m3)*
LEAD (µg/m3)*
CO (mg/m3)**
* 24 HOURS WEIGHTED AVERAGE
** 8 HOURS WEIGHTED AVERAGE
I. STACK EMISSIONS (UNIT WISE AND MONTH WISE)
II.
AMBIENT AIR QUALITY (MONTH WISE)
188 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4]
Previous and next
Questions people ask
Is form AT - 59 of Central Electricity Authority (Furnishing of Statistics, Returns & Information) Regulations, 2007 still in force?
No repeal of Central Electricity Authority (Furnishing of Statistics, Returns & Information) Regulations, 2007 is recorded.