Rule 36, Atomic Energy (Factories) Rules, 1996: PRESSURE VESSELS OR PLANTS
Atomic Energy (Factories) Rules, 1996 - Rule 36
Text of rule 36
PRESSURE VESSELS OR PLANTS
36. PRESSURE VESSELS OR PLANTS.-
(1) Interpretation.-In this rule-
(a) "design pressure" means the maximum pressure that a pressure vessel or plant is
designed to withstand safely when operating normally;
(b) "maximum permissible working pressure" means the maximum pressure at which
a pressure vessel or plant is permitted to be operated or used under this rule and is
determined by the technical requirement of the process;
(c) "plant" means a system of piping that is connected to a pressure vessel and is used
to contain a gas, vapour or liquid under pressure greater than the atmospheric
pressure, and includes the pressure vessel;
Atomic Energy Factory Rules, 1996
39
Rule 36
(d) "pressure vessel" means a vessel that may be used for containing, storing,
distributing, transferring, distilling, processing or otherwise handling any gas,
vapour or liquid under pressure greater than the atmospheric pressure and includes
any pipeline fitting or other equipment attached thereto or used in connection
therewith; and
(e) "competent person" means a person as defined in Sr.No. 5. of schedule to rule 31.
(2) Exceptions.-Nothing in this rule shall apply to -
(a) vessels made of ferrous materials having an internal operating pressure not
exceeding 1 kilogram per square centimeter;
(b) steam boilers, steam and feed pipes and their fittings coming under the purview of
the Indian Boilers Act, 1923;
(c) metal bottles or cylinders used for storage or transport of compressed gases or
liquefied or dissolved gases under pressure covered by the Gas Cylinder Rules,
1981 framed under the Indian Explosives Act, 1884;
(d) vessels in which internal pressure is due solely to the static head of liquid;
(e) vessels with a nominal water capacity not exceeding 500 litres connected in a
water-pumping system containing air that is compressed to serve as a cushion;
(f) vessels for nuclear energy application shall be covered by rules framed by
Competent Authority;
(g) refrigeration plant having a capacity of 3 tons or less of refrigeration in 24 hours;
and
(h) working cylinders of steam engines or prime movers, feed pumps and steam traps;
turbine casings; compressor cylinders; steam separators or dryers; steam strainers;
steam de-super- heaters; oil separators; air receivers for fire sprinkler installations;
air receivers of monotype machines provided the maximum working pressure of
the air receiver does not exceed 130 kPa (1.33 kg/sq.cm) and the capacity 85
litres; air receivers of electrical circuit breakers; air receivers of electrical relays;
air vessels on pumps, pipe coils, accessories of instruments and appliances such as
cylinders and piston assemblies used for operating relays and interlocking type of
guards; vessels with liquids subjected to static head only; and hydraulically
operating cylinders other than any cylinder communicating with an air loaded
accumulator.
Atomic Energy Factory Rules, 1996
40
Rule 36
(3) Design and construction.-Every pressure vessel or plant used in a factory -
(a) shall be properly designed on sound engineering practice;
(b) shall be of good construction, sound material, adequate strength and free from any
patent defects; and
(c) shall be properly maintained in a safe working condition:
Provided that the pressure vessel or plant in respect of the design and construction of
which there is an Indian standard or a standard of the country of manufacture or any other
law or regulation in force, shall be designed and constructed in accordance with the said
standards, law or regulation, as the case may be, and a certificate thereof shall be obtained
from the manufacturer or from the competent person which shall be kept and produced on
demand by an Inspector.
(4) Safety devices.-Every pressure vessel shall be fitted with-
(a) a suitable safety valve or other effective pressure relieving device of adequate
capacity to ensure that the maximum permissible working pressure of the pressure
vessel shall not be exceeded. It shall be set to operate at a pressure not exceeding
the maximum permissible working pressure and when more than one protective
device is provided, only one of the devices need be set to operate at the maximum
permissible working pressure and the additional device shall be set to discharge at
a pressure not more than 5 percent in excess of the maximum permissible working
pressure;
(b) a suitable pressure gauge with a dial range not less than 1.5 times the maximum
permissible working pressure, easily visible and designed to show at all times the
correct internal pressure and marked with a prominent red mark at the maximum
permissible working pressure of the pressure vessel;
(c) a suitable nipple and globe valve connected for the exclusive purpose of attaching
a test pressure gauge for checking the accuracy of the pressure gauge referred to in
clause (b) of this sub-rule;
(d) a suitable stop valve or valves by which the pressure vessel may be isolated from
other pressure vessels or plant or source of supply of pressure. Such a stop valve
or valves shall be located as close to the pressure vessel as possible and shall be
easily accessible;
Atomic Energy Factory Rules, 1996
41
Rule 36
(e) a suitable drain cock or valve at the lowest part of the pressure vessel for the
discharge of the liquid or other substances that may collect in the pressure vessel;
and
(f) every pressure gauge, stop valve, nipple and globe valve, shall be mounted at a
height not more than 1.5 m from the working level:
Provided that it shall be sufficient for the purpose of this sub-rule if the safety
valve or pressure relieving device, the pressure gauge and the stop valve are
mounted on a pipeline immediately adjacent to the pressure vessel and where
there is a range of two or more similar pressure vessels served by the same
pressure lead, only one set of such mountings need be fitted on the pressure lead
immediately adjacent to the range of pressure vessels, provided they cannot be
isolated.
(5) Pressure reducing devices.-
(a) Every pressure vessel which is designed for a working pressure less than the
pressure at the source of supply. or less than the pressure which can be obtained in
the pipe connecting the pressure vessel with any other source of supply, shall be
fitted with a suitable pressure reducing valve or other suitable automatic device to
prevent the maximum permissible working pressure of the pressure vessel being
exceeded.
(b) To further protect the pressure vessel in the event of failure of the reducing valve
or device, at least one safety valve having a capacity sufficient to release all the
steam, vapour or gas without undue pressure rise as determined by the pressure at
the source of supply and the size of the pipe connecting the source of supply, shall
be fitted on the low pressure side of the reducing valve.
(c) In case of a jacketed vessel in which heat is transmitted by means of steam or
other media in the jacket causing pressure rise in the vessel, the heat input in the
jacket shall be so controlled by a suitable device as not to allow the safe working
pressure of the vessel being exceeded.
6. Pressure vessel or plant being taken into use.-
(a) No new pressure vessel or plant shall be taken into use in a factory after coming
into force of this rule unless it has been hydrostatically tested by a competent
person at a pressure at least 1.3 times the design pressure, and no pressure vessel
or plant which has been previously used or has remained isolated or idle for a
period exceeding 6 months or which has undergone alterations or repairs shall be
taken into use in a factory unless it has been thoroughly examined by a competent
person externally and internally, if practicable, and has been hydrostatically tested
by the competent person at a pressure
Atomic Energy Factory Rules, 1996
42
Rule 36
which shall be 1.5 times the maximum permissible working pressure:
Provided that the pressure vessel or plant which is so designed and constructed
that it cannot be safely filled with water or liquid or is used in service when even
some traces of water cannot be tolerated, shall be pneumatically tested at a
pressure not less than the design pressure or maximum permissible working
pressure as the case may be:
Provided further that the pressure vessel or plant which is lined with glass shall be
tested hydrostatically or pneumatically as required at a pressure not less than the
design pressure or maximum permissible working pressure as the case may be.
Explanation:- Design pressure shall be not less than the maximum permissible
working pressure and shall take into account the possible fluctuations of pressure
during actual operation.
(b) No pressure vessel or plant shall be used in a factory unless there has been
obtained from the maker of pressure vessel or plant or from the competent person
a certificate specifying the design pressure or maximum permissible working
pressure thereof, and stating the nature of tests to which the pressure vessel or
plant and its fittings (if any) have been subjected, and every pressure vessel or
plant so used in a factory shall be marked so as to enable it to be identified as to
be the pressure vessel or plant to which the certificate relates and certificate shall
be kept available for perusal by the Inspector.
(c) No pressure vessel or plant shall be permitted to be operated or used at a pressure
higher than its design pressure, or the maximum permissible working pressure as
shown in the certificate.
(7) In-service test and examinations.-
(a) Every pressure vessel or plant in service shall be thoroughly examined by a
competent person -
(i) externally, once in every period of six months; and
(ii) internally, once in every period of twelve months:
Provided that if by reason of the construction of a pressure vessel or plant,
a thorough internal examination is not possible, this examination may be
replaced by a hydrostatic test which shall be carried out once in every
period of two years:
Provided further that for a pressure vessel or plant in continuous process
which cannot be frequently opened, the period
Atomic Energy Factory Rules, 1996
43
Rule 36
of internal examination may be extended to four years; and
(iii) hydrostatically tested once in every period of four years:
Provided that in respect of a pressure vessel or plant with thin walls, such
as sizing cylinder made of copper or any other non-ferrous metal, periodic
hydrostatic test may be dispensed with subject to the condition that the
requirements laid down in sub-rule (8) are fulfilled:
Provided further that when it is impracticable to carry out thorough
external examination of any pressure vessel or plant every six months as
required in sub-clause (i)of this clause, or if owing to its construction and
use a pressure vessel or plant cannot be hydrostatically tested as required
in sub-clauses (ii) and (iii) of this clause, a thorough external examination
of the pressure vessel or plant shall be carried out at least once in every
period of two years, and at least once in every period of four years a
thorough systematic non- destructive test like ultrasonic test or magnetic
particle test for metal thickness or other defects of all parts the failure of
which might lead to eventual rupture of the pressure vessel or plant shall
be carried out.
(b) The pressure for the hydrostatic test to be carried out for the purpose of this sub-
rule shall be 1.25 times the design pressure or 1.5 times the maximum permissible
working pressure, whichever is less.
(8) (a) In respect of any pressure vessel or plant which cannot hold the hydrostatic load,
periodic hydrostatic test may be dispensed with provided the requirements set
forth in clause (7)(a)above are complied with.
(b) If any information as to the date of construction, thickness of walls, or maximum
permissible working pressure is not available, the age of such pressure vessel or
plant shall be determined by the competent person in consultation with the
Competent Authority from the other particulars available with the factory.
(c) Every new and second hand pressure vessel or plant to which repairs, likely to
affect its strength or safety, have been carried out, shall be tested before use to at
least 1.5 times its maximum permissible working pressure.
(9) Report by competent person.-
(a) If during any examination any doubt arises as to the ability of the pressure vessel
or plant to work safely until the next prescribed examination, the competent
person shall enter in the prescribed register his
Atomic Energy Factory Rules, 1996
44
Rules 36-37
observations, findings and conclusions with other relevant remarks with reasons
and may authorise the pressure vessel or plant to be used and kept in operation
subject to a lowering of maximum permissible working pressure, or to more
frequent or special examination or test, or subject to both of these conditions.
(b) A report of every examination or test carried out shall be completed in Form 5 and
shall be signed by the person making the examination or test, and shall be kept
available for perusal by the Inspector at all hours when the factory or any part
thereof is working.
(c) Where the report of any examination under this rule specified any condition for
securing the safe working of any pressure vessel or plant, the pressure vessel or
plant shall not be used unless the specified condition is fulfilled.
(d) The competent person making report of any examination under this rule, shall
within seven days of the completion of the examination, send to the Competent
Authority a copy of the report in every case where the maximum permissible
working pressure is reduced or the examination shows that the pressure vessel or
plant or any part thereof cannot continue to be used with safety unless certain
repairs are carried out or unless any other safety measure is taken.
(10) Application of other laws.-
(a) The requirements of this rule shall be in addition to and without any prejudice to
and not in derogation of the requirements of any other law in force.
(b) Certificates or reports of any examination, or test of any pressure vessel or plant to
which sub-rules (7) to (9) do not apply, conducted or required to be conducted
under any other law in force and other relevant record relating to such pressure
vessel or plant, shall be properly maintained as required under the said law and
shall be produced on demand by the Inspector.