Rule 17, GUWAHATI BUILDING BYELAWS: “Completion Certificate”
GUWAHATI BUILDING BYELAWS - Rule 17
Text of rule 17
“Completion Certificate”
17. “Completion Certificate”:- The owner through the licensed architect, engineer,
structural engineer, as the case may be (RTP) who has supervised the
construction, shall give notice to the Authority regarding completion of work
described in the building permission. The completion certificate shall be
submitted in the prescribed form by four sets of completion plan. One of the
sets, duly certified as completion plan shall be returned to the owner along with
the issue of full occupancy certificate. The certificate should also be
accompanied by necessary NOC’s wherever required from other authorities like
Director, Fire Service, Pollution Control Board or as per Assam Health
Establishment Act 1993 & rules 1995 as the case may be for that particular
building.
(a) “Occupancy Certificate”:- The Authority, on receipt of the completion
certificate, shall inspect the work and sanction or refuse an occupancy
certificate within 21 days from the date of receipt of completion
certificate, after which period it shall be deemed to have been approved
by the Authority for occupation provided the building has been
constructed as per the sanctioned plans. Where the occupancy certificate
is refused, the various reasons shall be quoted for rejection at the first
instance itself.
(b) Part Occupancy Certificate:- Upon the request of the holder of the
building permission the Authority may issue a part occupancy certificate
for a building or part thereof before completion of the entire work as per
building permission provided sufficient precautionary measures are
taken by the holder of the building permission to ensure public safety
and health safety. The part occupancy certificate shall be given by the
Authority subject to the owner indemnifying the Authority as per the
proforma given in Appendix-IV.
18 (a) Violation Penalty: - Any person who contravenes any of the provisions
of these Byelaws or any requirements or obligation imposed on him by
virtue of these Byelaws or who interferes with or obstruct any person in
the discharge of his duties shall be guilty of an offence and upon
conviction shall be punished by a fine not exceeding Rs. 1000/- per day
and may also be imposed after the day of his first conviction.
NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006
Guwahati Metropolitan Dev. Authority Page No. [21]
(b) Existing buildings:- Nothing in the regulations shall require the
removal, alteration or amendment or prevent the continuance of use and
occupancy in a lawfully safety of life and property.
(c) The Authority shall have the power to carry out inspection of the work
at various stages to ascertain whether the work is proceeding as per the
provisions of rules and sanctioned plan. Section 88 of Guwahati
Metropolitan Development Authority Act. 1985 shall apply for the
action proposed to be taken for any violation/ deviation of sanctioned
plan.
(d) No correspondence regarding building permission and land sale
permission with the applicants will be served in their premises, but will
be made available in the reception counter of the Authority and
applicants are required to collect the same from the counter. This
includes NOC and all objection letters relating to building permission &
land sale.
NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006
Guwahati Metropolitan Dev. Authority Page No. [22]
Chapter-III
STANDARD FOR BUILDINGS OTHER THAN HUTS AND OTHER
REGULATIONS
Previous and next
Questions people ask
Is rule 17 of GUWAHATI BUILDING BYELAWS still in force?
No repeal of GUWAHATI BUILDING BYELAWS is recorded.