Regulation 71, Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023.: Lines crossing or approaching each other and lines crossing street and road
Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023. - Regulation 71
Text of regulation 71
Lines crossing or approaching each other and lines crossing street and road
71. Lines crossing or approaching each other and lines crossing street and road. – Where an overhead line
crosses or is in proximity to any telecommunication line, the owner of the overhead line or the
telecommunication line, whosoever lays his line later, shall arrange to provide for protective devices or guarding
arrangement as per code of practice or guidelines issued by Power and Telecommunication Coordination
Committee and shall observe the following provisions, namely: –
(i) when it is intended to lay a telecommunication line or an overhead line which will cross or be in
proximity to an overhead line or a telecommunication line, as the case may be, the person proposing to lay
such line shall give one month notice of his intention so to do along with the relevant details of protection
and drawings to the owner of the existing line;
(ii) guarding arrangement shall be provided where a line of voltage not exceeding 33 kV crosses a road or
street or telecommunication line;
(iii) where an overhead line crosses or is in proximity to another overhead line, guarding arrangements shall
be provided so as to safeguard against the possibility of their coming into contact with each other; and
(iv) where an overhead line crosses another overhead line, minimum clearances as provided in the table
below shall be ensured:-
Minimum clearances in metre between lines crossing each other
Sl.
No.
Nominal System Voltage
(kV)
11-66 kV
110-132
kV
220 kV 400 kV 765 kV 1200 kV
1. below 11 2.44 3.05 4.58 5.49 7.94 10.44
2. 11-66 2.44 3.05 4.58 5.49 7.94 10.44
3. 110-132
3.05
3.05 4.58 5.49 7.94 10.44
4. 220 4.58 4.58 4.58 5.49 7.94 10.44
5. 400 5.49 5.49 5.49 5.49 7.94 10.44
6. 765
7.94
7.94 7.94 7.94 7.94 10.44
7 1200 10.44 10.44 10.44 10.44 10.44 10.44
Provided that no guarding arrangement is required when an electric line of voltage exceeding 33
kV crosses over another line of 250 V and above voltage or a road or a tram subject to the condition that
adequate clearances are provided between the lowest conductor of the line of voltage exceeding 33 kV
and the top most conductor of the overhead line crossing underneath the line of voltage exceeding 33
kV and the clearances as stipulated in regulation 60 from the topmost surface of the road maintained;
(v) where an overhead direct current line crosses another overhead line, minimum clearances as provided in
the table below shall be ensured:-
Minimum clearances in metre between AC and DC lines crossing each other
Sl.No. System Voltage
AC/DC
100 kV
DC
200 kV
DC
300 kV
DC
400 kV
DC
500 kV
DC
600 kV
DC
800 kV
DC
1. below 11 kV AC 3.05 4.71 5.32 6.04 6.79 7.54 9.04
2. 11-66 kV AC 3.05 4.71 5.32 6.04 6.79 7.54 9.04
3. 110-132 kV AC 3.05 4.71 5.32 6.04 6.79 7.54 9.04
4. 220 kV AC 4.58 4.71 5.32 6.04 6.79 7.54 9.04
[भाग III—खण्ड 4] भारतकाराजपत्र:असाधारण 129
5. 200 kV DC 4.71 4.71 5.32 6.04 6.79 7.54 9.04
6. 300 kV AC 5.32 5.32 5.32 6.04 6.79 7.54 9.04
7. 400 kV AC 5.49 5.49 5.49 6.04 6.79 7.54 9.04
8. 400 kV DC 6.04 6.04 6.04 6.04 6.79 7.54 9.04
9. 500 kV DC 6.79 6.79 6.79 6.79 6.79 7.54 9.04
10. 600 kV DC 7.54 7.54 7.54 7.54 7.54 7.54 9.04
11. 765 kV AC 7.94 7.94 7.94 7.94 7.94 7.94 9.04
12. 800 kV DC 7.94 7.94 7.94 7.94 7.94 9.04 9.04
13. 1200 kV AC 10.44 10.44 10.44 10.44 10.44 10.44 10.44
(vi) a person laying or proposing to lay a line which may cross or be in proximity with an existing line,
shall provide arrangements on his own line or require the owner of the other overhead line to provide
guarding arrangements as referred to in clause (iii) and (iv);
(vii) in all cases referred to in this regulation the expenses of providing the guarding arrangements or
protective devices shall be borne by the person whose line was laid later;
(viii) where two lines cross each other, the crossing shall be made as nearly at right angles as the nature of
the case admits and as near the support of the line as practicable, and the support of the lower line shall not
be placed in the right of way of the upper line; and
(ix) the guarding arrangement shall be carried out by the owner of the support on which it is made and he
shall be responsible for its proper maintenance.
Previous and next
Questions people ask
Is regulation 71 of Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023. still in force?
No repeal of Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023. is recorded.