Form 4B, The West Bengal Ground Water Resources (Management, Control and Regulation) (Amendment) Rules, 2022: Form 4B
The West Bengal Ground Water Resources (Management, Control and Regulation) (Amendment) Rules, 2022 - Form 4B
Text of form 4B
Form 4B .
Form 4B .
[See rules 9(3) and 10(5)]
(HOLOGRAPHIC EMBLEM OF THE CONCERNED AUTHORITY)
PERMIT FOR GROUND WATER ABSTRACTION (MINING PROJECTS)
[u/s 7(3)(b) /7(4)(b) /7(5)(a) of the West Bengal Ground Water Resources
(Management, Control and Regulation) Act 2005.]
PIERIMET NO. vinceszsa steric ap onpntoverad ops vapninthtnendocraurcn uerventucrn sais.
Name of the Project / Mines :
Location details of the Project / Mines :
District— Block — Mouza—
J.L.No. - Plot No. — Lat/Long : —
Subdivision/ Corporation/Municipality/Urban Development Authority/Statutory idusttia!
Notified Area/ SEZ/Gram Panchayat—
Communication Address / Postal Address. with PIN :
Book No. & Serial No. of the Application Form and date of submission :
Approved in DLA/SLA/HLA details :
Specimen Signature of the applicant : [
2. Particulars of the proposed structure and pumping device :
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
Type of Ground water Abstraction/Dewatering Structures (DW/DCB/BW/TW/MP/MPu) :
Approx. depth of the well/structure (m) :
Assembly size (in case of tubewell) : mm. x mm
Type of the pump to be used :
H.P. ef the pump :
Operational device :
Rate of withdrawal (m°/hr) :
Maximum allowable running hours per day :
Maximum allowable running days per year :
This permit authorizes the owner applicant (user) to sink a well in the location specified at SI. (1) (b) for extractionof ground water at a rate not exceeding that as shown at SI. (2) (g) and for running hours /day and maximum runningdays per year as shown at SI. (2) (h) & (1), and is valid subject to the observance of the conditions stated overleaf.
‘Place ;
Date :
Signature of the Issuing Authority
with Designation
OFFICIAL SEAL
Ay Parl] _, THEKOLKATA GAZETTE, EXTRAORDINARY, OCTOBER 14,2022 | es)y
(1)
(2)
(3)
(4)
[B.]
10.
11.
12,
13,
[A.] General Conditions :
In case of any change of ownership of the proposed well, fresh permit has to be obtained.
No change of location, design, rate of withdrawal and pumping device in respect of the proposed well as indicatedat SI (1) and (2) of this certificate shall be made without prior permission of the Competent Authority. Anydeviation in this regard shall lead to cancellation of this permit.
In case, any of the particulars / information furnished by the applicant in his/her application for issuance of thispermit is found to ‘be-incorrect during verification at any subsequent stage, this permit is liable for cancellation.
Any other condition imposed by the concerned Authority.
Mandatory Conditions:
The sinking of Tube-Well should be done within one year from the date of issuance of the permit. If not, then the
_ user must be informed to the permit issuing authority with a satisfactorily explanation.
Installation of Separate Energy/ Electric Meter is mandatory for each tube well.& confirmation of the same shall beintimated to the permit issuing authority within 45 days from the date of installation of the tube well.
It shall be mandatory for all the mining industries to ensure that water available from de-watering operations isproperly treated and should be gainfully utilized for supply for irrigation, dust suppression, mining process, rechargein downstream.
Provision/ Arrangement of "Rooftop Rainwater Harvesting" is mandatory in the premises‘ as per the prevailingModel Building By Laws, for all applicant. The stored water shall be utilised for beneficial uses (other than drinking
purpose) by the applicant.
In case of mining project the applicant shall submit groundwater quality report of mine discharge/seepage from
Govt. approved/ NABL accredited lab to permit issuing authority, in yearly basis.
In case of coal and other base metal mining projects, the project proponent shall use the advance dewateringtechnology to avoid contamination of surface water.
The “Safe Distance Criteria” (as per the instruction of DLA/SLA/HLA) for more than one tube wells should be
adopted.
Installation of tamper proof digital Flow Meter with Telemetry Sensor System is mandatory for Medium to Large
scale units immediately after installation of the tube well and intimation regarding the installation shall be communicated
to the concerned DLA within 30 days from the date of installation of the Flow Meter. The monthly water meterreading should be recorded and submitted to the concerned authority on annual basis. The server will be maintainedby the supplier of the instrument and access will be provided to SWID. For small scale units an ISI marked tamper
proof Digital Flow Meter is mandatory. The daily water meter reading with time (starting & ending time of pump)should be recorded and submitted to the permit issuing authority on annual basis.
Construction of purpose-build Observation Well/Piezometers for groundwater monitoring shall be mandatory for
mining, in the core and buffer zones, as suggested by the authority.
Environmental Clearance Consent to Establish (CTE)/Consent to Operate (CTO) for Medium to Large Scale Unitfrom SPCB/ SEAC/SEIAA, whichever is a applicable.
Unexpected variation in inflow of groundwater into mine pit, if any shall be reported to the concerned DistrictGeologist of SWID.
Treated water/ wastewater shall not be used for recharge to groundwater, since it may contain heavy metals &other toxic elements. The treated water shall be fully used by the proponent or any other agency, who can utilizeit without contaminating the underlying aquifer or water bodies.
The issue of this permit “ee not imply that other statutory/ administrative clearisic=s shall be granted to the projectos
by the concerned authority. Such authorities would consider the project on merits and take decisions independently_ of the permit.
28 uae THE KOLKATA GAZETTE, EXTRAORDINARY, OCTOBER 14, 2022 |
14.. Violation of any above mentioned conditions will be treated as offence under Section 10 and 16 of the West Bengal’
Ground Water Resources (Management, Control & Regulation) Act, 2005 and Rules made thereunder. ‘
OFFICIAL SEAL
| FORM 4C |
PERMIT FOR SINKING OF NEW TUBEWELL UNDER KMC AREA [OTHER THAN INDUSTRY]
[U/S 7 (3)(b)/7(4) (b)/7(5)(a) of the West Bengal Ground Water Resources (Management, Control and Regulation)
Amendment Act, 2005]
KMC Building plan case no. : ...... 0.2. eec cece nSWID PERMIT NOy 3 ¢ cine ccesiis cece cyecine coe
1. (a) Name of the owner
(b) Address of the owner
_(c) Serial No. of Application Form and date of
submission
(d) CLA details and Date
2. Location particulars of TW—
(a) Assessee No., Ward No., Borough No.
(b) Address
(c) Lat/Long
Particulars of the proposed well and pumping device —Go
(a) Type of the well
(b) Approx. depth of the well (m)
(c) Purpose of the well (Domestic/Commercial)
(d} Assembly size : mm x mm
(e) Approx. strainer length © ) i m
(g) Type of pump to be used
(h) H. P. of the pump
G) Rate of withdrawal (m3/hr.)
(k) Maximum allowable running hours per day
This permit authorizes the owner (user) to sink a well in the location specified at Sl. (2) for extraction of groundwater at a rate not exceeding that as shown at SI. (3) (j) and for running hours/day as shown at SI. (3) (x), and is validsubject to the observance of the conditions stated overleaf.
Place: Signature of the Issuing Authority
Date: ‘ with Designation and seal.
*For Online Computer Generated Permits signature is not required. ae 7 ry Le
Paarl] THEKOLKATA GAZETTE, EXTRAORDINARY, OCTOBER. 14, 2022 29
[A] General Condition ;
(1)
(2)
(3)
(4)
[B.]
In case of any change of ownership of the proposed well, fresh permit has to be obtained.
No change of location, design, rate of withdrawal and pumping device in respect of the proposed well as indicatedat SI. (2) and (3) of this certificate shall be-made without prior permission of the Competent Authority. Anydeviation in this regard shall lead to cancellation of this permit.
In case, any of the particulars / information furnished by the owner in his application for issuance of this permit isfound to be incorrect during verification at any subsequent stage, this permit is liable for cancellation.
Any other condition imposed by the concerned Authority,
Mandatory Conditions :
1, The sinking of Tube-Well should be done within one year from the date of issuance of the permit. If not, then theuser must be informed to the permit issuing authority with a satisfactorily explanation.
2. Installation of Separate Energy/ Electric Meter is mandatory for each tube well and confirmation of the same shallbe intimated to the permit issuing authority within 45 days from the date of installation of the tube well.
3. Installation of tamper proof Digital Water Flow Meter with telemetry system is mandatory immediately afterinstallation of the tube well and intimation regarding installation shall be communicated to the concerned CLAwithin 30 days from the date of installation of the Flow Meter [When requirement is more than 100KLD for anyMedium to Large scale project]. The server will be maintained by the supplier of the instrument and access will beprovided to SWID. For small scale units an ISI marked tamper proof Digital Flow Meter is mandatory.
4. Provision/ Arrangement of “Rooftop Rain Water Harvesting” is mandatory in the premises as per the prevailingModel Building Acts and By Laws of Central or State in practice, for Medium to Large scale project. The storedwater shall be utilized for beneficial uses (other than drinking purpose) by the applicant.
5. Ground water Quality report from Govt. approved/ NABL accredited lab to be submitted by the applicant to theCorporation Level Authority on annual basis.
6. Incase of Permission within KMC area Boring Permit will only be valid after generating KMC Licence Fee demandu/s 248 of KMC Act. :
7. Violation of any above mentioned conditions will be treated as offence under Section 10 and 16 of the West BengalGround Water Resources (Management, Control & Regulation) Act, 2005 and Rules made thereunder.
Previous and next
Questions people ask
Is form 4B of the West Bengal Ground Water Resources (Management, Control and Regulation) (Amendment) Rules, 2022 still in force?
No repeal of the West Bengal Ground Water Resources (Management, Control and Regulation) (Amendment) Rules, 2022 is recorded.