19. Boundary wall Maximum height allowed: -
Facing road or open area: upto 0.9m solid wall with
0.9m high perforated Grill/Jali.
Facing other property: upto 1.83m solid wall.
Minimum Turning Radius for corner plot: -
5’-0” or 1/8th of the adjoining road width, whichever is more
and maximum upto 20’-0”
20. Basement Plot size upto 2025 sq.m: single story basement is allowed upto
zoned area or upto the boundary of the plot except front and rear
side, as the case may be, subject to the condition that the owner
shall leave minimum 2.44 m (8'-0") setback from the respective
side of the boundary wall of the plot, if adjoining plot has a
building upto 2.44m from the plot line.
Plot size above 2025 sq.m: The multi-level basement shall be
allowed below the ground and beyond the building line at ground
level subject to a clear minimum front margin of 4.5 m and side
Serial Parameter Permissible Limits
Num- Category Pre Nursery/ Primary School High/ Sr. Sec.
ber Nursery/ Creche (Class 1 To 5) School/ College
or Edu. Institute/
Universities
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2360
and rear margins of 3 m, subject to the provision of mechanical
ventilation and all safety provisions and drainage.
Basement shall not be allowed in the case of No
construction Zone/ Area or Master Plan Green area or any other
restricted area/zone under the provision of any other Act/policy
of the State or Central Government.
Minimum clear height for basement shall be as below:
• Non-Habitable use: 2.40 m
• Habitable Use: 2.75 m
21. Vehicular Ramp Ramps are mandatory for plot size above 3000 sq.m.
Minimum width: 7.2m for two way traffic
4m for one way traffic
Slope: i) Cars not less than 1:8 and at curve 1:12
ii) Heavy not less than 1:15
vehicles
22. Minimum 1.5 Equivalent 1.5 Equivalent School, College:
Parking Car Spaces / Car Spaces / 1.5 Equivalent Car
required 100sq.m of total 100sq.m of total Spaces /100 sq.m
Floor Area Ratio Floor Area Ratio. of the total Floor
Area Ratio area
University
Campus:
1.0 Equivalent Car Space/
100 sq.m of the total Floor
Area Ratio area
23. Allowable 1.83 m wide
Projection (Free
from Ground
Coverage and
Floor Area Ratio)
24. Balcony (Free 1.83 m wide
from Ground
Coverage and
Floor Area Ratio)
Serial Parameter Permissible Limits
Num- Category Pre Nursery/ Primary School High/ Sr. Sec.
ber Nursery/Creche (Class 1 To 5) School/ College
or Edu. Institute/
Universities
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2361
25. Rain Water Required
Harvesting System
26. Solar Water Not mandatory but recommended to meet its hot water
Heating System demand from solar water heaters, as far as possible.
27. Solar Photo Having Connected Load Minimum requirement
Voltaic 30 KWp and above Minimum 2 Kilo Watt peak
or 5 percent of whichever
is higher
28. Flushing System Provision of dual button type flushing cistern in each water closet.
29. DG Set The location of the Diesel Generator (DG) set and exhaust pipe
height shall be as per the provisions of the CPCB norms.
30. Parapet or Railing Minimum Height: 1.0 m
Maximum Height: 1.4 m from the finished floor level
31. Amalgamation Amalgamation allowed
or Fragmentation Fragmentation not allowed
Notes:-
a) In case of new school area of 1 acre or above, the front boundary wall shall be
recessed by 6m to accommodate visitors parking within setback area.
b) Minimum 15 percent of site area shall be kept/developed as playground
with minimum width of 15 m.
c) Upto 15 percent of the total Floor Area Ratio area in educational buildings
shall be permissible for the housing of staff or workers.
d) In case of large Campus/Universities/Indian Institute of Technology (IIT)/
Indian Institute of Management (IIM), upto 30 percent of the total Floor
Area Ratio area can be utilized for residential use for essential staff and
fellow accommodations by providing housing for staff, dormitories, guest
houses or crèche.
e) Student Hostel shall not be counted in residential component.
f) Area requirements of each type of educational institutions wherever not
specified shall be as per the norms or guidelines issued by the affiliating.
Serial Parameter Permissible Limits
Num- Category Pre Nursery/ Primary School High/ Sr. Sec.
ber Nursery/ Creche (Class 1 To 5) School/ College
or Edu. Institute/
Universities
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2362
7 INSTITUTIONAL.- The institutional buildings of various types shall be
governed by the following norms, namely:-
(1) Hospital or Nursing Home or Medical Laboratory; Orphanage Home;
Old Age Home; Children's Centre or Care Centre or School or Institute
for Mentally Challenged or Physically Handicapped Persons
Serial PARAMETERS Permissible Limits
Num- Category Hospital/ Nursing Orphanage Home, Old
ber Home/ Medical Age Home, Children's
Laboratory Centre/ Care Centre/
School/Institute for
Mentally Challenged or
Physically Handicapped
Person
1. Minimum 12 m 18 m 24 m 12m
Approach Road (40'-0") (60'-0") (80'-0") (40'-0")
2. Permissible / 1000 2000 Above 1000 sq.m
Minimum upto upto 4000
Site Area 2000 4000 sq.yd
sq.yd sq.yd
3. Minimum Set 6m minimum from site boundary and as per sub rule (1) of
back required: - these building rules.
However, for the plots upto 2025 sq.m area
where width of the plot is less than 30.50m (100'-0")
and the maximum height of building is below 15m
excluding the architectural and symbolism element of
religious building like dome, minarets, sikharas,
crucifix etc. from building height, then one side setbacks
may be relaxed subject to the condition that the owner
has to submit a fire safety certificate from the competent
authority in this regard.
4. Maximum Floor 1:1.50 1:1.75 1:2.25 1:1.5
Area Ratio
5. Maximum 40 percent of plot area 50 percent of plot area
Ground Coverage
6. Plinth 450mm or as specified by competent authority (from
the crown of adjoining road in front).
Provided that for a detached building, the plinth level
may be more than 450mm:
Section
180 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2363
Provided further that the level of front courtyard of any
building shall not exceed 450 mm and the ramp from the front
road to the courtyard shall be within the plot boundary.
7. Maximum Height No Restriction subject to the fulfilment of norms such as
of Building setbacks around building, ground coverage, Floor Area Ratio,
structural safety and fire safety norms.
However, clearance from Airport Authority of India or
Indian Air Force is required in case the height of the building
is 15m or more or site falls in the red colour of home grid of
Colour Coded Zoning Map issued by Airports Authority of
India or Indian Air Force.
8. Minimum Component of Building Min. Min. Min.
requirements of area Width Clear
different (SQ.M) (M) Height (M)
component of a Habitable room 9.5 2.4 2.75
building Kitchen
• where separate 5 1.8
dining area is
provided
• where separate 4.5 1.8 2.75
store is provided
• where dinning 7.5 2.1
included
Bathroom 1.8 1.2 2.1
Water Closet (W.C.) 1.2 0.9 2.1
combined bath and w.c 2.8 1.2 2.1
Store 3 1.2 2.2
Single occupancy 7.5 2.1 2.75
Servant Room
Serial PARAMETERS Permissible Limits
Num- Hospital/ Nursing Orphanage Home, Old Age
ber Home/ Medical Home, Children's Centre/
LaboratoryCare Centre/
School/Institute for
Mentally Challenged or
Physically Handicapped
Person
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2364
9. Light and (a) one or more openings, such as windows and ventilators,
Ventilation opening directly to the external air or into an open
Verandah.
(b) such openings, excluding doors inclusive of frames, shall
not be less than one-tenth of the floor area. In case of
Kitchen such opening shall be increased by 25 percent.
10. Ventilation Shaft the size of ventilation shaft shall not be less than the values
given below:-
Height of building Size Min. one dimension
(sq.m)
10m 1.2 0.9 m
12m 2.8 1.2 m
18m 4.0 1.5 m
24m 5.4 1.8 m
30m 8.0 2.4 m
Above 30m 9.0 3.0 m
Notes:-
(a) For buildings of height above 30 m, a mechanical ventilation
system shall be installed besides the provision of minimum
ventilation shaft.
(b) For fully air conditioned the ventilation shaft need not be
insisted upon, provided the air conditioning system works in
an uninterrupted manner, also, provided there is an alternative
source of power supply.
(c) Mechanical ventilation in building shall be as per the
provision of the National Building Code of India, 2016, as
amended from time to time.
Serial PARAMETERS Permissible Limits
Num- Hospital/ Nursing Orphanage Home, Old Age
ber Home/ Medical Home, Children's Centre/
Laboratory Care Centre/
School/Institute for Mentally
Challenged or Physically
Handicapped Person
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2365
11. Interior courtyard Minimum area 9 sq.m
for Light and Minimum width 2.4 m or 1/5 of the average height of the
Ventilation building whichever is more.
12. Staircase Minimum Minimum
Clear Width: 2000 mm Clear Width: 1500 mm
Minimum Tread: 300 mm Minimum Tread: 300 mm
Maximum Riser: 150 mm Maximum Riser: 150 mm
Minimum Minimum
Headroom Headroom
Height: 2200 mm Height: 2200 mm
13. Lift and Ramp Lift is mandatory in buildings 15m or more in height and
requirement for basement provided more than one level as per the provision
pedestrians, of the National Building Code of India, 2016.
differently-abled, upto Plinth Level upto Plinth Level
elderly and Min. Width - 2400mm Min. Width - 1800mm
children Min. Slope - 1:12 Min. Slope - 1:12
Only for In-patient
Medical Facilities upto
Higher Floors –
Minimum Width - 2400mm
or as per the occupant load
whichever is more
Minimum Slope - 1:12
14. Mumty Allowed upto 2.75 m, otherwise counted towards the height
of the building as well as Floor Area Ratio.
15. Services on Solar Photo Voltaic installation, Water tank, Rain water pipes
Terrace with drainage, Water Tank, cooling towers for air conditioning
plants, mumty, machine room and screening parapet to hide
services or as per the provisions of the National Building Code
Of India, 2016.
Serial PARAMETERS Permissible Limits
Num- Hospital/ Nursing Orphanage Home, Old Age
ber Home/ Medical Home, Children's Centre/
LaboratoryCare Centre/
School/Institute for Mentally
Challenged or Physically
Handicapped Person
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2366
16. Gate and post Watch and ward cabins upto 100 sq.ft along each entry gate
check exempted from Ground Coverage and Floor Area Ratio (FAR).
17. Boundary wall Maximum height allowed: -
Facing road or open area: upto 0.9m solid wall with
0.9m high perforated
Grill/Jali.
Facing other property: upto 1.83m solid wall.
Minimum Turning Radius for corner plot: -
5’-0” or 1/8th of the adjoining road width, whichever is more
and maximum upto 20’-0”.
18. Basement Plot size upto 2025 sq.m: single story basement is allowed
upto zoned area or upto the boundary of the plot except front
and rear side, as the case may be, subject to the condition that
the owner shall leave minimum 2.44 m (8'-0") setback from
the respective side of the boundary wall of the plot, if adjoining
plot has a building upto 2.44m from the plot line.
Plot size above 2025 sq.m: The multi-level basement shall
be allowed below the ground and beyond the building line at
ground level subject to a clear minimum front margin of 4.5 m
and side and rear margins of 3 m, subject to the provision of
mechanical ventilation and all safety provisions and drainage.
Basement shall not be allowed in the case of No
construction Zone/ Area or Master Plan Green area or any
other restricted area/zone under the provision of any other
Act/policy of the State or Central Government.
Minimum clear height for basement shall be as below:
• Non-Habitable use: 2.40 m
• Habitable Use: 2.75 m
19. Vehicular Ramp Ramps are mandatory for plot size above 3000 sq.m.
Minimum width: 7.2m for two way traffic
4m for one way traffic
Slope: i) Cars not less than 1:8 and at curve 1:12
ii) Heavy vehicles not less than 1:15
Serial PARAMETERS Permissible Limits
Num- Hospital/ Nursing Orphanage Home, Old Age
ber Home/ Medical Home, Children's Centre/
Laboratory Care Centre/
School/Institute for Mentally
Challenged or Physically
Handicapped Person
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2367
20. Parking 2 Equivalent Car Spaces/ 1 Equivalent Car Space / 100 sq.m
100 sq.m of the total of the total Floor Area Ratio
Floor Area Ratio
21. Projection or Maximum allowable projection (free from ground coverage
Balcony and floor area ratio): 1.80m (6’-0”) within zoned area
22. Rainwater Compulsory
Harvesting
23. Solar Water Not mandatory but recommended meeting its hot water
Heating System demand from solar water heaters, as far as possible.
24. Solar Photo Connected Load Minimum Requirement
Voltaic (a) 50 KWp to Minimum 10 Kilo Watt peak or
1000 KWp 5 percent of connected load,
whichever is higher.
(b) Above 1000 KWp Minimum 50 Kilo Watt peak or3
percent of connected load,
whichever is higher.
25. Flushing System Dual button type flushing cistern in each water closet.
26. Parapet or Minimum Height: 1.0 m
Railing Maximum Height: 1.4 m from the finished floor level.
27. Minimum Hospital, Nursing Homes, etc.: 2400 mm
Passage or Orphanage Home: 1500 mm for single loaded and 1800 mm
Corridor for double loaded.
This width shall increase with increase in the occupant load of
the building and shall provide as per the National Building
Code Of India, 2016.
Notes:-
a) Maximum up to 2 percent of Floor Area Ratio area shall be allowed to be
used for community space / creche / chemist shop/ bank counter on Hospital
sites and also Medical College/ Nursing and Paramedic institute sites.
b) In case of hospitals, 25 percent of the total Floor Area Ratio area may be
utilized for residential use for staff, dormitory/ hostels for attendants of the
patients, creche etc.
Serial PARAMETERS Permissible Limits
Num- Hospital/ Nursing Orphanage Home, Old Age
ber Home/ Medical Home, Children's Centre/
Laboratory Care Centre/
School/Institute for Mentally
Challenged or Physically
Handicapped Person
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2368
c) Adequate arrangements for disposal of hospital waste have to be made
as per the Bio- Medical Waste (Management and Handling) Rules,
1998, as amended from time to time along with the instructions/
guidelines issued by the Punjab Pollution Control Board from time to
time.
d) Floor Area Ratio above 1:1.50 will be chargeable on pro-rata basis in
Hospital, Nursing Home and Medical Laboratory sites. However, the
site allotted or sold by the development authority the charges shall be
applicable as per the terms and conditions of the allotment letter.
e) For sites of Orphanage Home, Old age home, Children's centre/ care
centre/ school/ Institute of Mentally challenged or Physically
Handicapped Person: Minimum 15percent of site area shall be kept/
developed as playground/green with minimum width of 15 m.
f) In case of school for mentally/differently able persons, 25 percent of
the total Floor Area Ratio area can be utilized for residential use for
essential staff and student accommodations.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2369
8 PUBLIC BUILDINGS.- The public buildings of various types shall be
governed by the following norms, namely:-
(1) Community Centre, Public Concert Hall or Auditorium, Museum,
Gymnasium or Public Exhibition; Religious Building; Public Offices
Serial PARAMETERS Permissible Limits
Num- Community Centre, Religious Public
ber Public Concert Hall Building Offices
or Public Exhibition
Auditorium,
Museum or
Gymnasium
1. Minimum Within Master Plan: 12 m 18m 18 m
Approach Road 18 m (60'-0") (40'-0") (60'-0") (60'-0")
Outside MasterPlan:
12m (40'-0")
2. Permissible or 2000 sq.m 1000 Above 1000
Minimum Site upto 2000 sq.m
Area 2000 sq.m
sq.m
3. Minimum Set 6m minimum from site boundary and as per sub rule (1) of
back required: - rule 26 of these building rules.
However, for the plots upto 2025 sq.m area where width of the plot is less
than 30.50m (100'-0") and the maximum height of building is below 15m excluding
the architectural and symbolism element of religious building like dome, minarets,
sikharas, crucifix etc. from building height, then one side setbacks may be relaxed
subject to the condition that the owner has to submit a fire safety certificate from
the competent authority in this regard.
4. Maximum 1:1.0 1:1.0 Minimum
permissible Floor approach
Area Ratio (FAR) Road
width: FAR
18m: 1:2.0
30m: 1:2.5
45m: Unlimited
5. Maximum 40 percent of 40 percent of 40 percent of
Ground plot area plot area plot area
Coverage
Section
180 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2370
6. Plinth 450mm or as specified by competent authority (from the crown
of adjoining road in front),
Provided that for a detached building, the plinth level
may be more than 450mm:
Provided further that the level of front courtyard of
any building shall not exceed 450 mm and the ramp from the
front road to the courtyard shall be within the plot boundary.
7. Maximum Height No Restriction subject to the fulfilment of norms such as
of Building setbacks around building, ground coverage, Floor Area Ratio,
structural safety and fire safety norms.
However, clearance from Airport Authority of India or Indian
Air Force is required in case the height of the building is 15m
or more or site falls in the red colour of home grid of Colour
Coded Zoning Map issued by Airports Authority of India or
Indian Air Force.
8. Minimum Clear 3.6m
Ceiling Height
for religious
gathering area
9. Minimum Component of Building Min. Min. Min.
requirements (SQ.M) Width Clear
of different (M) Height (M)
component Habitable room 9.5 2.4 2.75
of a building Bathroom 1.8 1.2 2.1
Water Closet (W.C.) 1.2 0.9 2.1
combined bath and w.c 2.8 1.2 2.1
Store 3 1.2 2.2
10. Light and (a) One or more openings, such as windows and ventilators,
Ventilation opening directly to the external air or into an open
Verandah.
Serial PARAMETERS Permissible Limits
Num- Community Centre, Religious Public
ber Public Concert Hall Building Offices
or Public Exhibition
Auditorium,
Museum or
Gymnasium
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2371
(b) Such openings, excluding doors inclusive of frames, shall
not be less than one-tenth of the floor area. In case of
Kitchen such opening shall be increased by 25 percent.
11. Ventilation Shaft The size of ventilation shaft shall not be less than the values
given below:-
Height of building Size (sq.m) Min. one dimension
10m 1.2 0.9 m
12m 2.8 1.2 m
18m 4.0 1.5 m
24m 5.4 1.8 m
30m 8.0 2.4 m
Above 30m 9.0 3.0 m
Notes:-
(a) For buildings of height above 30 m, a mechanical ventilation
system shall be installed besides the provision of minimum
ventilation shaft.
(b) For fully air conditioned, the ventilation shaft need not be
insisted upon, provided the air conditioning system works in
an uninterrupted manner, also, provided there is an alternative
source of power supply.
(c) Mechanical ventilation in building shall be as per the
provision of the National Building Code of India, 2016, as
amended from time to time.
12. Interior courtyard Minimum area 9 sq.m
for Light and Minimum width 2.4 m or 1/5 of the average height of the
Ventilation building whichever is more.
13. Staircase Minimum Clear
Width: 2000 mm or as Min. Width: 1500 mm
per occupants or as per occupants load
load whichever whichever is more
is more
Serial PARAMETERS Permissible Limits
Num- Community Centre, Religious Public
ber Public Concert Hall Building Offices
or Public Exhibition
Auditorium,
Museum or
Gymnasium
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2372
Minimum Tread: 300 mm Min. Tread: 300 mm
Maximum Riser: 150 mm Max. Riser: 150 mm
Minimum Min. Headroom
Headroom Height: 2200 mm Height: 2200 mm
14. Lift and Ramp Lift is mandatory in buildings 15m or more in height and
requirement basement provided more than one level as per the provision
of the National Building Code of India, 2016.
Ramp requirement for pedestrians, differently-abled, elderly
and children upto Plinth Level :-
Min. Width - 1800mm
Min. Slope - 1:12
15. Mumty Allowed upto 2.75 m otherwise counted in calculating the
height of the building as well as covered area.
16. Services on Terrace Solar Photo Voltaic installation, Water tank, Rain water pipes
with drainage, Water Tank, cooling towers for air conditioning
plants, mumty, machine room and screening parapet to hide
services or as per the provisions of the National Building Code
of India, 2016.
17. Gate and post Watch and ward cabins upto 100 sq.ft along each entry gate
check exempted from Ground Coverage and Floor Area Ratio (FAR).
18. Boundary wall Maximum height allowed: -
Facing road or open area: upto 0.9m solid wall with
0.9m high perforated
Grill/ Jali.
Facing other property: upto 1.83m solid wall
Minimum Turning Radius for corner plot: -
5’-0” or 1/8th of the adjoining road width, whichever is more
and maximum upto 20’-0”.
19. Basement Plot size upto 2025 sq.m: single story basement is allowed
upto zoned area or upto the boundary of the plot except front
Serial PARAMETERS Permissible Limits
Num- Community Centre, Religious Public
ber Public Concert Hall Building Offices
or Public Exhibition
Auditorium,
Museum or
Gymnasium
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2373
and rear side, as the case may be, subject to the condition that
the owner shall leave minimum 2.44 m (8'-0") setback from
the respective side of the boundary wall of the plot, if adjoining
plot has a building upto 2.44m from the plot line.
Plot size above 2025 sq.m: The multi-level basement shall
be allowed below the ground and beyond the building line at
ground level subject to a clear minimum front margin of 4.5 m
and side and rear margins of 3 m, subject to the provision of
mechanical ventilation and all safety provisions and drainage.
Basement shall not be allowed in the case of no
construction Zone/ Area or Master Plan Green area or any
other restricted area/zone under the provision of any other
Act/policy of the State or Central Government.
Minimum clear height for basement shall be as below:
• Non-Habitable use: 2.40 m
• Habitable Use: 2.75 m
20. Vehicular Ramp Ramps are mandatory for plot size above 3000 sq.m.
Minimum width: 7.2m for two way traffic
4m for one way traffic
Slope: (i) Cars not less than 1:8 and at curve
1:12
(ii) Heavy vehicles not less than 1:15
21. Parking 3 Equivalent Car 2 Equivalent 1 Equivalent
Spaces/ 100 sq.m Car Spaces/ Car Space /
of the total Floor 100 sq.m of 100 sq.m of
Area Ratio the total Floor the total Floor
Area Ratio Area Ratio
22. Projection or Maximum allowable projection (free from ground coverage
Balcony and floor area ratio): 1.80m (6’-0”) within zoned area
23. Rainwater Compulsory
Harvesting
Serial PARAMETERS Permissible Limits
Num- Community Centre, Religious Public
ber Public Concert Hall Building Offices
or Public Exhibition
Auditorium,
Museum or
Gymnasium
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2374
24. Solar Water Not mandatory but recommended meeting its hot water
Heating System demand from solar water heaters, as far as possible.
25. Solar Photo Connected Load Minimum Requirement
Voltaic
i) Community (a)50 KWp to 1000 KWp Minimum 10 Kilo Watt peak
Centre, Public or 5 percent of connected load,
Concert Hall or whichever is higher.
Public Exhibition (b) Above 1000 KWp Minimum 50 Kilo Watt peak or 3
Auditorium, percent of connected load,
Museum or whichever is higher.
Gymnasium
ii) Public Offices (a) 30KWp and above Minimum 2 Kilo Watt peak or 5
percent of connected load,
whichever is higher.
26. Flushing System Dual button type flushing cistern in each water closet.
27. Parapet or Railing Minimum Height: 1.0 m
Maximum Height: 1.4 m from the finished floor level.
28. Minimum Passage 2000mm or as per 2000mm or as 1500 mm for
or Corridor occupant load which- per occupant single loaded
ever is more load whichever and 1800 mm
is more for double
loaded or as
per occupant
load
whichever is
more.
Notes:-
(a) In case of Community Centre, it shall only have banquet hall, kitchen, library, office
Serial PARAMETERS Permissible Limits
Num- Community Centre, Religious Public
ber Public Concert Hall Building Offices
or Public Exhibition
Auditorium,
Museum or
Gymnasium
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2375
and reading room, except these, if any, other activity is proposed then it shall be
considered as club.
(b) Upto 1.0 percent of the total Floor Area Ratio area of Community Centre, Public
Concert Hall or Auditorium, Museum, Gymnasium or Public Exhibition shall be
allowable for commercial activity.
(c) *Unlimited Floor Area Ratio shall be subject to fulfilment of building controls such
as ground coverage, setbacks around the building, parking norms, light and ventilation,
height, fire and structural safety.
(d) Floor Area Ratio above 1:1.75, shall be chargeable on pro-rata basis except State or
Central Government offices. However, the site allotted or sold by the development
authority the charges shall be applicable as per the terms and conditions of the
allotment letter.
(e) Upto 15 percent of the total Floor Area Ratio area in Public buildings shall be
permissible for the housing of staff or workers.
(2) Convention Centre
Serial PARAMETERS Permissible Limits
Number
1. Minimum Within Master Plan: 18 m (60'-0")
Approach Road Outside Master Plan: 12m (40'-0")
2. Minimum Site Area 2000 sq.m
3. Minimum Set back 6m minimum from site boundary and as per table of sub
required rule (1) of rule 26 of these building rules.
However, for the plots upto 2025 sq.m area where
width of the plot is less than 30.50m (100'-0") and the
maximum height of building is below 15m excluding the
architectural and symbolism element of religious building
like dome, minarets, sikharas, crucifix etc. from building
height, then one side setbacks may be relaxed subject to the
condition that the owner has to submit a fire safety certificate
from the competent authority in this regard.
4. Maximum Floor 1:2.0
Area Ratio
5. Maximum Ground 50 percent of plot area
Coverage
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2376
6. Plinth 450mm or as specified by competent authority (from the crown
of adjoining road in front).
Provided that for a detached building, the plinth level
may be more than 450mm:
Provided further that the level of front courtyard of
any building shall not exceed 450 mm and the ramp from the
front road to the courtyard shall be within the plot boundary.
7. Maximum Height No Restriction subject to the fulfilment of norms such as
of Building setbacks around building, ground coverage, Floor Area Ratio,
structural safety and fire safety norms.
However, clearance from Airport Authority of India
or Indian Air Force is required in case the height of the building
is 15m or more or site falls in the red colour of home grid of
Colour Coded Zoning Map issued by Airports Authority of
India or Indian Air Force.
8. Minimum Component of Building Min. Min. Min. Clear
requirements of area Width Height (M)
different (SQ.M) (M)
component of Habitable room 9.5 2.4 2.75
a building Kitchen
• where separate 5 1.8
dining area is
provided
• where separate 4.5 1.8 2.75
store is provided
• where dinning 7.5 2.1
included
Bathroom 1.8 1.2 2.1
Water Closet (W.C.) 1.2 0.9 2.1
combined bath and w.c 2.8 1.2 2.1
Store 3 1.2 2.2
Single occupancy 7.5 2.1 2.75
Servant Room
Serial PARAMETERS Permissible Limits
Number
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2377
9. Light and (a) One or more openings, such as windows and ventilators,
Ventilation opening directly to the external air or into an open
Verandah.
(b) Such openings, excluding doors inclusive of frames, shall
not be less than one-tenth of the floor area. In case of
Kitchen such opening shall be increased by 25 percent.
10. Ventilation Shaft The size of ventilation shaft shall not be less than the values
given below:-
Height of building Size (sq.m) Min. one dimension
10m 1.2 0.9 m
12m 2.8 1.2 m
18m 4.0 1.5 m
24m 5.4 1.8 m
30m 8.0 2.4 m
Above 30m 9.0 3.0 m
Notes:
(a) For buildings of height above 30 m, a mechanical ventilation
system shall be installed besides the provision of minimum
ventilation shaft.
(b) For fully air conditioned, the ventilation shaft need not be
insisted upon, provided the air conditioning system works in
an uninterrupted manner, also, provided there is an alternative
source of power supply.
(c) Mechanical ventilation in building shall be as per the
provision of the National Building Code of India, 2016, as
amended from time to time.
11. Interior courtyard Minimum area 9 sq.m
for Light and Minimum width 2.4 m or 1/5 of the average height of the
Ventilation building whichever is more.
12. Staircase Minimum Clear Width: 2000 mm or as per occupant
load whichever is more
Minimum Tread: 300 mm
Maximum Riser: 150 mm
Minimum Headroom Height: 2200 mm
Serial PARAMETERS Permissible Limits
Number
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2378
13. Lift and Ramp Lift is mandatory in buildings 15m or more in height and
requirement basement provided more than one level as per the provision
of the National Building Code of India, 2016.
Ramp requirement for pedestrians, differently-abled, elderly
and children upto Plinth Level :-
Min. Width - 1800mm
Min. Slope - 1:12
14. Mumty Allowed upto 2.75 m, otherwise counted towards the height
of the building as well as Floor Area Ratio.
15. Services on Terrace Solar Photo Voltaic installation, Water tank, Rain water pipes
with drainage, Water Tank, cooling towers for air conditioning
plants, mumty, machine room and screening parapet to hide
services or as per the provisions of the National Building Code
of India, 2016.
16. Gate and post Watch and ward cabins upto 100 sq.ft along each entry gate
check exempted from Ground Coverage and Floor Area Ratio (FAR).
17. Boundary wall Maximum height allowed:-
Facing road or open area: upto 0.9m solid wall with 0.9m
high perforated Grill/Jali.
Facing other property: upto 1.83m solid wall.
Minimum Turning Radius for corner plot: -
5’-0” or 1/8th of the adjoining road width, whichever is more
and maximum upto 20’-0”.
18. Basement Plot size upto 2025 sq.m: single story basement is allowed
upto zoned area or upto the boundary of the plot except front
and rear side, as the case may be, subject to the condition that
the owner shall leave minimum 2.44 m (8'-0") setback from
the respective side of the boundary wall of the plot, if adjoining
plot has a building upto 2.44m from the plot line.
Plot size above 2025 sq.m: The multi-level basement shall
be allowed below the ground and beyond the building line at
ground level subject to a clear minimum front margin of 4.5
m and side and rear margins of 3 m, subject to the provision
of mechanical ventilation and all safety provisions and drainage.
Serial PARAMETERS Permissible Limits
Number
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2379
Basement shall not be allowed in the case of no
construction Zone/ Area or Master Plan Green area or any
other restricted area/zone under the provision of any other
Act/policy of the State or Central Government.
Minimum clear height for basement shall be as below:
• Non-Habitable use: 2.40 m
• Habitable Use: 2.75 m
19. Vehicular Ramp Ramps are mandatory for plot size above 3000 sq.m.
Minimum width: 7.2m for two way traffic
4m for one way traffic
Slope:(i) Cars not less than 1:8 and at curve 1:12
(ii) Heavy vehicles not less than 1:15
20. Parking 2 Equivalent Car Spaces/ 100 sq.m of the total Floor Area Ratio
21. Projection or Maximum allowable projection (free from ground coverage
Balcony and floor area ratio): 1.80m (6’-0”) within zoned area
22. Rainwater Compulsory
Harvesting
23. Solar Water Not mandatory but recommended meeting its hot water
Heating System demand from solar water heaters, as far as possible.
24. Solar Photo Connected Load Minimum Requirement
Voltaic (a)50 KWp to 1000 KWp Minimum 10 Kilo Watt
peak or 5 percent of
connected load, whichever
is higher.
(b) Above 1000 KWp Minimum 50 Kilo Watt
peak or 3 percent of
connected load, whichever
is higher.
25. Flushing System Dual button type flushing cistern in each water closet.
26. Parapet or Railing Minimum Height: 1.0 m
Maximum Height: 1.4 m from the finished floor level.
27. Minimum Passage 2000mm or as per occupant load whichever is more or Corridor
Serial PARAMETERS Permissible Limits
Number
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2380
Notes:-
(a) Upto 30 percent of the total Floor Area Ratio area of Convention Centre
shall be allowable for hotel activity.
(b) Upto 1.0 percent of the total Floor Area Ratio area of Convention Centre
shall be allowable for commercial activity.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2381
PART-III
PROCEDURE OF SUBMISSION OF APPLICATIONS FOR BUILDING
PLAN, COMPLETION CERTIFICATE AND OCCUPATION CERTIFICATE
9 Erection or re-erection without permission. - Subject to the provisions of
the Act and other provisions of these rules, no person shall commence the
erection or re-erection of any building on any site without previous sanction of
the competent authority.
10 Design and supervision. - Except where standard design has been supplied
by the competent authority, the architectural design of every building shall be
prepared and signed by an Architect or Civil Engineer and every building
operation shall be supervised by an Architect or an Engineer.
11 Application to erect or re-erect buildings (without self-certification).- (1)
Every person who intends to erect or re-erect a building shall make an application
in Form ‘A’ (Annexure 1) to the competent authority along with the following
documents and fee as determined by the competent authority, namely:-
(i) ownership documents-lease deed or sale deed or possession letter in the
name of owner issued by the allotment authority or permission to use the
land issued by the competent authority;
(ii) Site plan as detailed in sub- rule (3);
(iii) Hard copy of Building plan and other plans along with an un-editable
Compact Disc or DVD or any other electronic medium permissible by
the competent authority from time to time containing the drawings in
“dwg” format as detailed in sub- rule (4);
(iv) Details of specifications of the work to be executed in Form- ‘C’ (Annexure 3);
(v) Structural safety drawings (for record) as per Form- ‘B’ (Annexure 2);
(vi) Fire safety design as required under Part IV, Fire and Life Safety of the
National Building Code of India, 2016, as amended from time to time, if
applicable;
(vii) Heating, Ventilation, Air-Conditioning (H.V.A.C.) service plan wherever
required;
(viii) Certificate of conformity to regulation and structural safety for the relevant
buildings (depending upon type and height) in the relevant Form
‘B’(Annexure 2);
(ix) Public health services plan in un-editable compact Disc or DVD or any
other electronic medium, containing drawings in “.dwg” format;
(x) Scrutiny fees (non–refundable) shall be deposited in favour of the competent
authority through any specified payment mode, at the rate as described below:
Section
108 (2)
Section
108 (2)
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2382
Scrutiny fees for building plan approval
Type of Building Rate in Rupees Per Square meter of the
Total Covered Area of the Proposed
Building
Residential 30
Commercial buildings and other Public 60
Buildings Construction of boundary wall @Rs. 10 per running meter of the
of plots having area more than 1000 sq.mt. boundary wall.
No scrutiny fees for building plan approval of care centre or school for disabled
persons, care centre or school for mentally challenged persons, orphanage and old
age home shall be chargeable.
In case of revised or superseded plans, the fee chargeable shall be half of the rates
charged for fresh plans for such category of plots as mentioned above.
Note:-
(a) The applicant shall submit all kind of plans in electronic format on the online
portal of the competent authority along with hard copies of the plans. The competent
authority shall convey objections or observations or sanction or refusal through
online portal or as specified mode.
(b) Every person applying under this rule shall appoint an Architect or Engineer for
drawing up of building plans or structural drawings and for the supervision of
erection or re-erection of the building. The supervision of erection or re-erection
of residential or commercial building up to 15 metres height (G+3 floors including
stilt) may be undertaken by the Architect or the Engineer. However, in case of
buildings of 15 meters or above height (including stilt), the supervision shall be
undertaken by both the Architect and the Engineer. During construction, if appointed
Architect or Engineer notices that violations (except compoundable) are going on,
he shall intimate the owner and advise him to stop further construction and remove
the violation and shall also intimate the concerned authority.
(c) The applicant, the Architect and the Engineer shall sign the application, plans,
structural drawings, specifications and the certificates as required in the relevant
forms and documents, before making submission to the competent authority.
(d) In case of row type or semi-detached building, at the time of re-erection of building,
the owner shall provide an indemnity bond as per Annexure 21 that in case of any
damage caused to the adjoining property during construction, the owner shall be
bound to get the damages repaired to the satisfaction of the neighbour.
(2) Size of drawing sheets and colouring of plans. – The size of drawing sheets shall
be any of those specified below, namely:-
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2383
Size of drawing sheets
Serial Number Sheet name Sheet size (in mm)
I. A0 841 X1189
II. A1 594 X 841
III. A2 420X594
IV. A3 297 X 420
Note:
(a) All dimensions in plan can be indicated in metric or feet-inches units.
(b) Various elements of plans (site and building), elevation, section and details
shall be shown in different colours and thickness or type of line, etc., and
shall be preferably prepared in layers and as per Bureau of Indian Standard
(BIS) Code.
(c) The prints of drawings shall be on one side of paper only.
(3) Site plan.- Site plan fully dimensioned shall be drawn to a scale of not less than 1:
500 for a site up to one hectare and not less than 1: 1000 for a site more than one
hectare and shall show:-
(i) boundaries of the site and any contiguous features;
(ii) direction of the north point relative to the site of the building;
(iii) streets or roads adjoining the site with their width clearly dimensioned and
names, if any, giving also all existing roads, trees, lamp posts or any other
feature or structure likely to affect the approach to the building;
(iv) outlines of the proposed building;
(v) immediate neighbours on all sides identified, whether buildings or vacant plots;
(vi) levels of the site and the plinths of the building in relation to those of the
neighbouring roads and also the level of courtyard and open space;
(vii) area calculations such as ground coverage, Floor Area Ratio and Non Floor
Area Ratio, parking calculations, any other relevant calculations as required;
(viii) all existing buildings or structures on or over or under the site or projecting
beyond it;
(ix) proposed access points on site boundary for the proposed construction;
(x) methods of disposal of waste water, sewerage and storm water;
(xi) surroundings up to a distance of fifteen metres on all sides from the boundaries
of the site;
(xii) prominent trees in the area of the drawing and any important urban service
points above or under ground (like sewer or water pipes, gas pipeline,
transformers, electric poles or lines, phone distribution boxes, etc.);
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2384
(xiii) such other particulars as may be specified by the competent authority;
and
(xiv) plot number or revenue particulars of the property on which the building
is intended to be erected.
(4) Building plans, sections and elevations.- The building plans, sections and
elevations shall be drawn to a scale of 1:100. The building plans and details so
drawn shall show -
(i) the plans of all the floors including basements and all external elevations
and cross sections illustrating distinctly all the different levels and minimum
one section through staircase, water closet, bath, kitchen and garage;
(ii) the plinth level of the building with reference to the level of the mean
level of street from where approach to the site is taken;
(iii) the schedule indicating the size of the doors, windows, openings and
other methods of ventilation of each room or area;
(iv) the use or occupancy of all parts of the buildings;
(v) the means of access to the buildings and to its various floors as well as
the means of escape in case of fire, if required under the specific law or
code; along with ramps and steps with respect to the building;
(vi) in case of proposed additions and alterations in the existing building, all
new works shall be shown on the drawings in distinctive colours along
with index;
(vii) exact location of essential services, for example, water closet, sink, bath
and the like;
(viii) the method of disposal of waste water, sewage, storm water and water
supply in detail;
(ix) provision of rain water harvesting system in accordance with rule 40
(wherever applicable);
(x) provision for photovoltaic solar power plant in accordance with these
rules (wherever applicable);
(xi) provision for barrier free build environment for persons with disability
and elderly persons in accordance with these rules (wherever applicable);
(xii) indications of the north point relative to the plan.
Note: The requirement of 1:100 is permitted to be flexible for specific details
needed for further illustration; and also for drawings for these in electronic form.
In case any detail in building plan is not readable, the same can be shown in enlarged
form with clouding of that area.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2385
(5) Standard design and architectural controls.- Where the applicant intends
to construct a building in accordance with a standard design, approved by the
competent authority concerned, he shall obtain a copy of the same before
starting the construction and notify the competent authority accordingly of the
site and design. In such cases, he shall not be required to submit any building
plan. However, the site plan showing access, building footprint and all other
aspects in accordance with sub-rule (3) should be submitted. Only the design
plans can be indicated referring to standard design names or numbers:
Provided that if the owner proposes certain permitted modifications in
the standard design or the architectural controls, then he shall submit the same
to the competent authority for approval.
Note: For any urban area within the State of Punjab, notified in the Master
Plan as a “Special Area” of planning for any special purpose by virtue of
historical, functional, natural features or any other significance, for which a
Form Based Codes (FBC) or Regulating Plan has been prepared and notified
by the concerned Local Authorities, provisions under sub-rules (3), (4) and
(5) shall be in accordance with such Form Based Codes (FBC) or Regulating
Plan superseding any other general development norms and standards
stipulated in these Building Rules.
12 Procedure for submitting application through self-certification.- (1) The
self-certification is applicable on the following category of buildings, namely:-
(i) Residential plot having size upto 1000 sq.yd (836 sq.m);
(ii) Industrial plots having size upto 1000 sq.yd (836 sq.m); and
(iii) Commercial plots such as shop-cum-office (SCO), shop-cum-flat (SCF),
Shops and Booths within approved layout for which standard design has
been approved by the competent authority.
(2) Procedure.- (i) Any person intending to erect or re-erect building shall apply
through an architect in Form ‘A’ along with documents specified in rule 11 to
the competent authority for approval of building plans duly signed with stamp
of “sanctioned”, under self-certification by giving thirty days notice to the
competent authority for record of building plans intimating the date of start of
construction. The construction of proposed building can be started after thirty
days, in case any objection is not conveyed to the applicant.
(ii) The plan submitted shall conform to the provisions of these rules as amended
from time to time and approved zoning plan. In this regard, a certificate shall
be given on the plan as under, namely:-
“Certified that the above building plan is as per the zoning plan
Drg. No. ........ dated..... and as per the Punjab Urban Planning and
Development Building Rules, 2021 as amended from time to time.”
Architect/Civil Engineer
Seal with signature
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2386
(iii) Certificate of conformity to regulation and structural safety for the relevant buildings
(depending upon type and height) in the relevant Form.
(iv) After receiving the above documents, the competent authority issues an auto-
generation receipt mentioning that documents have been received and are being kept
in the office for record with this understanding that these plans have been prepared
as per the provisions of approved zoning plan and these rules. The competent authority
shall also convey within thirty days to the applicant regarding discrepancies in the
building plans and the applicant shall be bound to rectify the discrepancies in building
plans and shall submit the same before start of the construction otherwise submitted
plan shall be taken as deemed approved.
(v) The competent authority or any other person authorized by him reserves the right to
check the building plans and construction at any stage and violations (except
compoundable ones), if found, shall have to be rectified by the owner or applicant.
In case the owner or applicant fails to rectify the violations, the competent authority
may take necessary steps to remove the violations and the action shall also be taken
against the defaulting Architect or Civil Engineer by referring his case to the Council
of Architecture or Institute of Engineers of misconduct and for debarring or blacklisting
the Architect or Civil Engineer from doing all practice, especially for the Departments
of the State Government or Authorities. All rectifications shall be at the risk and cost
of the owner and no plea of the owner shall be entertained for any default committed
by the Architect or Civil Engineer engaged by him. In all such cases, the procedure
of self-certification shall stand aborted.
(vi) If a building is erected or re-erected or construction work is commenced in
contravention to any of the building regulations, the competent authority or any
other person authorized by him shall be competent to require the building to be
altered or demolished, by a written notice delivered to the owner. Such notice shall
also specify the period during which such alteration or demolition has to be completed
and if the notice is not complied with, the competent authority or any other person
authorized by him may demolish the said building at the expense of the owner.
Notes:-
(a) The decision of the competent authority, in case of any dispute, shall be final
and binding on all concerned.
(b) At any stage during construction, if an Architect or Civil Engineer notices
that violations (except compoundable ones) are taking place, he shall intimate
to the concerned authority of such violations and stop further supervision.
He shall also intimate the allottee about the violations and advise him to
stop further construction. Complete details along with photographs shall be
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2387
submitted to the concerned authority. The competent authority shall
immediately issue a notice to the owner on the basis of the Architect’s
or Civil Engineer's certificate to suspend further work and rectify
violations. In such cases, the owner shall be held responsible for further
additions in violations. Such a situation shall automatically annul the
process of self-certification and the owner may, after removal of
violations, engage an Architect or Civil Engineer for preparing the
revised drawings. In such case, completion shall be given only after
scrutiny of revised drawings and inspection of site.
(c) The compoundable changes shall be allowed to be done, provided that
at the completion stage all changes are incorporated by the Architect or
Civil Engineer in the completion drawings to be submitted by the owner
to the competent authority. While seeking completion certificate, the
Architect or Civil Engineer shall give a certificate that all changes
done are in accordance with these rules and policies of the Government
as amended from time to time.
(d) After submission of application or during the construction of building,
if the Owner or Architect or Civil Engineer or Structural Engineer are
changed, the applicant shall intimate the competent authority by email
or online building plan approval system that he is no longer responsible
for the project from the date of actual dispatch of the letter. The
information must be sent within seven days of occurrence of the change
to the competent authority by the respective owner or Architect or
Engineer. The construction work shall have to be suspended until the
new owner or Architect or Civil Engineer or Structural Engineer, as
case may be, undertakes the full responsibility of the project vide forms
and documents submitted at the time of applying for erection or re-
erection of the building within seven days of his taking over. The owner’s
intimation regarding change of name of professionals shall be considered
to be final by the competent authority or any other person authorized
by him.
13 Preparation of building plans of the Departments of the Government.-
The Department of the Government intending to erect or re-erect building
shall get their building plans prepared from the Department of Architecture of
the State Government or Central Government, as the case may be, conforming
to these building rules and shall issue a certificate specifying that the provisions
of these building rules have been followed in all respects. Such plans shall be
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2388
submitted to the competent authority for information and record before
commencement of erection or re-erection of the building.
However, if the building plans are prepared by the private Architect or Civil
Engineer, the same shall be submitted to the competent authority for approval.
14 Completion certificate. – (1) The applicant shall submit a notice of completion
of the building to the competent authority regarding completion of the work as
per approved plans. The notice of completion shall be submitted by the owner
through the Architect and Engineer as engaged for building plan design who
fulfills the specified qualifications mentioned in Annexure 13, or as the case
may be, who has supervised the construction, in the Performa given in Form-
‘F’ and ‘G’ respectively (Annexure 6 and Annexure 7), accompanied by three
copies of completion plan and the following documents along with the specified
fee, namely:-
(i) copy of all inspection reports of the Authority e.g. Fire Safety, Structural
Safety, Green Building (if applicable) etc;
(ii) detail of compoundable violations from the approved building plans, if
any, in the building, jointly signed by the owner, Architect and Engineer
along with demand draft of the due payment for compounding charges of
such violations at the rates specified by the competent authority shall be
submitted;
(iii) complete completion drawings or as-built drawings - certified by the
Architect and Engineer;
(iv) photographs of front, side, rear setbacks, front and rear elevation of the
building shall be submitted along with photographs of essential areas like
cut outs and shafts from the roof top. An un-editable compact disc or
DVD or any other electronic media containing all photographs shall also
be submitted;
(v) structural stability certificate duly signed by the Structural Engineer;
(vi) certificate of fitness of the lift from concerned Department wherever
required;
(vii) certificate from the Punjab Energy Development Agency (PEDA) for
installation of Rooftop Solar Photo Voltaic Power Plant in accordance to
orders or policies issued by the Renewable Energy Department from
time to time;
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2389
(viii) completion certificate or final Certificate or no objection certificate from the
rating agencies (GRIHA/LEED/IGBC) for green building or Bureau of Energy
Efficiency (BEE), Certified Energy Auditor for Green Building or constructing
building in accordance to the provision of the Punjab Energy Conservation and
Building Code, wherever applicable;
(ix) no objection certificate (NOC) of fire safety of building from concerned Fire
Officer or an officer authorized for the purpose; and
(x) any other information or document that the Authority may deem fit.
(2) The ‘completion certificate’ or ‘partial completion certificate’ shall be issued on the
basis of the following parameters, namely: -
(i) the applicant shall remove or demolish any temporary building which might
have been erected and the debris from the site and adjoining roads or vacant
site before the completion certificate is issued;
(ii) the partial completion certificate may be granted for partially constructed building
with at least one habitable room, one water closet and one kitchen as per the
sanctioned plan and duly functional in case of a residential house;
(iii) the partial completion certificate may be granted for partially constructed non-
residential buildings subject to the minimum completion of 25 percent
construction of the availed total floor area along with all the required public
utilities and public safety measures;
(iv) the partial completion certificate to shop-cum-offices or shops may be granted
subject to the condition that construction of ground floor is completed along
with public safety measure;
(v) in case of large campus or complex, completion of individual block or building
shall be issued by the competent authority in accordance with the construction
work completed phase wise;
(vi) in case of high rise buildings, partial completion certificate shall be issued if the
superstructure of the building has been constructed as per approved plans
along with all the required parking, public utilities, public safety etc. measures
of the proportionate area completed on site; and
(vii) the minimum permissible covered area as mentioned below shall have to be
constructed to obtain partial completion certificate for industrial buildings:
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2390
Minimum permissible ground coverage to obtain partial completion certificate for
industrial buildings
Serial Number Area of site Percentage of permissible ground
coverage
I. Upto 2 acre 25 percent
II. Above 2 acre upto 5 acres 20 percent
III. Above 5 acres 15 percent
(3) The competent authority on receipt of the notice of completion shall inspect the
work and communicate the approval or refusal, or objection thereto, in the Performa
given in Form- ‘H’ within thirty days from the receipt of notice of completion.
However, the competent authority may also seek compounding charges of
compoundable violations which are compoundable before issuance of completion
certificate. If nothing is communicated within this period, it shall be deemed to have
been approved for completion provided that the fact is immediately brought to the
notice of the competent authority in writing by the person, who had given the notice
and has not received any intimation from the competent authority within the specified
period. Where the completion certificate is refused, the reasons shall be intimated
for rejecting in the first instance itself.
(4) If the Architect or Engineer engaged by the owner or applicant submits a wrong
report while making application under these rules or if any additional construction or
violation is reported to exist at site or has concealed any fact or misrepresented
regarding completion of construction of building along with its eligibility for seeking
completion certificate or before the completion of such report, he shall be jointly
and severally held responsible for such omission and complaint against the Architect
or Engineer for suspension of his registration and the owner shall be liable to pay for
the penalty as may be decided by the competent authority after giving an opportunity
of hearing. Further, if it is emerged that the information is concealed by the Architect
or Engineer, necessary penal proceedings shall be initiated along with debarring such
Engineer or Architect from practicing in the State of Punjab.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2391
PART IV
ADMINISTRATIVE CONTROL
15 Power of the competent authority to sanction or refuse erection or re-
erection.- (1) The competent authority shall refuse to sanction the erection or
re-erection of any building, if it is in contravention of any of the provisions of
these rules.
(2) The competent authority may sanction the erection or re-erection of any
building either absolutely or subject to such modification in accordance
with these rules as it may deem fit and one copy of the sanctioned plans
shall be sent to the applicant.
(3) The intimation of sanction or rejection of the building plans shall be given
in Form 'D'.
16 Presumption of sanction.- If the competent authority fails to convey approval
or rejection within a period of sixty days of the receipt from any person of a
valid application, complete in all respect to erect or re-erect a building, the
plans shall without prejudice to the provisions of these rules and the restrictions
specified for erection or re-erection of buildings, be deemed to have been
sanctioned and the applicant may proceed with the erection or re-erection of
building or carryout any development work as described in the application and
in any accompanying documents, but not so as to contravene any of the
provisions of the Act and rules made thereunder and the restriction specified
for erection or re-erection of buildings.
17 Pre-approved building applications.- Where building applications which
have been already approved by the competent authority before coming into
force of these rules and where construction is in progress and has not been
completed within the specified period of such approval, the said approval or
permission shall be deemed to be sanctioned under these rules and shall only
be eligible to re-validation under these rules, but where the construction on
site has not yet been started, the owner or applicant may get his building plans
revised after paying the requisite charges.
18 Validity period of sanction.– Every sanction for the erection or re-erection
of any building or carrying out any development work shall remain in force,
unless it is modified or cancelled by the competent authority by due process of law.
19 Submission of revised building plans in case of major alterations.- (1) If
during the construction of a building, any major deviation from the sanctioned
plan is intended to be made, approval of the competent authority for the same
Section
108 (2)
Section
108 (2)
Section
108 (2)
Section
108 (2)
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2392
may be obtained before the change is made. The revised plan showing the
deviations shall be submitted and the procedure laid down for the sanction of
building plan as specified in these rules shall be followed for all revised plans,
along with the balance scrutiny fee, if any.
(2) The building approval is not necessary for compoundable alterations or violations,
which do not otherwise violate any provisions regarding general building
requirements, structural stability and fire safety requirements of these rules.
20 Revocation of sanction.–The sanction granted under these rules can be revoked
by the competent authority, if it is found that such sanction has been obtained
by the owner by misrepresentation of material facts or fraudulent document
submitted along with the building plan application or otherwise or the majority
of construction is not being done in accordance with the sanction granted.
21 Maintenance of e-register for sanction or Registration of Building Plans.–
An online e-register shall be maintained for all building applications received,
permissions given or deemed to have been given or refused or returned under
these rules. The said register shall be available online to the public for inspection
on Departmental website.
22 Damp proof course certificate.– The owner shall submit a certification from
an Architect or Civil Engineer or by himself, in case of self-certification to the
effect that the construction of building upto damp proof course level is as per
sanctioned plan. The competent authority shall verify the certification and
shall issue consent or comments within fifteen days of receiving the certification.
The damp proof course certificate shall be deemed to be accepted, if it is in
conformity with these rules, and no consent or comments have been passed by
Competent Authority within a specified time.
23 Occupation certificate.– (1) The applicant shall apply for obtaining occupation
certificate of the building to the competent authority for which completion
certificate has already been issued as specified in Form- “I”. No owner or
applicant shall occupy or allow any other person to occupy building or part of
a building or any portion whatsoever, until such building or part thereof has
been issued Occupation Certificate by the competent authority after checking
and found fit to occupy the building.
(2) After receipt of application, the competent authority shall communicate
in writing within thirty days, his decision for grant or refusal of such
permission for occupation of the building in Form- ‘J’. The E-register
shall be maintained as specified in these rules for maintaining record in
Section
108 (2)
Section
108 (2)
Section
108 (2)
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2393
respect of Occupation Certificate. If no communication is received from the
competent authority within thirty days of submitting the application for
“Occupation Certificate”, the owner is permitted to occupy the building,
considering deemed issuance of “Occupation certificate” and the application
Form-D shall act as “Occupation Certificate”. However, the competent authority
may check the violations made by the owner and take suitable action.
(3) Revocation of occupation certificate.- In case, after the issuance of
occupation certificate, if found at any stage that the building is used for some
other purpose against the permission or make any addition or alteration in the
building without approval, then, after affording personal hearing to the owner,
the competent authority may pass orders for revocation of occupation permission
and the same shall be restored only after removal of violations.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2394
PART V
PLANNING AND ARCHITECTURAL CONTROLS
24 Compliance of zoning plan or standard design or architectural control
sheets and master plan/ zonal plan.- In addition to these rules, the erection
or re-erection of any building(s) and uses thereof as well as activities permissible
therein shall comply with the provisions of the Zoning Plan or Standard Design
or Architectural Control Sheets; schedule of clauses appended thereto and use
of the site shall conform to the Master Plan or Zonal Plan of the area.
25 Compliance to Special Area development and control as per Master Plan
or Zonal Plan.- For the planned and regulated development of all ‘Special
Areas’ with specific emphasis on harmonious development with Public spaces,
the planning and development shall be undertaken by specially formulated
Form Based Codes (FBCs) for each such ‘Special Area’, namely:-
(1) Planning authority to delineate “Form Based Zoning Districts” within the
Master or Zonal Plan for special consideration of planning with integrated
Public spaces;
(2) Form Based Zoning Districts (FBCs) to be formulated for each such
Form Based Zoning Districts (FBZDs) with Single or Multiple Regulating
Plans as necessary to cover the entire delineated special area;
(3) Space Use matrix along with Form Based Codes (FBC) development
standards, for each Form Based Zoning District (FBZD) as formulated in
the Form Based Codes (FBC) are to be used for site layouts and building
designs for all types of buildings; and
(4) Form Based Codes (FBC) standards of flexible and adaptive designs
shall be superseding, overriding all stipulations from rule 3 to rule 8 of
these rules for all types of buildings in the respective Form Based Zoning
Districts (FBZDs).
26 General Planning/ Development Norms.-
(1) Setbacks and Height of other buildings.– For buildings other than residential
plotted or independent floors or row type buildings or crèche or pre nursery or
nursery school or farm house, the set back around the building(s) or outer
open spaces shall be as given in the Table below: -
Section
108 (2)
Section
108 (2)
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2395
Minimum Setback or Open Space Around Buildings
Serial Height of Setback all
Number building (m) around
building (m)
I. 10 3
II. 14.99 5
III. 18 6
IV. 21 7
V. 24 8
VI. 27 9
VII. 30 10
VIII. 35 11
IX. 40 12
X. 45 13
XI. 50 14
XII. 55 16
XIII. 70 17
XIV. 120 18
XV. Above 120 20
Notes:
(a) In case of industrial buildings (except I.T. buildings), the open spaces around
the building shall not be less than 4.5m for height upto 15 m, with an increase
of the open spaces of 0.25 m for every increase of 1 m or fraction thereof in
height above 15m. However, for industrial plots (including I.T Buildings)
upto 2025 sq.m area where width of the plot is less than 30.50 m (100'-0"),
the front and rear set back shall be ¼ of the height or 2m whichever is more
are mandatory. The side setbacks may be relaxed subject to the condition that
the owner has to submit a fire safety certificate from the competent authority
in this regard.
(b) Where rooms do not derive light and ventilation from the exterior open space,
the width of such exterior open space as given above may be reduced by 1 m
subject to a minimum of 3m and a maximum of 8m.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2396
(c) In case of Residential Group Housing, if the length or depth of the building
exceeds 40 m, add to the above Table ten percent of length or depth of building
minus 4.0 m subject to maximum requirement of 20 m.
(d) For high rise buildings and special buildings as specified in rule 30(11)
(see Part4 Fire and Life Safety' of the National Building Code of India, 2016
as amended from time to time), the approach to the building and open spaces
on all sides shall not be less than 6 m.
(e) For buildings other than residential plotted or independent floors, industrial
plotted or general industrial buildings, or hazardous building, minimum setback
from the boundary shall be 6 m or as shown in zoning plan whichever is more.
However, for the plots upto 2025 sq.m area where width of the plot is less
than 30.50m (100'-0") and the maximum height of building is below 15m
excluding the architectural and symbolism element of religious building like
dome, minarets, sikharas, crucifix etc. from building height then one side
setback may be relaxed subject to the condition that the owner has to submit
a fire safety certificate from the competent authority in this regard.
However, if the corner plot upto 2025sq.m in size, the side setback
adjoining to the side road may be relaxed and shall not be less than 3 m from
the boundary subject to the following conditions, namely:
(i) Minimum road width of side road shall not less than 9m.
(ii) Minimum setback of the building shall be governed as per table above
from the centre of the adjoining side road for this side.
(iii) This relaxation shall be applicable only for one time for one side and
not applicable for front and rear side.
(iv) The height of the boundary wall including railing for this side shall not
be more than 2m.
(v) No objection certificate from Fire Department is required for this
relaxation.
(f) In Tower like/ recessed building(s) deficiency of setbacks shall be achieved
through additional setbacks at upper levels.
(2) Setback of projected portion of roof level.- The projected portion of parapet,
flues, ducts, water storage tanks, mumties, minarets, domes, water cooling tanks,
lift rooms exceeding 2.75 meters in height shall be receded from the facade by a
minimum distance equal to their height above roof level, failing which these shall be
counted in calculating the height of the building as well as covered area.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2397
(3) Projection and Balcony.-
Projections
Serial Size of Plot Maximum allowable projection
Number (free from ground coverage and floor area ratio)
I. Upto 250 sq.mt. Shall not be more than one-third of the corresponding
depth of front or rear setback or 0.91 meters (3'-0"),
whichever is less.
II. Above 250 sq.mt. 1.83 meter (6'-0")
Balcony
Serial Size of Plot Maximum allowable projection
Number (free from ground coverage and floor area ratio)
I. Upto 250 sq.mt. Shall not be more than one-third of the corresponding
depth of front or rear setback or 1.22 meters (4'-0"),
whichever is less.
II. Above 250 sq.mt. 1.83 meter (6'-0")
Note:
(a) The projection on door and window shall not exceed 0.91 meters. (3'-0").
(b) The projection shall not be at a lesser height than 2.06 meters (6'-9") clear
above the plinth level of the building.
(c) In case of corner plots, sunshade not exceeding 0.60 meters (2 feet) on window
opening on to the side shall be permitted at a height not less than 2.06 meters
(6'-9).
(d) If the projection or balcony is provided more than the provision of above
Tables. then the area of the additional projection shall be counted toward
Floor Area Ratio.
(e) Wrap around continuous balconies shall be allowed as long as their area
does not exceed 50 percent of the total open area.
(4) Parking.- (i) Parking of vehicles shall be permissible as given below: -
(a) Surface Parking.
(b) Under stilts of building(s).
(c) Under Basement or Multilevel Basement of the building(s):
Provided that the provisions of the basement shall be in
accordance with sub-rule (5) of rule 30 of these rules.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2398
(d) Under podium of a building(s):
The provisions of the podium shall be in accordance with
provisions of the National Building Code of India, 2016, as
amended from time to time.
(e) Under separate multi-level parking block maximum up-to 20
percent of the plot area and such area shall not be counted
towards Floor Area Ratio.
(ii) Minimum 10 per cent of the total required parking shall be surface parking on
ground level.
(iii) Upto 20 percent of the total required parking shall be allowed as mechanical
parking, except in residential buildings. However, it shall be provided fully
automatic in which lower cars do not have to be manually moved out to take
out the cars parked in upper stacks. Mechanical parking shall be permitted
subject to mechanical and structural safety and should be covered with
permanent or temporary roof structure:
Provided that to establish the automatic stacks, brochure showing the
working of the stacks shall be taken as part of application for the approval of
building plans and completion certificate shall be issued only after verifying
that the installed stacks parking works accordingly.
(iv) Parking in independent floors under stilts shall be permissible beyond stilts
within the plot area, if the parking under stilts is not sufficient as per norms.
Clear height from the finished level of the ground floor to the under surface of
the beam, joint girders or any other horizontal structure member shall be 7’-6”.
(v) In case parking is provided under stilts or podium or basement, it shall not be
counted towards Floor Area Ratio and height for calculating the setback of the
building for light and ventilation only.
(vi) Parking spaces shall be paved and clearly marked for different types of vehicles.
(vii) In buildings of mercantile (commercial), industrial (except Information
Technology Industry) and storage type, in addition to the parking spaces
provided, a space at the rate of 3.5 m × 7.5 m, shall be provided for loading
and unloading activities, for each 1000 m2 of floor area or fraction thereof.
(viii) For the provision of car parking spaces, the space standards shall be as under.-
(a) For open parking: 23 square meters per equivalent car space.
(b) For ground floor covered parking: 28 square meters per equivalent car space.
(c) For basement or podium or multilevel floors: 32 square meter per
equivalent car space.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2399
(ix) Vehicular ramp is mandatory in accordance with sub-rule (12) of rule 30 for
multilevel parking i.e. stilt or basement or podium, if used for vehicular parking.
However, in case of car showrooms or car workshops, car lift may be allowed
subject to condition that the plot area is not more than 3000 sq.m.
(x) In the case of parking spaces provided in basement(s) or multilevel podium (s)/
floor(s) at least two ramps of width and slope in accordance with sub-rule
30(12) of rule 30 shall be provided, located preferably at opposite ends.
(xi) If there is any doubt regarding the category of any building, for the purpose of
calculation of parking the decision of the Government shall be final. Parking
for the disabled persons shall comply the provisions of the Rights of Persons
with Disabilities Act, 2016 (Central Act 49 of 2016), National Building Code of
India, 2016 and Harmonised Guidelines and Space Standards for Barrier-Free
Built Environment for persons with Disability and Elderly Persons, 2016.
(5) Exemptions.- (i) Exemptions from Ground Coverage:-
(a) Canopy/ porch maximum upto 100sq.ft,
(b) watch and ward cabins upto 100sq.ft along each entry gates;
(c) Atrium/atria, escalator/ travellator well, covered sky bridges in high rise buildings,
jogging tracks, swimming pools (open to sky), architectural features or elements
such as, coffers, louvers, end wall projected upto 900 mm;
(d) Pergolas, other sunshade elements, any landscape element;
(e) Fire Staircase, fire towers, ramp;
(f) Podium(s) or multi-storey podium, stilt, separate parking block, basement if
used for parking and the services like sewerage treatment plant, water treatment
plant, garbage collection, electrical sub-station, service ducts,
(g) Service area block having services such as Diesel Generator (DG) room, Air
Conditioning (AC) plant room etc. No habitable rooms are allowed to be made in
any of the items above. If they are, then they shall be part of the Ground Coverage.
(ii) Exemptions from Floor Area Ratio (FAR):
(a) Canopy/projections upto 100 sq.ft.;
(b) watch and ward cabins upto 100 sq.ft along each entry gates;
(c) Atrium/atria, covered sky bridges or intermittent floors as relief in high rise buildings;
(d) Area on habitable floor for providing services like Heating, Ventilation and Air
Conditioning (HVAC), Mechanical Electrical and Plumbing (MEP) installations,
Janitor rooms, Air Handling Unit (AHU) room, Air Conditioning (AC) plant
room, electric installations, Low Tension (LT) panel room, Closed Circuit
Television (CCTV) room or any other similar services;
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2400
(e) Architectural features such as coffers, louvers, end wall projected upto 900
mm, pergolas, other sunshade, elements;
(f) Any landscape element, podium(s) or multistorey podium or basement or stilts
of building(s) if used for parking and services like water tank or water works,
sewerage treatment plant, water treatment plant, garbage collection, electrical
sub-station, Diesel Generator (DG) room and service ducts,
(g) Ramp, fire exit stair cases or fire towers, fire refuse area (as per the National
Building Code of India, 2016 as amended from time to time), toilet blocks for
visitors or drivers or guards on ground floor only, cupboards upto depth of
0.6m and 1.8m length shall be exempted from Floor Area Ratio.
(h) The width of corridors and staircases provided in addition to their minimum
required width shall be exempted from floor area ratio:
Provided that the area of lift wells, service shaft shall be taken on one floor:
Provided further that in multi-storey buildings, service floors shall be allowed
after minimum four floors. Maximum of three service floors shall be allowed in a
building. The area of service floors shall not be counted towards floor area ratio and
maximum height of such floors shall be 2.40m from floor to bottom of the beam.
Any habitable rooms made along with any of the items above shall be taken as
part of Floor Area Ratio.
(iii) Exemptions to projections into open spaces.- Every open space provided either
interior or exterior shall be kept free from any erection thereon and shall be open to
the sky, except as given below:
(a) Cornice, roof or weather shade not more than 0.75 m wide;
(b) Sunshades over windows or ventilators or other openings not more than 0.75
m wide;
(c) Canopy not to be used as a sit out with clearance of 1.5 m between the
plot boundary and the canopy;
(d) Projected balcony at higher floors of width not more than 1.83 m;
However, these projections into open spaces shall not reduce the minimum
required open spaces and hinder the fire tender movement.
(iv) Exemption to accessory use buildings.- The following accessory use buildings
may be permitted in the open spaces:
(a) In an existing building, sanitary block of 2.4 m in height subject to a maximum
of 4m2 in the rear open space at a distance of 1.5 m from the rear boundary
may be permitted, where facilities are not adequate.
(b) Parking lock up garages not exceeding 2.4 m in height shall be permitted in the
side or rear open spaces at a distance of 7.5 m from any road line or the front
boundary of the plot;
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2401
(c) Suction tank and pump room each up to 2.5 m2 in area.
(d) Meter Room (Power supply) or Diesel Generator (DG) set room, Rain
water harvesting Pit, Check post, Waste or Garbage collection room,
Covered parking for car or motorcycle or cycles, Pump room or
Underground tank or Overhead tank, Cooling Towers for Heating,
Ventilation and Air Conditioning (HVAC) Plant and Diesel Generator (DG)
set, Sewer treatment plant and water treatment plant may be allowed in
rear and side setback of the site subject to that they cannot hinder the fire
tender movement with minimum 6m setback from the building(s) and the
maximum height of these structure shall not more than 2.75m.
27 General Notes.- (i) For projects proposed within the “Special Area” as defined
or delineated in the Master Plan or Zonal Plan, the Development regulations of
Height, Floor Area Ratio, Ground Coverage and any other building controls
stipulated in these rules for general buildings shall be superseded by site-specific
Form Based Code prepared and notified by the competent authority under the
Punjab Regional and Town Planning and Development Act,1995 and the
provision of rule 3 to rule 8 of these rules shall be superseded by relevant Form
Based Code or Regulating Plans.
(ii) For projects proposed within the Prohibited and Regulated areas as defined
in the Ancient Monuments and Archaeological Sites and Remains Act,
2010, the development regulations of Height, Floor Area Ratio, Ground
Coverage and any other controls stipulated in these rules for general
buildings shall be superseded by site specific Heritage Bye-Laws prepared
and notified by the competent authority or the National Monuments
Authority under the said Act of 2010. No Objection Certificate shall
have to be obtained in accordance with the rules framed under the said
Act by submission of required documents as may be necessary vide
rules, including “Heritage Impact Assessment” report, if so necessitated
by the National Monuments Authority.
(iii) The premises for which building regulations have not been formulated
shall be examined by the competent authority on the basis of actual
requirements and other relevant factors. Activities or uses for which these
rules are silent shall be governed by the National Building Code of India,
2016, as amended from time to time and where the National Building
Code of India, 2016, as amended from time to time are silent; Norms or
Guidelines of Model Building Byelaws, 2016, as amended from time to
time shall be followed.
(iv) The provision of minimum setbacks for different sizes of plots for all
categories of the plots if not specified in these rules shall be in accordance
with the provisions of the Zoning Plan of the said site.
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2402
(v) The area requirements of each type of educational institutions wherever
not specified shall be in accordance with the norms or guidelines issued
by the affiliating authority for such institutions.
(vi) The Punjab Energy Conservation Building Code notified by the
Government of Punjab, Department of New and Renewable Energy vide
Notification No. 18/4/16-6;1/1856, dated the 24th June, 2016, as amended
from time to time, wherever applicable shall be adhered to the buildings
in additions to these rules.
(vii) The setting up of the Petrol Pumps, Brick Kiln, Rice Sheller, Stone
Crusher, Cinema, Multiplex, Economical Weaker Section Houses,
Affordable Housing, Communication Towers, Iconic building, Low Density
Country Homes, Housing for All, Ancient Building and any other activity
not specifically mentioned in these rules, shall be governed by the relevant
respective Acts or rules or notifications or policy guidelines or norms of
the Department of Housing and Urban Development, Punjab or any
other department concerned, as the case may be.
(viii) In addition to these rules, Guidelines or Notifications as amended from
time to time issued by the Punjab Pollution Control Board (Department
of Science, Technology and Environment, Government. of Punjab) and
the Department of Forests and Wildlife Preservation, Punjab shall be
applicable, where ever required.
(ix) No sub-division of the land or site would be subsequently permitted.
(x) The specific approvals shall be obtained from Airport Authority of India,
National Highway Authority of India, Ministry of Environment, Forest
and Climate Change, Fire Services Department, Pollution Control Board,
designated authorities under the Factories Act, 1948 or the Punjab Cinemas
(Regulation) Act, 1952, Archaeological Survey of India, Heritage
Committee and any such other authority, as may be applicable. Approval
of Fire Services Department shall be required for buildings of height 15
m or above and for such other buildings or special buildings referred to in
Part 4 – Fire and Life Safety of the National Building Code of India,
2016, as amended from time to time.
(xi) In case the height of building or structure is 15 m or more, then ‘No
Objection Certificate’ from Airports Authority of India or Indian Air Force
is required.
Further provided that if, site falls in the red colour of home grid of
Colour Coded Zoning Map issued by Airports Authority of India or Indian
Air Force, then irrespective height of the building or structure, it is
mandatory to get ‘No Objection Certificate’ from Airports Authority of
India or India Air Force, as the case may be.”
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2403
PART VI
GENERAL BUILDING REQUIREMENTS
28 Occupant Load.- The occupant load of any building shall be calculated as
under, namely:-
Occupant Load
Serial Type of occupancy Occupant load factor (sq.m
Number per person)
I. Residential 12.50
II. Educational 4.00
III. Institutional
Indoor patient area 15.00
Outpatient area 10.00
IV. Assembly:
Concentrated use without 0.65
fixed seating
Less concentrated use 1.40
without fixed seating
Fixed seating Multiplying the number of seats
by 1.2
Dining areas and restaurants 1.80
with seating and table
V. Mercantile:
Street floor and sales 3.00
basement
Upper sales floor 6.00
Storage/warehouse, 20.00
receiving and the like
VI. Business 10.00
VII. Industrial Calculated on the basis of Detailed
VIII. Storage Project Report (DPR) approved by
IX. Hazardous labour Department plus 10 percent addition
of it.
However, if DPR is not approved by the
labour Department then applicant shall
submit the undertaking in this regard as
per annexure 22.
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2404
Notes:-
(a) Gross area shall be the floor area as defined in clause (lxxviii) of
sub-rule (1) of rule 2 of these rules. All factors expressed are in gross
area unless marked net.
(b) Occupant load in dormitory portions of homes for the aged,
orphanages, insane asylums, etc, where sleeping accommodation is
provided, shall not be calculated at less than 7.5 m2 gross floor area/
person.
(c) For the purpose of public health facilities like W.C., urinal, washbasin,
drinking water fountain, ablution tabs etc., occupant load shall be
calculated on floor area ratio.
29 Clearance zone for buildings near High Tension Electrical Line.- The
building shall not be constructed within the clearance zone. The clearance
zone shall be in accordance with the guidelines of Punjab State Power
Corporation Limited (PSPCL) and in accordance with the table given below,
as amended from time to time:
Clearance Zone for buildings near High Tension Electrical Line
Type of supply line Type of supply line Horizontal
clearance (in meters) (including
both sides and from the centre
line of the tower)
High voltage lines up to 11 KV 11.5
High voltage lines above 11 KV 15.0
and up to 33KV
High voltage lines above 33 KV and 18.0
up to 66KV
High voltage lines above 66 KV 27.0
and up to 132KV
High voltage lines above 132 KV 35.0
and up to 220KV
High voltage lines above 220 KV 52.0
and up to 440KV
30 Part Building requirement.-This part sets out the standard space requirements
of various parts of a building (for all types of buildings-low/high rise), namely:-
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2405
(1) Plinth.- The plinth level for building (s) shall be computed from the crown of the
adjoining road in front or as specified by the Competent Authority from time to
time. Interior court yard shall be raised at least 150 mm above the determining
ground level and shall be satisfactorily drained.
(2) Lighting and ventilation of rooms.-
(a) If a window is partly fixed, the openable area shall be counted.
(b) No portion of a room shall be assumed to be lighted, if it is more than 7.5 m
away from the opening assumed for lighting that portion.
(c) The area of openings above shall be increased by 25 percent in the case of a
kitchen.
(d) In bathroom or water closet have a window or ventilator, opening to a shaft
or open space, of area not less than 0.3 m2 with side not less than 0.3 m.
(e) No room containing water-closets shall be used for any purpose except as a
lavatory and no such room shall open directly into any kitchen or cooking
space by a door, window or other opening. Every room containing water-
closet shall have a door completely closing the entrance to it.
(f) Mechanical light and ventilation shall be permissible in accordance with the
National Building Code of India, 2016, as amended from time to time.
(3) Ledge or Tand. – (i) Height.- The minimum head-room of ledge or Tand or loft
shall be 2.2 m. The maximum height of loft shall be 1.5 m.
(ii) Size.- A ledge or Tand or loft in a habitable room shall not cover more than 25
percent of the area of the floor on which it is constructed and shall not
interfere with the ventilation of the room under any circumstances.
(4) Mezzanine Floor.- (i) Height.- It shall have a minimum height of 2.2 m. with no
beams or protuberances below 1.8 m.
(ii) Size.- The minimum size of the mezzanine floor, if it is to be used as a living room,
shall not be less than 9.5 m2. The aggregate area of such mezzanine floor in a
building shall in no case exceed one-third the plinth area of the building.
Notes:-
(a) A mezzanine floor may be permitted over a room or a compartment;
(b) It conforms to the standard of living/ habitable rooms as regards lighting and
ventilation in case the size of mezzanine floor is 9.5 m2 or more;
(c) It is so constructed as not to interfere under any circumstances with the
ventilation of the space over and under it;
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2406
(d) Such mezzanine floor is not subdivided into smaller compartments;
(e) Such mezzanine floor or any part of it shall not be used as a kitchen; and
(f) In no case shall a mezzanine floor be closed so as to make it liable to be
converted into unventilated compartments.
(5) Basement.- (i) The multi-level basement in plots of an area above 2025 sq.m shall
be allowed below the ground and beyond the building line at ground level subject to
a clear minimum front margin of 4.5 m and side and rear margins of 3 m, subject to
the provision of mechanical ventilation and all safety provisions and drainage.
However, it is essential that the basement top slab below the external circulation at
ground level should be designed for fire fighting vehicular loads as given in clause
4.6 of Part III of the National Building Code of India, 2016, as amended from time
to time. The owner or the applicant, as the case may be, shall be bound to execute
indemnity bond in the favour of competent authority as specified in Annexure 21.
(ii) In case of plot size upto 2025 sq.m, single story basement is allowed upto
zoned area or upto the boundary of the plot except front and rear side, as the
case may be, subject to the condition that the owner shall leave minimum 2.44
m (8'-0") setback from the respective side of the boundary wall of the plot, if
adjoining plot has a building upto 2.44m from the plot line.
(iii) The basement shall not be allowed in the case of No construction Zone or Area
or Master Plan Green area or any other restricted area or zone under the
provision of any other Act or policy of the State or Central Government.
(iv) Other conditions:.- The following are the conditions for the basement, namely:-
(a) First level basement area may be used for habitable purposes subject to the
condition that mandatory parking norms are fulfilled and compliance of all
requirements for fire safety in accordance with Part 4- Fire and Life Safety of
the National Building Code of India, 2016, as amended from time to time and
necessary measures for required lighting, ventilation and water supply, drainage
and sanitation is ensured;
(b) The minimum height of basement shall be 2.40 meters measured from the
finished level of the floor to the under surface of the beam, joist girders or any
other horizontal structural member. However, if basement is used for habitable
purpose than the minimum height and space requirement of that area shall be
in accordance with these rules;
(c) Adequate ventilation shall be provided for the basement. Any deficiency may
be met by providing adequate mechanical ventilation in the form of blowers,
exhaust fans, air conditioning system and conform to fire safety and structural safety;
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2407
(d) The minimum height of the ceiling of first level basement shall be 0.9 meters
and maximum 1.2 meters above the average surrounding ground level, except
convenient shopping and residential plots. However, if sunken court is provided
for light and ventilation or stilt is provided for parking or then the same shall
not be mandatory;
(e) Adequate arrangement shall be made that surface drainage does not enter the
basement;
(f) There shall be provisions of sufficient doors in case the basement is used for
habitable purposes and maximum travel distance from any point to the door
shall not exceed 15 meters;
(g) In case, where the basement is allowed beyond the building envelope in
accordance with sub-rule (5), then the level of the basement shall be at the
ground floor level and the slabs should be designed to bear the load of fire tenders;
(h) The walls and floors of the basement shall be watertight and be so designed
that the effects of the surrounding soil and moisture, if any, are taken into
account in design and adequate damp proofing treatment is given;
(i) The access to the basement shall be separate from the main and alternative
staircase providing access and exit from higher floors. Where the staircase is
continuous in the case of buildings served by more than one staircase, the
same shall be of enclosed type serving as a fire separation from the basement
floor and higher floors. Open ramps shall be permitted if they are constructed
within the building line subject to the provision of condition (e).
(j) In the case of parking spaces provided in basement(s), at least two ramps of
width and slope in accordance with sub-rule (12) shall be provided, located
preferably at opposite ends.
(k) Access to basements through ramps shall be permitted subject to provision of
condition (e). The requirements for the ramps shall be in accordance with sub-
rule (12) and the National Building Code of India, 2016, as amended from
time to time;
(l) For all public buildings and uses including group housing, having basement
going up to more than one level, access to all levels shall also be provided
through lift. The exit requirements in basements shall comply with the provisions
of Part 4- Fire and Life Safety of the National Building Code of India, 2016, as
amended from time to time:
Provided that in case where basement used for habitable purpose shall be
counted in Floor Area Ratio.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2408
(6) Chimneys.- The chimneys shall be built at least 0.9 m above flat roofs, provided
the top of the chimneys is not below the top of the adjacent parapet wall. In the case
of sloping roofs, the chimney top shall not be less than 0.6 m above the ridge of
the roof in which the chimney penetrates.
(7) Cabin.- The size of cabins shall not be less than 3.0 m2 with a minimum width of
1.0 m. The clear passages within the divided space of any floor shall not be less than
0.75 m and the distance from the farthest space in a cabin to any exit shall not be
more than 18.5 m. In case, the sub-divided cabin does not derive direct lighting and
ventilation from any open spaces or mechanical means, the maximum height of the
cabin shall be 2.2 m.
(8) Boundary wall.- (i) In case of corner plot, radius of corner boundary wall shall be
minimum 5’-0” or 1/8th of the width of the adjoining road whichever is more and
maximum upto 20’-0” excepted residential plot or independent plots in which turning
radius shall be 5’-0”.
(ii) In industrial buildings like workshops, factories, electric sub-stations, trans
former stations and institutional buildings like sanatoria, hospitals, sports
complex, stadium, and educational buildings like schools, colleges, including
hostels, and other uses of public utility undertakings and strategically sensitive
buildings, a height up to 2.4 m may be permitted on special request of the
applicant. However, in case of security establishments, Jails, mental hospitals,
etc. where additional height of the boundary wall is required by the applicant,
the same may be allowed by the competent authority.
(iii) Boundary wall may be allowed to be constructed in No Construction Zone
after leaving the road widening, if required, subject to the condition that the
owner shall dismantle the boundary wall as and when required by any
Government agency or authority without any claim.
(9) Septic tanks.-Where a septic tank is used for sewage disposal, the location, design
and construction of the septic tank shall conform to requirements of Part 9- ‘Plumbing
Services (including Solid Waste Management) and Section 2- Drainage and Sanitation’
of the National Building Code of India, 2016.
(10) Meter rooms.-For all buildings 15 m and above in height and in special occupancies,
like educational, assembly, institutional, industrial, storage, hazardous and mixed
occupancies with any of the aforesaid occupancies having area more than 500 m2
on each floor, provision shall be made for an independent and ventilated meter
(service) room, as per requirements of electric (service) supply undertakings on
the ground floor with direct access from outside for the purpose of termination of
electric supply from the licensee’s service and alternative supply cables. The door or
doors provided for the service room shall have fire resistance of not less than two hours.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2409
(11) Staircase or exit requirements.- The number of staircases in the building(s) shall
be determined on the basis of the occupant load, travel distance, dead end restriction
subject to minimum two staircases in respect of buildings identified under these
rules:
Provided that where the travel distance and other requirements are complied
with, one shall be a fire exit staircase out of two staircases.
The following Building(s) shall have minimum of two staircases:
(i) Building(s) of 15m in height or above, and
(ii) Special buildings, such as,
(a) hotel, educational, institutional, business, mercantile, industrial, storage,
hazardous and mixed occupancies, where any of these buildings have
floor area more than 500 m2 on any one or more floors;
(b) educational buildings having height 9 m and above;
(c) institutional buildings having height 9 m and above;
(d) all assembly buildings;
(e) buildings having area more than 300 sq.m of incidental assembly
occupancy on any floor; and
(f) buildings with two basements or more, or with one basement of area
more than 500 m2.
(iii) All exit staircases shall discharge, at the level of exit discharge, to the exist
discharge, either,
(a) directly, or
(b) through an exit passageway, or
(c) through a large lobby.
At least 50 percent of the staircases shall discharge as per (a) and/or (b) above.
(12) Ramps.- Ramp requirement for vehicular movement.-
(a) Open Ramps with minimum width of 6m may also be provided in the setbacks
which can be sloped considering unhindered movement of fire engine and in
no case, the gradient shall be less than 1:10.
(b) The ramp to basement and parking floors shall not be less than 7.2 m wide for
two way traffic and 4 m wide for one way traffic, provided with gradient of 1:8
for cars and 1:15 for heavy vehicles. At curved portions of the ramp or for
circular ramps, the slope should not be more than 1:12.
(c) After a 40 m length of continuous ramp, a flat surface of minimum 6.0 m
length shall be provided.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2410
(d) All and structural design or safety aspects as per latest Bureau of Indian Standard
Codes and the National Building Code of India, 2016 shall be complied along
with consideration of weight of Fire Engine and its maneuverings.
(13) Exit Requirements.- In respect of width and travel distance, all aspects of exit
requirements for corridors, doors, staircases, ramps shall be as per Part 4- Fire and
Life Safety of the National Building Code of India, 2016.
(14) Roofs.- (i) The roof of a building shall be so designed and constructed as to
effectively drain water by means of sufficient rain water pipes of size as
specified in the National Building Code of India, 2016, as amended from time to
time wherever required, so arranged, jointed and fixed as to ensure that the rain
water is carried away from the building without causing dampness in any part of the
walls, roof or foundations of the building or an adjacent building.
(ii) The rain water pipes shall be connected to a drain or a sewer which connects
the rain-water pipe to the road gutter or in any other approved manner.
(iii) The rain-water pipes shall be affixed to the outside of the external walls of the
building or in recesses or chases cut or formed in such external walls or in such
other manner as may be approved by the Authority.
(iv) It is desirable to conserve rain water using suitable rain water harvesting
techniques including by roof water collection. For this purpose, the provisions
made in Part 9- Plumbing Services (including Solid Waste Management), Section
2 Drainage and Sanitation of the National Building Code of India, 2016 shall
be followed.
(15) Sunken courtyard.- Sunken courtyard up to 3 m in depth from the ground level
and minimum 2 m width and minimum 10 sq.m. area as ‘light well’ within zoned
area shall be permitted for light and ventilation for basement area provided that it
does not interfere with the movement of fire tenders and adequate arrangements for
drainage shall be provided.
However, for plot size upto 2025 sq.m area, sunken courtyard may be allowed
upto the boundary wall of the plot in rear courtyard subject to the fulfillment of
parking and fire tender movement as required.
(16) Fitments for drainage and sanitation.- (i) For Residences.- Dwelling with individual
convenience shall have at least the following fitments, namely:-
(a) one bath room provided with a tap and a floor trap;
(b) one water closet with flushing apparatus with an ablution tap or health faucet; and
(c) one tap with a floor trap or a sink in kitchen.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2411
(ii) The requirements for fitments for drainage and sanitation in the case of
buildings other than residences shall be in accordance with Tables as below.
Office Building
Serial Fixtures Public Toilets Staff Toilets
Num- Male Female Male Female
ber
Executive Rooms and Conference Halls in Office Buildings
I. Toilet suite comprising one Unit could be For individual
Water Closets (WC), one common for officer rooms
wash basin (with optional male/female
shower stall if building is or separate
used round the clock at depending on
user's option) the number of
Pantry optional as per user of each
user requirement facility
Main Office Toilets for Staff and Visitors
II. Water Closets (WC) 1 per 25 1 per 15
III. Ablution tab with each water 1 in each water closet
closet
IV. Urinals Nil up to 6 -
see see 1 for 7 to 20
note note 2 for 21 to 45
3 for 46 to 70
4 for 71 to 100
From 101
to 200, add
@ 3 percent ;
for over 200,
add @ 2.5
percent
V. Wash Basins 25 25
VI. Drinking Water Fountain 1 per 100
persons
VII. Cleaner's sink 1 per floor
Note:- Staff and public toilet utilities are generally common in office buildings.
Where public toilets are to be provided separately, similar requirements as that of staff
toilet may be provided.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2412
Cinema, Multiplex Cinema, Concert and Convention Halls, Theatres and Stadia
Serial Fixtures Public Toilets Staff Toilets
Num- Male Female Male Female
ber
I. Water Closets 1 per 100 3 per 100 1 for up 1 for up
up to 400; up to 200; to 15 to 12
Over 400 Over 200 2 for 16 2 for 13
add at 1 add at 2 to 35 to 25
per 250 per 100
or part or part
thereof thereof
II. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be provided for
every 50 persons or part thereof in the vicinity of water closets
and urinals
III. Urinals 1 per 25 - 1 for 1 to 20 -
or part 2 for 21 to
thereof 45
IV. Wash Basins 1 per 200 or part 1 for upto 1 for upto
thereof 15 12
2 for 16 2 for 13 to
to 35 25
V. Drinking Water 1 per 100
Fountain
VI. Cleaner's sink 1 per floor
VII. Showers/bathing As per trade equirements
rooms
Notes :-
(a) Some Water Closets (WC) may be Indian style, if desired.
(b) Male population may be assumed as two-third and female population as
one-third.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2413
Art Galleries, Libraries and Museums
Serial Fixtures Public Toilets Staff Toilets
Num- Male Female Male Female
ber
I. Water Closets 1 per 200 1 per 100 1 for up 1 for up
up to 400; up to 200; to 15 to 12
Over 400 Over 200 2 for 16 2 for 13
add at 1 add at 1 to 35 to 25
per 250 per 150
or part or part
thereof thereof
II. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be provided for
every 50 persons or part thereof in the vicinity of water closets
and urinals
III. Urinals 1 per 25 - 1 for 1 to 20 -
or part 2 for 21
thereof to 45
IV. Wash Basins 1 per 200 1 per 100 1 for 1 for
up to 400; up to 200; upto 15 upto 12
Over 400 Over 200 2 for 16 2 for 13
add at 1 add at 1 to 35 to 25
per 250 per 150
or part or part
thereof thereof
V. Drinking Water 1 per 100
Fountain
VI. Cleaner's sink 1 per floor
VII. Showers/bathing As per trade requirements
rooms
Notes :-
(a) Some Water Closets (WC) may be Indian style, if desired.
(b) Male population may be assumed as two-third and female population as
one-third.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2414
Restaurants
Serial Fixtures Public Toilets Staff Toilets
Num- Male Female Male Female
ber
I. Water Closets 1 per 50 2 per 50 1 for up to 1 for up
seats up to seats up to 15 to 12
200; Over 200; Over 2 for 16 to 2 for 13
200 add 200 add 35 to 25
at 1per at 1 per 3 for 36 to 3 for 26
100 or part 100 or part 65 to 40
thereof thereof 4 for 66 to 4 for 41 to 57
to 100 5 for 58 to 77
6 for 78 to 100
II. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be provided for
every 50 persons or part thereof in the vicinity of water closets
and urinals
III. Urinals 1 per 50 - 1 for 1 -
persons to 20
or part 2 for 21
thereof to 45
3 for 46
to 65
4 for 66
to 100
IV. Wash Basins 1 per 1 per 1 per 1 per
Water Water Water Water
Closets Closets Closets Closets
(WC) (WC) (WC) (WC)
V. Cleaner's sink 1 per restaurant
VI. Kitchen sink/ 1 per kitchen
dish washer
Notes :-
(a) Some Water Closets (WC) may be Indian style, if desired.
(b) Male population may be assumed as two-third and female population as
one-third.
(c) Provision for additional and special fittings where required shall be made.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2415
Shopping Malls and Retail Buildings
Serial Fixtures Public Toilets for Staff Toilets in
Number floating population Shopping Building
Male Female Male Female
I. Water Closets 1 per 50 1 per 50 1 for up to 15 1 for up to 12
(min. 2) (min. 2) 2 for 16 to 35 2 for 13 to 25
3 for 36 to 65 3 for 26 to 40
4 for 66 to 100 4 for 41 to 57
5 for 58 to 77
6 for 78 to 100
II. Ablution tab 1 in each water closet
III. Urinals 1 per 50 - 1 for 1 to 20 -
2 for 21 to 45
3 for 46 to 65
4 for 66 to 100
IV. Wash Basins 1 per 1 per 1 per 1 per
Water Water Water Water
Closets Closets Closets Closets
(WC) (WC) (WC) (WC)
V. Cleaner's sink 1 per floor
VI. Bath/showers 1 per 100 persons
Notes :-
(a) Toilet facilities for individual facilities in a shopping building should be
taken same as that for office buildings.
(b) Staff toilets in the shopping buildings provide facilities for persons working
in shops and building, as well as for maintenance staff.
(c) The number of persons against the fixture bath/showers represent the
maintenance staff requiring such facility.
(d) Public toilet facilities are provided for a large floating population for
buyers and visitors.
(e) Some Water Closets (WC) may be Indian style, if desired.
(f) Male population may be assumed as two-third and female population as
one-third.
(g) Provision for additional and special fittings where required shall be made.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2416
Hotel
Serial Fixtures Public Room Non Residential Staff
Number Male Female Male Female
I. Toilet suite Individual guest rooms -
comprising one with attached toilets
Water Closets
(WC), wash
basin with
shower or a
bath tub
Guest room with common facilities
II. Water Closets 1 per 100 1 per 100 1 for up 1 for up to 12
persons up persons to 15 2 for 13 to 25
to 400; up to 200; 2 for 16 3 for 26 to 40
over 400 over 200 to 35 4 for 41 to 57
add at 1 add at 1 3 for 36 5 for 58 to 77
per 250 per 100 to 65 6 for 78 to
or part or part 4 for 66 100
thereof thereof to 100
III. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be provided for
every 50 persons or part thereof in the vicinity of water
closets and urinals
IV. Urinals 1 per 50 - 1 for 1 -
person or to 20
part 2 for 21
thereof to 45
3 for 46
to 65
4 for 66
to 100
V. Wash Basins 1 per 1 per 1 for up 1 for up
Water Water to 15 to 12
Closets Closets 2 for 16 2 for 13
(WC) (WC) to 35 to 25
3 for 36 3 for 26
to 65 to 40
4 for 66 4 for 41
to 100 to 57
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2417
VI. Bath (showers) 1 per 10 person or part thereof
VII. Cleaner's sink 1 per 30 rooms, minimum 1 per floor
VIII. Kitchen sink 1 per kitchen
Notes :-
(a) Some Water Closets (WC) may be Indian style, if desired.
(b) Male population may be assumed as two-third and female population as
one-third.
(c) Provision for additional and special fittings where required shall be made.
Hospital with indoor patient ward
Serial Fixtures Patient Toilets Staff Toilets
Number Male Female Male Female
I. Toilet suite Private room with For individual doctor's /
comprising one up to 4 patient officer's rooms
Water Closets
(WC), one wash
basin and shower
stall
For General wards, Hospital staff and visitors
II. Water Closets 1 per 5 Beds or part 1 for up 1 for up
thereof to 15 to 12
2 for 16 2 for 13
to 35 to 25
III. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be provided for
every 50 persons or part thereof in the vicinity of water
closets and urinals
IV. Urinals 1 per 15 - 1 for 1 to 20 -
beds 2 for 21 to 45
V. Wash Basins 2 for every 30 beds or 1 for up 1 for up
part thereof. Add 1 per to 15 to 12
additional 30 beds or 2 for 16 2 for 13
part thereof to 35 to 25
Serial Fixtures Patient Toilets Staff Toilets
Number Male Female Male Female
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2418
VI. Drinking Water 1 per Ward 1 per 100 person or
Fountain part thereof
VII. Cleaner's sink 1 per Ward -
VIII. Bed pan sink 1 per Ward -
IX. Kitchen sink 1 per Ward -
Notes :-
(a) Some Water Closets (WC) may be Indian style, if desired.
(b) Male population may be assumed as two-third and female population as
one-third.
(c) Provision for additional and special fittings where required shall be made
(d) Drinking water fountain are not recommended for hospitals for reasons of
infection control. This is to be decided by the health authority
recommendations.
Hospital with Outdoor Patient Department
Serial Fixtures Patient Toilets Staff Toilets
Number Male Female Male Female
I. Toilet suite For up to 4 patient For individual doctor's /
comprising one officer's rooms
Water Closets
(WC) and one
wash basin (with
optional shower
stall if building
used for 24 h)
II. Water Closets 1 per 100 2 per 100 1 for up 1 for up
persons persons to 15 to 12
or part or part 2 for 16 2 for 13
thereof thereof to 35 to 25
III. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be provided for
every 50 persons or part thereof in the vicinity of water closets
and urinals
IV. Urinals 1 per 50 - 1 for 1 -
persons to 20
or part 2 for 21
thereof to 45
Serial Fixtures Patient Toilets Staff Toilets
Number Male Female Male Female
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2419
V. Wash Basins 2 per 100 persons 1 for up 1 fot up
or part thereof to 15 to 12
2 for 16 2 for 13
to 35 to 25
VI. Drinking Water See note (d) 1 per 100 person or
Fountain part thereof
Notes :-
(a) Some Water Closets (WC) may be Indian style, if desired.
(b) Male population may be assumed as two-third and female population as
one-third.
(c) Provision for additional and special hospital fittings where required shall
be made.
(d) Drinking water fountain are not recommended for hospitals for reasons of
infection control. This is to be decided by the health authority
recommendations.
(e) The Water Closets (WC) shall be provided keeping in view the location of
main Out Patient Department (OPD) waiting hall and sub-waiting halls,
floor wise, so as to serve the people effectively. The number of patients
shall be calculated floor wise. The Out Patient Department (OPD)
population shall include patient attendants @ at least 1 per patient.
Hospital Administrative Buildings
Serial Fixtures Staff Toilets
Number Male Female
I. Toilet suite comprising one For individual doctor's /officer's
Water Closets (WC) and one rooms
wash basin (with optional
shower stall if building used
for 24 h)
II. Water Closets 1 per 25 persons 1 per 15 persons
or part thereof or part thereof
III. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be
provided for every 50 persons or part thereof in
the vicinity of water closets and urinals
Serial Fixtures Patient Toilets Staff Toilets
Number Male Female Male Female
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2420
IV. Urinals Nil up to 6 -
1 for 6 to 15
2 for 16 to 50
V. Wash Basin 1 per 25 persons or part thereof
VI. Drinking Water Fountain 1 per 100 persons or part thereof
(see note c)
Notes:-
(a) Some Water Closets (WC) may be Indian style, if desired.
(b) Male population may be assumed as two-third and female population as
one-third.
(c) Drinking water fountains to be provided only where there is a separate
block and patients will not use it.
Factories
Serial Fixtures Offices/Visitors Workers
Number Male Female Male Female
I. Water Closets 1 for up 1 for up 1 for up 1 for up
(workers and to 15 to 12 to 15 to 12
staff) 2 for 16 2 for 13 2 for 16 2 for 13
to 35 to 25 to 35 to 25
3 for 36 3 for 26 3 for 36 3 for 26
to 65 to 40 to 65 to 40
4 for 66 4 for 41 4 for 66 4 for 41
to 100 to 57 to 100 to 57
From 101 5 for 58 From 101 5 for 58
to 200, add to 77 to 200, add to 77
@3 percent; 6 for 78 @3 percent; 6 for 78
for over to 100 for over to 100
200, add From 101 200, add From 101
@ 2.5 to 200, @ 2.5 to 200,
percent add @ 5 percent add @ 5
percent; percent;
for over for over
200, add 200, add
@ 4 @ 4
percent percent
Serial Fixtures Staff Toilet
Number Male Female
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2421
II. Ablution tab 1 in each water closet
III. Urinals 1 for 1 - 1 for 1 -
to 20 to 20
2 for 21 2 for 21
to 45 to 45
3 for 46 3 for 46
to 70 to 70
4 for 71 4 for 71
to 100 to 100
From 101 From 101
to 200, to 200,
add @ 3 add @ 3
percent; percent;
for over for over
200, add 200, add
@ 2.5 @ 2.5
percent percent
IV. Wash Basins 1 per 25 or part thereof
(wash basins in
rows or troughs
and taps spaced
750 mm c/c
V. Drinking Water 1 per 100 persons or part thereof with minimum
Fountain one on each floor
VI. Cleaner's sink 1 on each floor
VII. Showers/bathing As per trade requirements
rooms
VIII. Emergency - - 1 per every shop floor per
shower and eye 500 persons
wash fountain
Notes :-
(a) For factories requiring workers to be engaged in dirty and dangerous
operations or requiring them to being extremely clean and sanitized conditions,
additional and separate (if required so) toilet facilities and if required by applicable
Industrial and safety laws and the Factories Act shall be provided in consultation with
the user.
Serial Fixtures Offices/Visitors Workers
Number Male Female Male Female
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2422
(b) Depending on the type of disability of a person and the hazard posed by
the type of activities in the factory for a person with disabilities, if a
person with disabilities is decided to be engaged for a particular activity,
the requirements of accessibility shall be guided by the provisions given
in 13 of Part 3 -'Development Control Rules and General Building
Requirements of the National Building Code of India, 2016' as amended
from time to time.
Schools and Educational Institutions
Serial Fixtures Nursery Non-Residential Residential
Number School Boys Girls Boys Girls
I. Water Closets 1 per 15 1 per 40 1 per 25 1 per 8 1 per 6
pupils or pupils or pupils pupils pupils
part part or part or part or part
thereof thereof thereof thereof thereof
II. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be provided for
every 50 persons or part thereof in the vicinity of water closets
and urinals
III. Urinals - 1 per 20 - 1 per 25 -
pupils or pupils or
part part
thereof thereof
IV. Wash Basins 1 per 15 1 per 60 1 per 40 1 per 8 1 per 6
pupils or pupils or pupils or pupils or pupils or
part part part part part
thereof thereof thereof thereof thereof
V. Drinking 1 per 50 1 per 50 pupils or 1 per 50 pupils or
Water pupils or part thereof part thereof
Fountain part
thereof
VI. Cleaner's sink 1 per each floor
VII. Bath or 1 per 40 - 1 per 8 1 per 6
Showers pupils or pupils pupils
part or part or part
thereof thereof thereof
Notes :-
(a) Some Water Closets (WC) may be Indian style, if desired.
(b) For teaching staff, the schedule of fixtures to be provided shall be the
same as in case of office building.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2423
Hostels
Serial Fixtures Resident Non-Resident Visitor/
Number Common Room
Males Females Males Females Males Females
I. Water 1 per 8 1 per 6 1 for 1 for up 1 per 1 per
Closets or part or part upto 15 to 12 100 up 100 up
thereof thereof 2 for 16 2 for 13 to 400; to 200;
to 35 to 25 add add
3 for 36 3 for 26 at 1 at 1
to 65 to 40 per per
4 for 66 4 for 41 250 100
to 100 to 57
5 for 58
to 77
6 for 78
to 100
II. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be provided for every
50 persons or part thereof in the vicinity of water closets and urinals
III. Urinals 1 per 25 - 1 for 1 - 1 per -
or part to 20 50
thereof 2 for 21 or part
to 45 thereof
3 for 46
to 70
4 for 71
to 100
IV. Wash 1 per 8 1 per 6 1 for up 1 for up 1 per 1 per
Basins or part or part to 15 to 12 Water Water
thereof thereof 2 for 16 2 for 13 Closets Closets
to 35 to 25 (WC) (WC)
3 for 36 3 for 26
to 65 to 40
4 for 66 4 for 41
to 100 to 57
5 for 58
to 77
6 for 78
100
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2424
V. Bath or 1 per 8 1 per 6 - - - -
showers or part or part
thereof thereof
VI. Cleaner's 1 per each floor
sink
Notes :-
(a) Some Water Closets (WC) may be Indian style, if desired.
Fruit and Vegetable Markets
Serial Fixtures Shop Owners Common toilets public toilet
Number in market for floating
building population
Males Females Males Females Males Females
I. Water 1 per 8 or 1 for up 1 for up 1 per 1 per
Closets part thereof to 15 to 12 50 50
2 for 16 2 for 13 (min 2) (min 2)
to 35 to 25
3 for 36 3 for 26
to 65 to 40
4 for 66 4 for 41
to 100 to 57
5 for 58
to 77
6 for 78
to 100
II. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be provided for every
50 persons or part thereof in the vicinity of water closets and urinals
III. Urinals - - 1 for 1 - 1 per -
to 20 50
2 for 21
to 45
3 for 46
to 70
4 for 71
to 100
Serial Fixtures Resident Non-Resident Visitor/
Number Common Room
Males Females Males Females Males Females
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2425
IV. Wash 1 per 8 or part 1 for up 1 for up - -
Basins thereof to 15 to 12
2 for 16 2 for 13
to 35 to 25
3 for 36 3 for 26
to 65 to 40
4 for 66 4 for 41
to 100 to 57
V. Bath or 1 per 8 1 per 6 - - 1 per 1 per
showers or part or part 50 50
thereof thereof persons persons
Notes :-
(a) Toilet facilities for individual buildings in a market should be taken same
as that for office buildings.
(b) Common toilets in the market buildings provide facilities for persons
working in shops and their regular visitors.
(c) Special toilet facilities for a large floating population of out-of-town buyers/
sellers, labour, drivers of vehicles for whom special toilet (public toilets).
Bus Stations, Airports and Railway Stations
Serial Fixtures Junction Terminal Domestic
Number Stations, Railway and
Intermediate and Bus International
Stations and Stations Airports
Bus Stations
Males Females Males Females Males Females
I. Water 3 for 4 for 4 for 5 for for for
Closets up to up to up to up to 200: 5 200: 8
1000 1000 1000 1000 for for
add 1 add 1 add 1 add 1 400: 9 400: 15
per per per per for for
additio- additio- additio- additio- 600:12 600:20
nal nal nal nal for for
1000 1000 1000 1000 800:16 800:26
or part or part or part or part for for
thereof thereof thereof thereof 1000: 1000:
18 29
Serial Fixtures Shop Owners Common toilets public toilet
Number in market for floating
building population
Males Females Males Females Males Females
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2426
II. Ablution tab 1 in each water closet
1 water tap with draining arrangements shall be provided for every
50 persons or part thereof in the vicinity of water closets and urinals
III. Urinals 4 for - 6 for 1 per -
to up up to 40 or
1000 1000 part
add 1 add 1 thereof
per per
additio- additio-
nal nal
1000 1000
IV. Wash 1 per WC
Basins
V. Bath or 2 per 1000 or 3 per 1000 or 4 per 1000 or
showers part thereof part thereof part thereof
VI. Drinking 2 per 1000 or 3 per 1000 or 4 per 1000 or
Water part thereof part thereof part thereof
Fountain
or taps (in
common
lobby for
male/
female)
VII. Cleaner's 1 per toilet compartment with 3 WCs
sink
Notes :-
(a) Some Water Closets (WC) may be Indian style, if desired.
(b) Male population may be assumed as three-fifth and female population as
two-fifth.
(c) Separate provision shall be made for staff and workers.
Serial Fixtures Junction Terminal Domestic
Number Stations, Railway and
Intermediate and Bus International
Stations and Stations Airports
Bus Stations
Males Females Males Females Males Females
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2427
PART VII
FIRE PROTECTION, STRUCTURAL DESIGN, BUILDING MATERIAL,
LIGHTING AND VENTILATION
31 Fire protection.- (1) All requirements of fire protection through classification
of buildings based on occupancy, type of construction and other requirements
shall be as per Part 4- Fire and Life Safety of the National Building Code of
India, 2016.
(2) For buildings having more than four storeys in height, non-combustible
material shall be used for construction.
32 Structural design.- Structural design of all buildings shall be as per Part 6-
Structural Design of the National Building Code of India, 2016. For requirements
regarding construction (including management and safety), reference shall be
made to Part 7- Construction Management, Practices and Safety of the National
Building Code of India, 2016.
33 Lighting and ventilation.- For requirements regarding lighting and ventilation
for different uses and occupancies, reference shall be made to Section 1-
Lighting and Natural Ventilation of Part 8- Building Services of the National
Building Code of India, 2016.
34 Electrical and allied installation.- The electrical installation in the building
shall be carried out in conformity with the requirements of the Electricity Act,
2003 and the rules made thereunder, the work of electric installations shall be
carried out under the supervision of a person holding a Certificate of
Competency issued by the Chief Electrical Inspector, Punjab.
For requirements regarding electrical installations in buildings including lightning
protection of buildings, reference shall be made to Section 2- Electrical and
Allied Installations of Part 8-Building Services of the National Building Code
of India, 2016.
35 Building Material.- Building Materials shall be as per Part 5-Building Materials
of the National Building Code of India, 2016 and use of glass in buildings shall
conform to the relevant provisions of the Bureau of Indian Standard Code or
the National Building Code of India, 2016.
Section
108 (2)
Section
108 (2)
Section
108 (2)
Section
108 (2)
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2428
PART VIII
PROVISIONS FOR DIFFERENTLY-ABLED, ELDERLY AND CHILDREN
36 Applicable provisions.- (1) In the case of group housing building, studio
apartments building, commercial building, industrial building, educational
building, institutional building, public building, office building, assembly buildings
or any type of building used for public purpose, provisions contained in
Harmonised Guidelines and Space Standards for Barrier-Free Built Environment
for persons with Disability and Elderly Persons, 2016 and The Rights of Persons
with Disabilities Act, 2016 related to planning, designing and construction of
public buildings and guidelines issued thereunder and space standards for Barrier
Free Environment as specified under the said Act (as amended from time to
time), shall also be complied with.
(2) Annexure-B of Part-3 (Anthropometrics and Requirements for Accessibility
in Built-Environment for Elders and Persons with Disabilities) of the National
Building Code of India, 2016 (as amended from time to time) shall also be
applicable for requirements for accessibility in Built-Environment for persons
with disability, elderly and children.
Section
180 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2429
PART IX
GREEN BUILDINGS AND SUSTAINABILITY PROVISIONS
37 Provisions and applicability. - The approval of building plans shall be subject
to the fulfilment of provisions of water conservation and management, energy
efficiency, waste management and solar energy utilization as are given in the
table below: -
(a) Provisions for various plot sizes (Residential uses)
Residential plotted Group
housing
Green Building Provisions Plot Area in Sq.mt.
Upto Above Above Above Above As per
250 250 500 1,000 3,000 Govern-
upto upto upto ment
500 1,000 3,000 policy
Water Rain √ √ √ √ √
Conservation Water
and Harvesting
Management (by
Recharge)
Low Water √
Consump-
tion
Plumbing
Fixtures
Energy Efficiency and Provisions of notification no. 18/4/16 HG 1/1856
Solar Energy Utilization dated: 24-06-2016 of Department of New and
Renewable Energy shall be applicable or as
amended from time to time.
(b) Provisions for various plot sizes (Non-Residential uses)
Green Building Provisions Plot Area in Sq.mt.
Upto Above Above Above Above
250 250 500 1,000 3,000
upto upto upto
500 1,000 3,000
Water Rain √ √ √ √
Conservation Water
and Harvesting
Management (by
Recharge)
Section
180 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2430
Low Water √
Consump-
tion
Plumbing
Fixtures
Energy Efficiency and Provisions of notification no. 18/4/16 HG 1/1856
Solar Energy Utilization dated: 24-06-2016 of Department of New &
Renewable Energy shall be applicable or as
amended from time to time.
Note:-
The √ indicate that the provision is applicable for a plot.
38 Energy efficiency.- The provisions of the Punjab Energy Conservation Building
Code shall be applicable to the buildings or areas in accordance with the
notification issued by the Government vide No. 18/4/16 HG 1/1856, dated the
24th June 2016, as amended from time to time.
(ii) The applicant or owner shall submit a certificate from an architect or Civil
Engineer confirming that the building plans conform to the Punjab Energy
Conservation Building Code and is duly verified by Punjab Energy Development
Agency (PEDA) along with the application approval of building plan.
(iii) The completion and occupation certificate of buildings shall be issued by the
competent authority only after the applicant or owner shall submit a certificate
from an architect or Civil Engineer (who has supervised the construction of
building), that building has been constructed in accordance with the provisions
of the Punjab Energy Conservation Building Code and is duly verified by
Punjab Energy Development Agency.
(iv) An incentive of additional Floor Area Ratio of five percent for Three Star or
Bronze or Sliver rated building, seven and half percent for Four Star or Gold
rated building and ten percent for Five Star or Platinum rated building free of
cost with hundred percent exemption of building scrutiny fee shall be permissible
Residential plotted Group
housing
Green Building Provisions Plot Area in Sq.mt.
Upto Above Above Above Above As per
250 250 500 1,000 3,000 Govern-
upto upto upto ment
500 1,000 3,000 policy
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2431
on submission of Green Building Certificate from the following agencies with
rating duly verified by rating agencies, namely: -
(a) Buildings granted Three Star or Four Star or Five Star rating by Green
Rating for Integrated Habitat (GRIHA); or
(b) Buildings granted Bronze or Silver or Gold or Platinum rating by
Leadership in Energy and Environmental Design (LEED); or
(c) Buildings granted Bronze or Silver or Gold or Platinum rating by Indian
Green Building Council (IGBC).
However, in case the owner or applicant fails to submit maintenance certificate
after a period of every three years from the rating agencies (GRIHA/LEED/
IGBC), the defaulter can be penalized equivalent to five times the collector
rate of land proportional to the five percent additional Floor Area Ratio availed
and Building scrutiny fee shall be recovered along with interest at the rate of
twelve percent from the date of the approval of building plans.
39 Provisions for tree plantation in new building sites.- The building plan
shall only be approved, if the provision for planting trees of indigenous species
is shown on the building plans as given below:-
(i) One tree for every 225 sq.m covered area of building(s) shall be planted.
While calculating the number of trees, if there is a fraction less than 0.5,
it shall be rounded down to the nearest whole digit and if there is a
fraction equal to or greater than 0.5, it shall be rounded up to the nearest
whole digit.
(ii) The occupancy certificate shall only be granted, if the owner has planted
the requisite number of trees as per the sanctioned plans.
40 Rainwater harvesting.- The harvesting of rainwater simply involves the
collection of water from surfaces on which rain falls, and subsequently storing
this water for use. The rainwater collected can be stored for direct use or can
be recharged into the underground aquifers. In scientific terms, water harvesting
(broadly) refers to collection and storage of rainwater from the rooftops. This
also restricts evaporation and seepage into building foundations.
A rainwater harvesting system consists of the following: -
(a) Roof catchment;
(b) Gutters;
(c) Down pipes;
(d) Rain water/ Storm water drains;
Section
108 (2)
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2432
(e) Filter Chamber;
(f) Storage Tanks/ Pits/ Sumps; and
(g) Ground Water recharge structures like pit, trench, tube well or
combination of above structure.
(1) Rainwater harvesting techniques. – There are two main techniques of rain water
harvestings, namely: -
(a) Storage of rainwater under surface; and
(b) Recharge to ground water.
(2) Harvesting provisions in various building categories.- The provision for rain
water harvesting is as under:
Rainwater harvesting by building types:-
Category/ Area of Provisions to be made Other conditions
Use Plot
Residential Plotted Houses
New Above 250 Construction of Rain Water Shall have emphasis on
Proposals sq.mt. Harvesting Structure. both storage and reuse.
Group Housing
New All plot Construction of Rain Water Should indicate the
Proposals sizes Harvesting Structure. system of Storm Water
Concrete paving to be Drainage, Rain Water
avoided and permeable Harvesting Structure and
materials are to be used Recharging Well
or all open parking spaces.
Government and Semi Government Public Buildings and Private Institutions
All Proposals Above 250 Shall have Rain Water Shall have emphasis on
sq.mt. Harvesting Structure and both storage and reuse.
storage
Shall have Recharge pits
Commercial / Mixed use Buildings
All Above 100 Construction of Rain
Proposals Sq.mt. Water Harvesting Structure. Should indicate the
Soft landscape provisions and system of Storm Water
open spaces with Percolation pits. Drainage, Rain Water
Common treatment plant to be Harvesting Structure and
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2433
made part of the integrated Recharging Well
development, funded by sale Shall have emphasis on
of commercial space. both storage and reuse.
Industrial
All Above 100 Construction of Rain Should indicate the
proposals Sq.mt. Water Harvesting Structure. system of Storm Water
Soft landscape provisions and Drainage, Rain Water
open spaces with Percolation pits. Harvesting Structure and
Use of abandoned bore wells for Recharging Well.
recharging of ground water. Provision should be made
Common treatment plant to be not to inject contaminated
made part of the integrated water into recharge
development funded by sale structures in industrial
of commercial space. areas and care is to be
taken to keep such
structures away from
sewer lines, septic tanks,
soak pits, landfill and
other sources of
contamination.
Provided that design and structural specification of rain water harvesting system shall be
prepared and certified by an Engineer dealing with civil work.
Category/ Area of Provisions to be made Other conditions
Use Plot
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2434
41 Sustainable waste management.- (1) Zero waste is a concept of waste
management and planning approach that emphasize waste prevention as opposed
to end waste management. This means restructuring production and distribution
systems, designing and managing products and processes to systematically
follow the rule of 3R’s i.e., Reduce, Re-use and Re-cycle, the volume of
waste, to conserve and recover all used resources, and therefore, eliminating
all discharges to landfills, and prevent air, water and land pollution.
(2) Zero waste/ land-fill can be achieved by adopting systematic approach of
segregation at source by planning, by collection facilitation and most
importantly by creating public awareness.
(3) The green waste can be converted into fuel cakes, kitchen waste into
manure, construction and demolition waste into bricks, plastic waste into
oil, paper, glass and steel back into the same and all residual inert materials
can also be converted into bricks. Achieving zero land-fill is more
conveniently possible, if :-
(a) the collection is made from house to house and some segregation is
done at household level;
(b) separate wet and dry bins must be provided at the ground level; and
(c) the recycling is done at decentralized.
(4) For Plot area 500 sq.m and above, the composting of biodegradable waste
such as kitchen waste, garden waste etc. is mandatory. They should not be
allowed to send their biodegradable waste to landfill. Final product after
composting i.e Humus or Black Gold should be used as manure for green area
within their complexes or sites.
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2435
PART X
CONSERVATION OF HERITAGE SITES INCLUDING HERITAGE
BUILDINGS, HERITAGE PRECINCTS AND NATURAL FEATURE
AREAS
42 Applicable provisions.- The provisions for conservation of heritage sites
including heritage buildings, heritage precincts and natural feature areas shall
be as per the Model Building Byelaws, 2016 (as amended from time to time)
and the provisions in the prohibited and regulated areas as defined in the Ancient
Monuments and Archaeological Sites and Remains (Amendment and Validation)
Act, 2010 and the site specific Heritage Bye-Laws prepared and notified by
the competent authority or the National Monuments Authority under the said
Act, shall be applicable.
PART XI
ENVIRONMENTAL CLEARANCE FOR BUILDING PLAN APPROVAL
43 Integration of environmental conditions for building plan approval.- The
competent authority shall adhere to the objective and monitorable environment
conditions as given in the policy notified vide notification no. S.O 3999(E),
dated the 9th December, 2016 by the Government of India, Ministry of
Environment, Forest and Climate Change, as amended from time to time,
regarding construction of building as per the size specified in ‘Annexure-14’.
Section
108 (2)
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2436
PART XII
PUBLIC HEALTH: WATER SUPPLY, SEWERAGE AND DRAINAGE
44 WATER SUPPLY.- (1) Application for connection.- Every application for
water connection from the main water supply for a private domestic purpose shall
be made in Form- 'K' to the competent authority through a registered plumber.
(2) Material for water connection.- Every applicant shall procure at his own
cost at least a ferrule ISI (Indian Standards Institute) mark, a stop cock ISI (Indian
Standards Institute) mark, water meter and surface box, if the water meter and
surface box is not supplied by the competent authority, medium size G.I. (Galvanised
Iron) pipes and specials to be installed for the ground floor level.
(3) Sanction of water connection.- On receipt of the application under sub-rule
(1) of rule 44 and subject to the fulfilment of the requirements of these rules, the
competent authority may sanction the water connection and direct the applicant to
deposit such security and any other charges, as may be determined by the Chief
Administrator for getting the water connection.
(4) Release of water connection.- (i) After the water connection is sanctioned
under rule sub-rule (3) of rule 44, the applicant shall excavate the trench in a
safe manner at the place from where connection from the water main has been
sanctioned and thereafter supply pipe line shall be drilled and ferrule and
connection pipe shall be laid.
(ii) No building or premises shall be supplied with water by the competent
authority through more than one communication pipe and in the case of
multi storeyed flats, separate water connection for each flat will be allowed
and its water meter shall be installed at the ground floor.
(iii) All works to be carried out by the applicant in connection with the supply
or use of water shall be required to be executed by the registered plumber
and shall conform to the standard and specifications laid down for such
items in the Punjab Public Works Department specification Book 1986
Edition and if no standards or specifications are laid down for any item, it
shall be as per standard and specifications of the Indian Standard Institute
and if no standard and specifications are laid down by the Indian Standard
Institute, then that item shall be as per the Bureau of Indian Standards.
(iv) The applicant shall make provision of dual button type flushing cistern in
each water closet.
(v) Tertiary treated water from nearby Sewerage Treatment Plant shall be
supplied to every public, commercial, residential building through separate
Section
180 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2437
connection which shall be utilized for non-potable purposes such as
gardening, washing of floors or courtyards, flushing of WC’s (Water
Closet) through separate network system to be provided in the building.
This provision shall be applicable to newly developed areas after coming
into operation of this provision.
(5) Notice and certificate of completion of work.- (i) No connection to any
public sewer shall be made nor any water borne sanitary installation and drainage
work intended to be connected through the connection shall be brought into
use, until the applicant, after completion of minimum works, has applied to the
competent authority for a certificate, and a certificate has been issued by the
competent authority in Form 'H' after satisfying that the sanitary installations
and drainage have been satisfactorily completed in compliance with these rules.
(ii) If no decision is communicated or taken on the application for a certificate
mentioned under sub-rule (5) of rule 44 within a period of 20 days of the
receipt of the application to the applicant, the certificate shall be deemed
to have been granted.
45 SEWERAGE AND DRAINAGE .- (1) Application for connection with
public sewer.- (i) After the grant of the certificate referred to in sub-rule
44(5) of rule 44 or in the event of the certificate having been deemed to have
been granted, every person intending to connect a drain or sewer to a public
water sewer shall apply in Form- 'L' to the competent authority at least seven
days before the date on which connection is required.
(ii) The application under sub-rule (i) shall be accompanied by the certificate
referred to in sub-rule 44(5) of rule 44 along with a fee, which the Chief
Administrator may specify from time to time.
(iii) On receipt of the application and subject to the requirements of sub-rule
44(5) of rule 44, the Competent Authority shall accept or reject the
application after giving the opportunity of being heard.
(iv) In the event of the required connection having been sanctioned, it shall
be got connected through a registered plumber.
(2) Connection with public sewer.- Every drain or sewer discharging into a
public sewer shall join the sewer obliquely in the direction of the flow of the sewer
and such a connection shall be made at an existing junction in the sewer or there
shall be an intersection manhole before the connection within the boundaries of the
site.
(3) Material for drain and construction.- The material and methods of
construction for drain shall conform to the Punjab Public Works Department
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2438
Specification, 1986 Edition and if there are no such specifications laid down for any item,
the same should conform to the specifications laid down for such item by the Bureau of
Indian Standards or Indian Standards Institute.
(4) Drain connection for trade effluent.- Every drain and private sewer intended
solely for conveyance of industrial or chemical or other trade effluent shall be constructed
of good and sound type of material unaffected by the chemical action of the effluent and
shall be laid as provided in the Punjab Public Works Department Specifications or the
National Building Code of India 2016 or in accordance with the instructions issued from
time to time by the competent authority.
(5) Waste water pipes.- A waste water pipe from a bath, sink (not being a slope sink),
bidet or lavatory basin and pipe for carrying water directly shall:-
(i) not discharge as to cause dampness in the walls or the foundation of a building;
and
(ii) if it discharges into a drain, be disconnected from the drain by a trapped gully
with a suitable grating above the level of the water in the trap.
(6) Manholes.- (i) At every change in alignment, gradient or diameter of a drain, there
shall be a manhole inspection chamber, and bends and junctions in the drain shall be
grouped together in a manhole as far as possible and a maximum distance between
manhole and gully chamber shall not exceed six meters.
(ii) Where the diameter of a drain is increased the crown of the pipes shall be fixed
at the same level and the necessary slopes given in the invert of the manhole
chamber, and in exceptional cases, where the required fall is not available,
connection may be made upto half the difference in the diameter that is the
connecting branch sewer shall be connected with the main sewer in such a
manner that full supply level of both the sewers is maintained running half the
diameter of both the sewers of drain and the minimum internal size of chamber
(between brick faces) shall be as follows:-
Provisions for minimum internal size of Chamber
I. For depth of 0.80 meter 0.75 x 0.75 meters
II. For depth of more than 0.80 meters but 1.2 x 0.90 metres
not exceeding 2.1 meters
III. For depths of more than 2.1 meters Rectangular chamber
with minimum internal
dimension of 1.20 x 0.90
meter
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2439
(7) Septic tank.-(i) No septic tank shall be located within thirty meters of any percolation
well, water sources or stream used or likely to be used for drinking or domestic
purposes or for the manufacture or preparation of any articles of food or drink for
human consumption and it shall be readily accessible so as to permit cleaning
operations being carried out without interference with the operation of any water
borne sanitary installation as a whole.
(ii) Every septic tank shall be constructed into two separate compartments so that
one compartment when required may be put out of use for cleaning purposes.
(iii) The capacity of every compartment of the septic tank shall be two and a half
times, the total water allowance for the total number of residents of the building.
(iv) Every inlet pipe into a septic tank shall be effectively trapped.
(v) The design of septic tank shall be in accordance with the B.I.S. (Bureau of
Indian Standards) Code No. IS 2470, Part-I-1968 and IS 2470 (Part-II-1971)
Code of practice for design and construction of septic tank.
(8) Absorption pits.- (i) In the matter of location, every absorption pit shall conform
to the same restrictions as are laid down for a septic tank under sub-rule (7) of this
rule.
(ii) No absorption pit shall have any outlet into, or means of communication with,
any sewer, storm water, drain or surface drain.
(iii) The wall of every absorption pit shall be at least 0.50 metre above ground level
so as to exclude effectively the entry of storm water into the absorption pit.
(iv) The absorption pit shall be constructed in duplicate, so that one pit can be put
out of use for cleaning purpose and the capacity of the absorption pit shall be
as approved by the competent authority.
(v) The other details of the absorption pit should conform to the B.I.S. (Bureau of
Indian Standards) Code No. IS 2470(Part I) 1968 Code of Practice for design
and construction of septic tanks.
(vi) The absorption pits shall be provided with adequate means of access for
removing the filtering media and cleaning the same.
Note:-
For requirements regarding water supply, drainage and sanitation, solid waste management,
gas supply shall be made as per Part 9, Plumbing Services of the National Building Code
of India, 2016.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2440
PART XIII
RISK BASED CLASSIFICATION OF BUILDING PLAN APPROVAL
PROPOSALS
46 Risk Based Classification of building proposals.- (1) Hazardous
buildings.- These shall include any building or part there of which is used for the
storage, handling, manufacture or processing of highly combustible or explosive
materials or products which are liable to burn with extreme rapidity and/or which
may produce poisonous fumes or explosions for storage, handling, manufacturing or
processing which involve highly corrosive, toxic or noxious alkalis, acids or other
liquids or chemicals producing flame, fumes and explosive, poisonous, irritant or
corrosive gases and for the storage, handling or processing of any material producing
explosive mixtures of dust which result in the division of matter into fine particles
subject to spontaneous ignition. The examples of buildings in this class are the
buildings, which are used for:-
(i) storage under pressure of more than 0.1 N/mm2 and in quantities
exceeding 70 m3, of acetylene, hydrogen, illuminating and natural
gases, ammonia, chlorine, phosgene, sulphur dioxide, carbon dioxide,
methyloxide and all gases subject to explosion, fume or toxic hazard,
cryogenic gases, etc;
(ii) storage and handling of hazardous and highly flammable liquids, liquefiable
gases like LPG, rocket propellants, etc;
(iii) storage and handling of hazardous and highly flammable or explosive
materials (other than liquids); and
(iv) manufacture of artificial flowers, synthetic leather, ammunition, explosives
and fireworks.
Note:-
A list of hazardous substances giving quantities, for which or exceeding
which owners handling such substances are required to be covered under
the Public Liability Insurance Act, 1991, has been notified under the
Rules on Emergency Planning, Preparedness and Response for
Chemical Accidents by the Government of India, Ministry of
Environment and Forests vide Notification No. G.S.R. 347(E), dated
the 01st August 1996.
(2) Classification of risk based storage building.- The provisions for site
inspection of risk based storage building, as per storage material specifications are as
per table given below:-
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2441
Classification of risk based storage building
Category Storage Material Specifications Stacking Designated officer
Height (in m) for site Inspection
Medium High
Category-I Articles such as Carpets, Non 4 6.5 Assistant Town
(Low Risk) synthetic/synthetic yarn and fabrics. Planner/Assistant
Mechanical and electrical goods Engineer/Senior
(dominantly metal parts), Glassware Divisional Engineer
and crockery, fiberboards, groceries,
metal goods, Papers other than those
listed under categories Moderate
and High, Powdered and canned
foods, Plastic/glass bottles containing
non-flammable liquids, etc.
Category-II Articles such as Batteries, Baled 3 5.5 District Town
(Medium cotton/synthetic fibers, Books, Baled Planner/Executive
Risk) cork, Baled waste paper, Cartons Engineer.
containing alcohols ( in cans/bottles),
Cartons of canned lacquers which
dry by solvent evaporation, Chipboard,
Cardboard rolls (horizontally Stored),
Cereals/Grains/Foodstuff/ Flour/Sugar
in sacks, Cellulose/Cellulose pulp,
Electrical goods other than those
stated in Category low, Flammable
liquids in non-combustible containers,
Leather goods, Palletized liquor stocks,
Plastics (non-foamed, other than
cellulose nitrate), Rolled pulp and
paper and asphalted paper (Horizontal
storage), Veneer sheets, Wooden
patterns, Metal/wooden furniture with
plastic seats, etc.
Category-III Articles such as Bitumen/Wax coated 2 4.5 Senior Town
(High Risk) paper, Candles, Carbon black, Card Planner/Senior
board rolls (vertically stored), Charcoal, Engineer.
Coal, cellulose nitrate, Foamed plastic
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2442
and foam rubber products, Flammable
liquids in combustible containers,
Linoleum products, Matches, Plastics
other than those stated in Category
Moderate, Rolled pulp and paper and
asphalted paper (vertical storage),
Rubber goods including tyres and tubes,
Sawn timber, Ventilated wood stacks,
Waxed and asphalt coated papers and
containers in cartons, Wood wool,
wooden pallets and flats (idle), Ail
materials having wrappings or
pre-formed containers of foamed
plastics, etc.
Category-IV Off cuts and random pieces of 1.25 3.5 Senior Town
(Extreme foamed plastic or rubber rolls of Planner/Senior
High Risk) sheets of foamed plastic or Engineer.
foamed rubber, Foam mattress,
Expanded polystyrene packaging,
Foam upholstery, etc
Notes:-
(a) The deflector of the sprinkler fitted in the ceiling shall be at more than 1.5 m
from the goods stored below. However, in case of jute storage, no jute stock
shall reach within 2 m of the deflectors of the sprinkler heads.
(b) In case of storage in racks or shelves, if the height of storage is more than
what is specified, intermediate sprinklers shall be provided for each shelf/
rack in addition to the ceiling sprinklers and overall design density and
Assumed Maximum Area of Operation shall be maintained as per Table of
IS: 15105.
(c) The aisle width between the storage stacks shall not be less than 2.5 m and
the maximum area of each storage stack shall not be more than 150m2. If
these parameters are exceeded, the design density applicable shall be loaded
by 2.5 L/min/m2.
(d) In case of mixed storage (both moderate and high hazard storage) in buildings,
the parameters will be governed by the most hazardous occupancy.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2443
(e) Goods stored not higher than what is stated above table for the appropriate
category or not higher than the eaves height of the roofs or within 1 m of a
flat ceiling whichever is the lowest shall be regarded as moderate hazard
storage. If the above conditions are not met, the risk shall be regarded as
high hazard storage.
(f) Any new use which increases the number of occupants to a figure comparable
with other classes of occupancy shall change the classification of the building
to that of the new use (for example, Warehouse used for office purposes).
(g) Warehouse buildings shall not include any article which is highly combustible
or explosive materials or products which are liable to bum with extreme
rapidity and or which may produce poisonous fumes or explosions for storage,
handling and which involve highly corrosive, toxic or noxious alkalis, acids
or other liquids or chemicals producing flame, fumes and explosive, poisonous,
irritant or corrosive gases; and for the storage, handling of any material
producing ex-plosive mixtures of dust which result in the division of matter
in to fine particles subject to spontaneous ignition as such buildings fall in
Hazardous Building Category.
(3) Classification of risk based industrial building.- The provisions for site inspection
of risk based industrial building(s) are as per table given below:-
Classification of risk based industrial building
Category Nature of risk Designated
officer for site
Inspection
Low risk This subdivision shall include any building in which the Assistant Town
contents are of such comparative low combustibility and the Planner/
industrial processes or operations conducted therein are of Assistant
such a nature that there is hardly any possibility for any Engineer/ Senior
self- propagating fire to occur and the only consequent Divisional
danger to life and property may arise from panic, fumes or Engineer
smoke, or fire from some external source.
Medium This subdivision shall include any building in which the District Town
risk contents or industrial processes or operations conducted Planner/
therein are liable to give rise to a fire which will burn with Executive
moderate rapidity or result in other hazardous situation and Engineer.
may give off a considerable volume of smoke, but from
which neither toxic fumes nor explosions are to be feared in
the event of fire.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2444
High risk This subdivision shall include any building in which the Senior Town
contents or industrial processes or operations conducted Planner/Senior
therein are liable to give rise to a fire which will burn with Engineer.
extreme rapidity or result in other hazardous situation or
from which poisonous fumes or explosions are to be feared
in the event of a fire.
Hazard of occupancy shall be determined by the competent authority on the
basis of the fire loads of the contents, and the processes or operations conducted in
the building, provided, however, that where the combustibility of the material, the
flame spread rating of the interior finish or other features of the building or structure
are such as to involve a hazard greater than the occupancy hazard, the greater
degree of hazard shall govern the classification.
(a) For determination of fire loads and fire load density for arriving at the
classification of occupancy hazard, guidance on calorific values of some common
materials is given at Annexure ‘A’ of Part IV of the National Building Code of
India, 2016.
(b) A broad classification of industrial occupancies into low, moderate and high
hazard classes is given at Annexure ‘B’ of Part IV of the National Building
Code of India, 2016.
(4) Classification of risk based on nature of occupancy in building.- The provisions
for site inspection of risk based on nature of occupancy in building(s) are as per the
table given below:-
Classification of risk based on nature of occupancy in building
Category Nature of occupancy Designated
officer for site
Inspection
Low risk • Residential (excluding rental housing) and commercial Assistant Town
like shops, booths, sco's building and office below Planner/
15m height, Assistant
• Creche and Pre Nursery/ Nursery School Engineer/Senior
Divisional
Engineer
Category Nature of risk Designated
officer for site
Inspection
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2445
Medium • Residential and commercial like shops, booths, sco's District Town
risk building and office 15m and above but below 30m Planner/
• Educational building, Nursing Homes, Clinics, laboratory, Executive
below 15m Engineer.
• Orphanage Home , Old Age Home, Children's Centre/Care
Centre / School / Institute for Mentally challenged or
Physically Handicapped Person below 15m
• Hotel/ Motels, Guest House, Lodging & Boarding/Service
Apartments below 15m
• Restaurant/ Dabha seating capacity below 50 persons
• recreational, sports complex (low rise)
• rental housing below 15m
High risk • Assembly building like Religious, cinemas, multiplex, Senior Town
miniplex, concert hall, exhibition hall, convention centre, Planner/Senior
marriage palace, stadium, community centre, club, Engineer.
Religious Building, Auditorium, Museum, Gymnasium etc.
• Residential and commercial like shops, booths, sco's
building and office 30m and above
• Educational building, Nursing Homes, Clinics, laboratory,
15m and above
• Orphanage Home , Old Age Home, Children's Centre/Care
Centre School/Institute for Mentally challenged or
Physically Handicapped Person 15m and above
• Commercials such as Shopping Mall/Shopping Complex
• Restaurant/ Dabha seating capacity 50 persons and above
• Hospital
• Wholesale Trade/ Ware House/ Integrated Freight
complex (Standalone)
• rental housing 15m and above
Note: -
Inspection of the risk-based buildings site at the time of approval of building plan
shall be carried out as mentioned in tables below:-
(i) where the date of issuance of change of land use is within three months from
the date of application for approval of building plans
Category Nature of occupancy Designated
officer for site
Inspection
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2446
Serial Nature of Inspection of Remarks
Number risk site
I. Low risk Not Since the site has already been inspected at the
II. Medium applicable time of approval of Change of Land Use and the
risk application for approval of building plans has been
III. High risk submitted with in the period of three months.
Hence re-inspection of the site may not be required
after such a short period of time
(ii) where the date of issuance of change of land use exceeds a period of three months
Serial Nature of risk percent of random inspection Remarks
Number
I. Low risk 25 -
II. Medium risk 50
III. High risk 100
Provided that at the time of issuance of completion and occupation certificate,
100 percent inspection of all categories of buildings shall be carried out.
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2447
PART XIV
REGISTRATION OF PLUMBERS
47 Registration of Plumbers.- A plumber who is holding any of the qualifications
specified in the Annexure 20 and desirous of registration with the Authorized
Officer, shall make an application in Form ‘M’ along with such fee as is
determined by the Chief Administrator as a registration fee for a period of five
years.
48 Grant of registration.- If an application made under rule 47 is found in
order, the Authorized Officer may grant registration and issue a Registration
Certificate in Form-N to the applicant for registering him as Plumber.
49 Renewal of registration.- A Registration Certificate issued under rule 48 shall
be renewable for a period of five years on the payment of such renewal fee as
is determined by the Chief Administrator.
50 Cancellation of registration certificate.- A registration certificate granted
under rule 48 or renewed under rule 49, shall be liable to be cancelled by the
Authorized Officer, if the holder thereof contravenes any of the provisions of
the Act or the rules or regulations made thereunder or any direction issued
thereunder by the Competent Authority:
Provided that before cancelling the registration certificate, reasonable
opportunity of being heard shall be afforded to the holder of the registration
certificate.
Section
108 (2)
Section
108 (2)
Section
108 (2)
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2448
PART XV
MISCELLANEOUS
51 Relaxation.- The Government may relax any of the provisions of these rules,
for reasons to be recorded in writing, in respect of any class or category of
cases.
52 Matters not covered under these rules.- In respect of the matters which are
not directly or indirectly covered under these rules, the competent authority
shall be guided by the provisions of the National Building Code of India, 2016,
as amended from time to time.
53 Repeal and saving.- The Punjab Urban Planning and Development Building
Rules, 2018 are hereby repealed:
Provided that any order issued or any action taken under the provisions
of the rules so repealed, shall be deemed to have been issued or action taken
under the corresponding provisions of these rules.
Section
108 (2)
Section
108 (2)
Section
108 (2)
PUNJAB GOVT. GAZ., SEPTEMBER 10, 2021
(BHDR 19, 1943 SAKA)
2449
Annexure 1
FORM-‘A’
[see rule 11]
Previous and next
All provisions of The Punjab Urban Planning and Development Building Rules, 2021
Questions people ask
Is rule 19 of the Punjab Urban Planning and Development Building Rules, 2021 still in force?
No repeal of the Punjab Urban Planning and Development Building Rules, 2021 is recorded.