Regulation 6, The Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018: Declaration, scheduling and elimination of gaming
The Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018 - Regulation 6
Text of regulation 6
Declaration, scheduling and elimination of gaming
6. Declaration, scheduling and elimination of gaming.—(1) The provisions of the
Himachal Pradesh Electricity Grid Code, 2008, and the Himachal Pradesh Electricity
Regulation Commission (Short Term Open Access) Regulations, 2010 and the Himachal
Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and
Medium-term intra-State Open Access and Related Matters) Regulations, 2010, and other
appropriate regulations as may be relevant, as amended from time to time, shall be
applicable for declaration of capacity, scheduling and elimination of gaming.
(2) The generating stations, as far as possible, shall generate electricity as per the day
ahead generation schedule finalized by the State Load Despatch Centre in accordance with
the State Grid Code:
Provided that the revision in generation schedule on the day of operation shall be
permitted, in accordance with the procedure specified under the Himachal Pradesh
Electricity Grid Code, 2008 as amended from time to time.
(3) The QCA shall coordinate the aggregation of schedule of all generators
connected to a pooling station or selling power to the distribution licensee and communicate
it to the SLDC. The QCA shall undertake all commercial settlements on behalf of the
renewable energy generator(s) connected to the respective pooling station(s) or selling
power to the distribution licensee.
(4) The Commission, either suo motu, or on a petition made by SLDC or any affected
party, may initiate proceedings against any State Entity namely the generator, distribution
licensee, Open Access consumer etc. on charges of gaming and, if required, may order an
inquiry in such manner as decided by the Commission. When the charge of gaming is
established in the aforesaid inquiry, the Commission may, without prejudice to any other
action under the Act or Regulations made thereunder, disallow any Charges for Deviation
received by such State Entity during the period of such gaming.
Previous and next
Questions people ask
Is regulation 6 of the Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018 is recorded.