103. Repeal and Savings.-
(1) All rules as to the use of building sites and execution of building works, made
under the Tripura Municipal Act (herein after referred to as the former rules) and in force
immediately before the coming into force of these rules, shall, with effect from the date of
coming into force of these rules, cease to have effect.
(2) Notwithstanding such ceaser, every building plan sanctioned under the former
rules and remaining valid on date immediately before the date of coming into force of
these rules, shall continue to remain valid till the expiry of the period of validity thereof.
Page 75
PART —XII
Special Provisions on Huts, facilities for physically handicapped persons, Green
buildings and Sustainability provisions like Roof top solar energy installation, solar
1 04.
105.
assisted water-heating system. rainwater harvesting, wastewater recycling and
insurance of functional building;
Huts/mud Walls :-
In areas specially set apart in development plans and detailed Town Planning
Schemes, or in any area approved by the ULB, construction of huts may be allowed
subject to the following conditions:-
(a) Application for permission to construct or re- construct or alter or add to a
huts/Mud Walls shall be in the form set out vide these rules ( form set out in the Appendix
—“A” ) .
(b) A Hut/Mud Wall have 1.5 meters wide open space on all sides.
(c) A Hut/Mud Wall shall have its floor area at least 20 cm. above the surrounding
grounds.
(d) A Hut/Mud wall shall have a clear internal area of 4 square meters and minimum
width in any direction shall not be less then 2 mtrs.
(e) No Hut/Mud wall shall be of more than one storey. The minimum height at the
caves shall not be less than 2 meters.
(f) Every Hut/Mud wall shall invariably be provided with ventilating openings of not
less than 10 per cent of the floor area.
(g) Every Hut/Mud wall shall be provided with adequate sanitary and drainage
arrangements. Latrines shall be of water flush sanitary system.
(h) Application Fee for seeking permission to construct a Hut/Mud Wall, the rate will
be as per the fixed by the concerned ULB.
Green buildings and Sustainability provisions:-
(1) All buildings on various plot sizes above 500 sq.m. shall comply with the green norms
and conform to the requirements mandatory for sanction.
(2) Provisions and Applicability
The green building provisions on various plot sizes are indicated in the table below:
Provisions and applicability for various plot sizes ( Residential and Non-
Residential)
Plot Applicable plot Provisions for sanction as Provisions for sanction as
Category area(sq.m) sub rule (3) sub rule (3)
(Residential) (Non-Residential)
I Up to 500 Nil Nil
II 500 to 1000 1(a),1(c), 2(b), 3(c), 4(a) 1(a),1(c), 2(a), 2(b), 3(0),
4 a
1000 to 3000 1(a), 1(c), 1(d),2(a),2(b), 1(a),1(c), 1(d),2(a),2(b),
3(b),3(0),4(a) 3(b),3(0),4(a)
III Above3000 1 (a), 1(b), 1 (c), 1 (d), 2(a), 1 (a), 1 (b), 1 (c), 1 (d),2(a),
2(b),3(a),3(b),3(C),4(a),4(b) 2(b),3(a),3(b),3(0),4(a),
4(b)
Page 76
(3) Provisions for Sanction
1. Water Conservation and Management
a) Rain Water Harvesting
b) Low Water Consumption Plumbing Fixtures
c) Waste Water Recycle and Reuse
d) Reduction of Hardscape
2. Solar Energy Utilization
a) Installation of Solar Photovoltaic Panels
b) Installation of Solar assisted Water Heating Systems
3. Energy Efficiency (Concept ofpassive solar design of buildings)
a) Low Energy Consumption Lighting Fixtures (Electrical Appliances- BEE
Star and Energy Efficient Appliances)
b) Energy Efficiency in HVAC Systems.
c) Lighting of Common areas by Solar Energy/ LED devices.
4. Waste Management
a) Segregation of Waste
b) Organic Waste Management
In case owners of properties desire to procure green building rating from one or more
rating bodies, they may suitably incorporate any other provisions, if required.
106. Minimum provisions for DifferntIy-abled, Elderly and Children required in
various types of buildings.
(1) Applicability
These regulations shall be applicable to all buildings and facilities used by the
public such as educational, institutional, assembly, commercial, business,
mercantile buildings and group housing constructed on plots having an area of
more than 2000 sq.m. It shall not apply to private residential buildings.
(2) Guidelines andprovisions
Provisions in thefollowing guidelines shall apply .'
1. “Guidelines and Space Standardsfor Barrier Free Built Environmentfor Disabled
and Elderly Persons”, (1998), Central Public Works Department, G01.
2. “Manual on Barrier Free Environment”, (2002), 0/0 the Chief Commissionerfor
Persons with Disabilities, Ministry of Urban Development, G01.
3. “National Building Code”, (2005), Bureau ofIndian Standards.
4. “National Policyfor Persons with Disabilities (2006), Ministry ofSocial Justice
and Empowerment, G01.
5. “Harmonized Guidelines and Space Standards for Barrier Free Built
Environment for Persons with Disabilities and Elderly Persons”, (Draft 2014),
Ministry ofUrban Development, G01.
(3) Types ofbuildings to adopt barrierfree guidelines
(a) Buildings to be designedfor Ambulant Disabled People
Higher Secondary School, Conference Hall, Dance Halls, Youth Centers, Youth
Clubs, Sport Centers, Sport Pavilions, Boar Club Houses, Ice Rinks, Bowling
Centers, Swimming Pools, Police Stations, Law Courts, Courts Houses, Sport
Stadiums, Theaters, Concrete Halls, Cinemas, Auditoria, Small Oflicers (the
maximum plinth area 1400 sq.mt.) Snack Bars, Cafes and banqueting rooms 0'0r
capacity above 50 dinners).
Note:
Page 77
a. In sport stadiums provisions shall be madefor non-ambulant spectators(small
wheel-chair).
b. @ 1:1000 up to 10,000 spectators and @ 1 :2000for spectators above 10,000.
c. In Theaters, Concert Halls, Cinemas and Auditoria provisions shall be madefor
non-ambulant spectators (Small Wheel Chairs) @ 1/250 up to 1000 spectators
and 1/5000for spectators above 1000.
(b) Buildings to be designedfor Non-Ambulant Disabled People.
Schools for differently abled and all other buildings and along with Botanical
gardens, Religious Buildings, Elderly People Clubs, Village Halls, Day Centers,
Junior Training Centers, Post Oflices, Banks, Dispensaries, Railway Stations, Shops,
Super Markets, and Departmental Stores.
Note: Large wheel chair criteria shall be applicable on groundfloors of the following building, post
oflices, banks, dispensaries, railway station, shops, supermarkets, and departmental stores.
(c) Buildings to be designedfor Non-Ambulant People (Using small wheel chairs)
Public lavatories in Tourist Sports, Clubs Motels, Professional and Scientific
Institution, Museum, Art Galleries, Public Libraries, Laborites, Universities, College
for further Education, Teachers Training Colleges, Technical Colleges, Exhibition
Halls, Dentist Surgeries, Administrative Department of the Hospitals, Service
Stations, Car Parking, Buildings, Airports Terminals, Bus Terminals, Factories,
Employing differently abled for sedentary works, Large Offices, (with plinth area
abode 1400 sq.mt.), Tax Oflices, Passport Ofi‘ices, Pension Oflices, and Labour
Ofiices, Cafes, Banqueting Rooms and Snack Bars (For capacity above 100 dinners).
(d) Site development
Level of the roads, access paths andparking areas shall be described in the plan
along with specification ofthe materials.
(i) Access Path / Walk Way
Access path from plot entry and surface parking to building entrance shall be
minimum of 1800 mm wide having even surface without any steps. Slope, ifany, shall
not have gradient greater than 5%. Selection offloor material shall be made suitably
to attract or to guide visually impaired persons (limited to colouredfloor material
whose colour and brightness is conspicuously different from that of the surrounding
floor material or the material that emits difi’erent sound to guide visually impaired
persons; hereinafter referred “o” as “guidingfloor material”. Finishes shall have a
non-slip surface with a texture traversable by a wheel chair. Kerbs wherever
provided should blend to a common level.
(ii) Parking
Forparking ofvehicles ofdifferently-abledpeople, thefollowing provisions shall
apply:
a) Surface parking for two car spaces shall be provided near entrance for the
physically diflerently-abled persons with maximum travel distance of 30.0 m. from
building entrance.
b) The width ofparking bay shall be minimum 3.6 meter.
c) The information stating that the space is reservedfor wheel chair users shall be
conspicuously displayed.
Page 78
d) Guiding floor materials shall be provided or a device, which guides visually
impaired persons with audible signals, or other devices, which serves the same
purpose, shall be provided.
(4) Building requirements
The specified facilities in buildings for differently abled persons shall be as
follows:
((1) Approach to plinth level
Every building should have at least one entrance accessible to the diflerently
abled and shall be indicated by proper signage. This entrance shall be approached
through a ramp together with the stepped entry.
i. Ramped Approach: Ramp shall be finished with non-slip material to enter the
building. Minimum width of ramp shall be I800mm with maximum gradient 1;12.
Length of ramp shall not exceed 9.0 meter having 800mm high hand rail on both
sides extending 300mm beyond top and bottom of the ramp. Minimum gap from the
adjacent wall to the hand rail shall be 50mm.
ii. Stepped Approach: For stepped approach size of tread shall not be less than
300mm and maximum riser shall be I50mm. Provision of 800mm high hand rail on
both sides of the stepped approach similar to the ramped approach.
iii. Exit/Entrance Door: Minimum & clear opening of the entrance door shall be
900mm and it shall not be provided with a step that obstructs the passage ofa wheel
chair user. Threshold shall not be raised more than 12mm.
iv. Entrance Landing: Entrance landing shall be provided adjacent to ramp with
the minimum dimension I800mm x 2000mm. The entrance landing that adjoins the
top end of a slope shall be provided with floor materials to attract the attention of
visually impaired person’s flimited to coloured floor material whose colour and
brightness is conspicuously different fiom that of the surroundingfloor material or
the material that emits different sound to guide visually impaired persons. Finishes
shall have a non-slip surface with a texture traversable by a wheel chair, Kerbs
whereverprovided should blend to a common level.
(b) Corridor connecting the entrance/exitfor the differently abled
The Corridor connecting the entrance / exitfor difl‘erently abled leading directly
outdoors to a place where information concerning the overall use of the specified
building can beprovided to visually impairedpe3rsons either by a person or by signs,
shall be provided asfollows:
i) Guidingfloor materials ’ shall beprovided or device that emits sound to guide
visually impairedpersons.
ii) The minimum width shall be I500mm.
iii) In case there is a difference oflevel, slope ways shall beprovided with a slope of
1:12.
iv) Handrails shall be providedfor ramps/slope ways.
(5) Stair-ways
One ofthe stir-ways , near the entrance / existfor the dijferently abled shall have
thefollowingprovisions:
1) The minimum width shall be 1350 mm.
Page 79
ii) Height ofthe riser shall not be more than I50 mm and width ofthe tread 300 mm.
The steps shall not have abrupt (square) nosing.
iii) Maximum number ofrisers on aflight shall be limited to 12.
iv) Handrails shall be provided on both sides and shall extend 300 mm on the top
and bottom ofeachflight ofsteps.
(6) Lifts
Wherever lift is required as per bye-laws, provision of at least one lift shall be
made for the wheel chair user with the following cage dimensions of lift
recommendedfor passenger lift of 13 person ’s capacity ofNBC, BIS. Desirable Lift
size are:
Clear internal width 1100 mm.
Clear internal depth 2000 mm.
Entrance door width 900 mm.
a) A hand rail not less than 600mm long at 1000mm abovefloor level shall befixed
adjacent to the controlpanel.
b) The lift lobby shall be ofan inside measurement of1800 mm x 2000 mm or more.
c) The time ofan automatically closing door should be minimum 5 seconds and the
closing speed should not exceed 0.25 m/sec.
d) The interior ofthe cage shall beprovided with a device that audibly indicates the
floor, the cage has reached indicates that the door ofthe cage ofentrance/exit is
either open or closed.
e) Graphic/Braille signage, as per the Harmonized Guidelines, shall beprovided in
the lift lobby.
(7) Toilets
One special W.C. in a set of toilets shall be provided for the use of dijferently
abled with essential provision of washbasin near the entrance for the diflerently
abled.
a) The minimum size shall be 1500 mm x I 750 mm.
b) Minimum clear opening ofthe door shall be 900mm and the door shall swing out.
c) Suitable arrangement ofvertical/horizontal handrails with 50mm clearancefrom
wall shall be made in the toilet.
d) The WC. seat shall be 500 mm. from the door.
((1) Provision of W.Cs in buildings without lift:
Provision of special W.C. shall be made on allfloors for buildings designedfor
ambulant disabled persons. For buildings designed for non-ambulant disabled
special W.C. shall be provided at Ground Floor. Size of WC. shall depend on the
type ofwheel chair used by the disabled.
(b) Provisions of W.Cs in buildings with lift
Provision of Special W.C. shall be made on all floors. Size will depend on the
category ofdisabledfor whom it has been provided.
(c) Toilet Details: For Toilets Designedfor Ambulant Disabled
1) The minimum size of WC. shall; be 1075 x 1650 mm with a minimum depth of
I450 mmfrom entry door 900 mm.
Page 80
ii) Long handrail on the side closer to WC. with a clear width between the handrails
shall be 900 mm and height ofhandrails shall be 800 mmfromfloor level.
iii) Minimum size ofthe clear door opening shall be 780 mm.
(d) For Toilets Designedfor Non-Ambulant Disabled Small Wheel Chair:
The minimum size of WC. shall be I350 x I500 mm with minimum depth ofI500 mm
fiom entry door. 900 mm long handrail on the side closer to W.C. shall be provided.
To provide movement spacefor wheel chair, W. C. seat shall befixed towards one side
to the opposite adjacent wall. The centerline of WC. fiom the adjacent wall shall be
400 mm and minimum 950 mm from the other wall. Minimum size of the clear door
opening shall be 780 mm.
(e) For Toilets Designedfor Non-Ambulant Disabled Using Large Wheel Chair:
The minimum size of WC. shall be 1500 x I 750 mm with minimum depth ofI 750 mm
for entry door. 900 mm long handrail on the side closer to W.C. shall be provided. To
provide movement spacefor wheel chair, WC. seat shall befixed towards one side to
the opposite adjacent wall. The centerline of W. C. from the adjacent wall shall be 400
mm and a minimum of 1100 mm from the other wall. Minimum size of clear door
opening shall be 860 mm.
(8) Designingfor Children
In the buildings meantfor the pre-dominant use of the children, it wil be necessary to
suitably alter the height ofthe handrail and otherfittings &fixures etc.
Note ,' Guiding/ Warning Floor Material: The floor material to guide or warm the
visually impaired persons with a change of colour or material texture and easily
distinguishable fiom the rest of the surrounding floor materials. The material with
deferent texture gives audible signals with sensory warning when a person moves on
this surface with walking stick. The guiding / warningfloor material is meant to give
the directional eflect or warm a person at criteria places. It should be provided in the
following areas:
a. The access path to the building and to theparking area.
b. The landing lobby towards the information board, reception, lifts staircases and
toilets.
c. Immediately at the beginning / end ofwalkway where there is a vehicular traflic.
d. At the location abruptly changing in level or beginning /end ofa ramp.
e. Immediately in front ofan entrance /exit and the landing.
(9) Drinking Water:
Suitable provision of drinking water shall be made for the differently abled near the
special toiletprovidedfor them.
(10) Refuge:
An alternative to immediate evaluation ofa building via staircases and/ or lifts is the
movement of disabled persons to areas ofsafety within a building. Ifpossible, they
could remain there until thefire is controlled and extinguished or until rescued by the
firefighters.
a) It is useful to have provisions of a refuge area, usually at thefire protected stair
landing on eachfloor that can safely hold one or two wheelchairs.
b) Hand Doorways with clear opening width of900 mm and regular compliance
c) Have an alarm switch installed between 900 mm and 1200 mmfromfloor level.
Page 81
(1]) Proper signage
a) appropriate identification ofspecific facilities within a buildingfor the differently
abledpersons should be done with proper signals.
b) Visually impaired persons make use of other senses such as hearing and touch to
compensate for the lack of vision, whereas visual signals benefit those with hearing
disabilities. Signs should be designed and located so that they are easily legible by
using suitable letter size (not less than 20 mm high)
c) For visually impairedpersons, information board in brail should be installed on the
wall at a suitable height and it should be possible to approach them closely.
d) T0 ensure safe walking, there should not be any protruding sign which creates
obstruction in walking.
e) Public Address system may also be provided in busypublic areas.
fl The symbols /information should be in contrasting colour and properly illuminated
because people with limited vision may be able to dijferentiate amongst primary
colours.
g) Internal Symbol Markfor wheel chair be installed in a lift, toilet, staircase, parking
areas, etc., that have been providedfor the differently abled.
(12) Public Building regulations
In case of design regulations in public buildings (excluding domestic buildings),
provisionsfor differently-abled shall be adopted as below:
To Provide Facilitates in the Public Building Excluding Domestic Buildingsfor
Difl‘erently—abled Persons
a. Definitions
Ambulant Disabled People: Disabled who are able to walk but who may depend
on prostheses (Artificial Limbs) orthoses
(Calipers), Sticks, Crutches or Walking aids.
Non-Ambulant Disabled People: Disabledpeople impairments that confine them
to wheelchair.
Wheel Chair: Chair used by disabledpeoplefor mobility.
1) Size ofsmall wheel chair: 750 x 1050 mm
i1) Size of large wheel chair: 800 x 1 500 mm
b. Scope
These bye-laws are applicable to public buildings and exclude domestic building.
Building which shall provide access to ambulant disable and Non-Ambulant
disabled are listed below. Distinction is madefor buildings to be designedfor the
use of large wheel chairs and small wheel chairs.
c. Building to be designedfor Ambulant Disabled People
Higher Secondary School, Conference Hall, Dance Halls, Youth Centers, Youth
Clubs, Sport centers, Sport Pavilions, Boat Club Houses, Ice Rinks, Bowling
Centers, Swimming pools, Police Stations, Law Courts, Courts Houses, Sport
Stadium, Theaters, Concert Hall, Cinemas, Auditorias, Small Oflices ( the
maximum plinth area 1400 sq. mt) Snack Bars, Cafes and banqueting rooms 0'0r
capacity above 50 dinners)
Note:
1) In sport stadiums provisions shall be madefor non-ambulant spectators (small wheel chair)
ii) @ 1:1000 up to 10,000 spectators and @ 1 :2000for spectators above 10,000.
iii) In Theaters, Concert Halls, Cinemas and Auditoria provisions shall be made for non-ambulant
spectators (Small Wheel Chairs) @ 1/250 up to 1000 spectators and 1/ 500 for spectators above
1 000.
Page 82
107.
d. Building to be designedfor Non-Ambulant Disabled People:
Schools for physically handicapped, cremation, buildings as mentioned in 3,
Botanical Garden, Religious Buildings, Old People Clubs, Village Halls, Day
Centers, Junior Training Center, Post Oflices, Banks, Dispensaries, Railway
stations, Shops, Super Markets, and Departmental Stores.
Notes: Large Wheel Chair Criteria shall be applicable on groundfloors ofthefollowing building. Post
oflices, banks, dispensaries, railway stations, shops, Supermarkets and departmental stores.
e. Building to be designedfor Non-Ambulant People (Using Small Wheel Chairs)
Public lavatories in Tourist Sports, Clubs Motels, Professional and Scientific
Institution, Museum, Art Galleries, Public Libraries, Laborites, Universities,
Collage for further Education, Teachers Training Collages, Technical Collages,
Exhibition Halls Dentist Surgeries, Administrative Department of the Hospitals,
Service Stations, Car Parking, Buildings Airports Terminals, Bus Terminals,
Factories Employing Handicapped for sedentary works, Large Oflices, fl/Vith
Plinth area abode 1400 sq. mt), Tax Oflices, Passport Oflices, and Labour
Oflices, Cafes, Banqueting Rooms and Snack Bars (For Capacity Above 100
dinners).
f. Buildings Requirements:
All Building requirements for buildingprojects proposed under this category shall
be conforming to Annex D, Part 3 ofNBC.
Roof top solar energy installation.
Rooftop photovoltaic power station, or rooftop PV system, is a photovoltaic system
that has its electricity igenerating solar panels mounted on the rooftop of any
building. The various components of such a system include photovoltaic modules,
mounting systems, cables, solar inverters and other electrical accessories. Rooftop
PV systems are faster than other types of renewable power plants. They are clean,
quiet, and visually unobtrusive. Table below stipulates the Normsfor Roof Top solar
PVInstallation-
Normsfor Roof Top Solar PVInstallation and generation
Sl. Category of Area standards Generation requirement*
No. buildings/area
I Plotted Housing Plot size of 500 sqmt Minimum 5% of connected load
and above or 20W/sqft for ”available roof
space “,** whichever is less.
2 Group Housing Allproposals, as per Minimum 5% of connected load
Group Housing or 20W/sqft for “available roof
Norms space whichever is less.
3 Educational Plot size of 500 sqmt Minimum 5% of connected load
4 Institutional and above or 20 W/ sqft for “available roof
5 Commercial space”, whichever is less.
6 Industrial
7 Mercantile
8 Recreational
*Area provisions on roof top shall be @ 12sqmt per 1KWp, as suggested by Ministry of New
and renewable Energy.
** ”available rood area” = 70% of the total roof size, considering 30 % area reserved for
residents’ amenities.
Page 83
108. Installation of Solar Assisted Water Heating System in Govt. functional Building;
109.
Installation of Solar water Heating System:
(a) New Building:
Clearance of plan for the construction of new buildings shall only be given
if they have a provision in the building design itself for insulated pipelines from
the rooftop in the building to various distribution points where hot water is
required. The buildings must have a provision for continuous water supply to the
solar water heating system. The building should also have open space on the
rooftop, which receives direct sun light. The load bearing capacity of the roof
should at least be 50 Kg. per sqm. All new buildings must complete installation of
Solar Water Beating Systems before obtaining necessary license to continuance
their business.
(b) Existing Buildings:
Installation of Solar Assisted Water Heating Systems in the existing
building is mandatory at the time of change of use provided there is a system or
installation for supplying hot water. The ULB will strictly observe it while changing
the pattern of use.
(c) Capacity:
The capacity of Solar Water Heating System to be installed on the
building of different categories shall be decided in consultation with the ULB. The
minimum capacity shall not be less than 25 liters per day for each bathroom and
kitchen subject to the condition that maximum of 50% of the total roof area is
provided with the system.
(d) Specification:
Installation of Solar Assisted Water Heating System shall conform to BIS
(Bureau of Indian Standards) specification IS 12933.The Solar collectors used in
the system shall have the BIS certification mark.
(e) Auxiliary System:
Wherever hot water requirement is continuous auxiliary heating
arrangement either with electric elements or oil of adequate capacity can be
provided.
Categories of buildings/gublic u_tilitv mces where So_lar Assisted Water Heating
Systems are to be installed:-
The following categories of buildings in which there is a system of installation
for supplying hot water shall be built unless the system or the installation is also having
an auxiliary solar assisted water heating system:
(a) Hospitals & Nursing Homes;
(b) Hotels, Lodges and Guest Houses;
(c) Hostels of Schools, Colleges, Training Centres
(d) Barracks of armed forces, paramilitary forces and polices;
(e) Individual residential building having more than 150 sq. meter. plinth area;
(f) Functional Buildings of Railway stations and Air Ports - like waiting rooms,
retiring rooms, rest rooms, inspection bungalows and catering units;
(g) Community centres, Banquet Halls, Barat Ghars, Kalyan mandaps and buildings
for similar use.
Page 84
110. Provision for rainwater harvesting, wastewater recycling and Solid Waste
Management:-
(a) Rain Water Harvesting;
(1) The RWH system
The harvesting of rainwater simply involves the collection ofwaterfrom surfaces
on which rain falls, and subsequently storing this water for use. The rainwater
collected can be storedfor direct use or can be recharged into the underground
aquifers. In scientific terms water harvesting (broadly) refers to collection and
storage of rainwater from the rooftops. This also restricts evaporation and
seepage into building foundations. All building having plinth area not less than
200 sq.m., while submitting the building plans for sanction, shall mandatorily
include the complete proposal ofrainwater harvesting.
A rainwater harvesting system consists of:
i. Roof catchment
ii. Gutters
iii. Down pipes
iv. Rain water/Storm water drains
v. Filter chamber
vi. Storage Tanks/ Pits/ sumps,
vii. Ground Water recharge structures like pit, tube well or combination ofabove structure.
(2) Rainwater harvesting techniques:
There are two main techniques of rain water harvestings. They are Storage of rainwater
on surfaceforfuture use and Recharge to ground water.
The technical aspects and options ofRainwater harvesting are asfollows:
The storage of rain water on surface is a traditional technique and the structures used
were underground tanks, ponds, check dams, weirs etc. Recharge to ground water is a
new concept ofrain water harvesting and the structures generally used are:-
i. Pits: Recharge Pits are constructed for recharging the shallow aquifer. These are
constructed 1 to 2m wide and to 3m deep which are backfilled with boulders, gravels,
coarse sand.
ii. Trenches: These are constructed when the permeable steam is available at shallow
depth. Trench may be 0.5 to 1m. wide and I to 1.5m. deep and 10 to 20m long
depending up availability ofwater. These are backfilled withfiller materials.
iii. Dug wells: Existing dug wells may be utilized as recharge structure and water should
pass throughfilter media beforeputting into dug well.
iv. Handpumps: The Existing handpumps may be usedfor recharging the shallow/ deep
aquifer, if the availability of water is limited. Water should pass through filter media
before diverting it into handpumps.
Page 85
v. Recharge wells: Recharge wells of 1 00 to 300 mm. diameter are generally constructed
for recharging the deeper aquifer and water is passed through filter media to avoid
choking ofrecharge wells.
vi. Recharge Shafts: For recharging the shallow aquifer which are located below clayey
surface, recharge shafts of0.5 to 3m.diameter and 10 to 15 m. deep are constructed and
backfilled with boulders, gravels & coarse sand.
vii. Lateral shafts with bore wells: For recharging the upper as well as deeper aquifers
lateral shafts of 1.5 to 2 m. wide & 10 to 30 m. long depending upon availability of
water with one or two bore wells are constructed. The lateral shafts are backfilled with
boulders, gravels & coarse sand.
viii. Spreading techniques:
Spread the water in streams/Nalas by making check dams, nala bunds, cement plugs,
gabion structures or a percolation pond may be constructed.
(3) Harvestingprovisions in various Building categories:
All building in a city contribute to the rain water runofl during the monsoon and hence
such runoflcan be harvestedfor water reuse/ recharge.
The mandatory provision ofrainwater harvesting in various building types are asfollows:
When permeable strata from top then this technique used.
Provision for Rainwater harvesting by building types
Category/Use Plinth area
building (sq.m)
0f Provisions to be made Other conditions
Residential Plotted House
New Proposals 200 and above Construction of Rain water Harvesting Shall have emphasis on both
Structure storage and reuse.
Group Housing
New Proposals All sizes i) Construction of rain water Harvesting Should indicate the system of
Structure.
it) Concrete paving to be avoided and
permeable materials are to be usedfor all
open parking spaces.
Strom Water Drainage. Rain
Water Harvesting Structure
and Recharging Well
Public and semi public buildings
All Proposals All sizes i)Shall have rain
structure and storage
ii)Shall have Recharge pits
Water Harvesting Shall have emphasis on both
storage and reuse.
Commercial/Mixed use
All Proposals 50 and above i)Construction of Rain water Harvesting Should indicate the system of
Structure. Strom Water Drainage. Rain
ii)Soft landscape provisions and open Water Harvesting Structure
spaces with Percolation pits. and Recharging Well.
iii)Common treatment plant to be made
part of the integrated development, Shall have emphasis on both
funded by sale ofcommercial space. storage and reuse.
Industrial
All Proposals All sizes I) Construction ofRain Water Harvesting Should indicate the system of
Structure.
it) Soft landscape provisions and open
spaces with Percolation pits.
iii) Use of abandoned bore wells for
Strom Water Drainage, Rain
Water Harvesting Structure
and Recharging Well.
Provision should be made not
Page 86
recharging ofground water.
iv) Common treatment plant to be made
part ofthe integrated developmentfunded
by sale ofcommercial space.
to inject contaminated water
into recharge structures in
industrial areas and care is
to be taken to keep such
structures away from sewer
lines. Septic tanks, soak pits,
landfill and other sources of
contamination.
Otherproposals 50 and above Similar as above Similar as above.
(4) Rain Water Harvesting Provisionsfor Open spaces in cities
The open spaces/ recreational land use generally constitute regionalparks, districtparks,
play ground and stadium, sports complex, monument zones, public parking, plaza and
other public open space. This may be as high as 30% to 50% of the city’s geographic
area. All such public open spaces above the size of500 sq.m shall have arrangements for
complete utilization and capture of storm water with scientific rain water harvesting
arrangements.
Following ideas may also be included:
i) Well cum Channel cum percolation pits.
ii) Use of abandoned bore wells for recharging ofground water
iii) Artificial or natural storage ofstorm water runofffrom larger sites.
(5) Ground Water Recharge
Recharging ofground water should be made mandatory not only for residential building
butfor all types ofbuildings, including Group Housing Societies having a plot area more
than 500 sq. m. and above.
The Ground Water Recharge should also be mandatory for open spaces like parks,
parking, plazas and playgrounds. The harvesting and recharge structures could be
constructed by the authority with the involvement of community based organizations like
Resident Welfare Associations.
(6) Enforcement and Monitoring
i. The ULB shall constitute a rainwater Harvesting Cell which will be responsible for
enforcement and monitoring of the Provisions of Rainwater Harvesting. The cell shall
employ qualified persons who are well versed with the interpretation of Building Bye
Laws and responsible for enforcement as well as monitoring the functioning of the
Rainwater Harvesting System.
ii. The Authority shall include inspection of rainwater Harvesting Structures before
issuing Completion Certificates or NOCsfor service connections to the property.
iii. Set an example in the city by ensuring that Rainwater is harvested in the properties/
assets owned by them including public building, markets, community centers, parking
spaces, roads andparks etc.
iv. the Authority shall also establish a mechanism to monitor 100% ofRWHprovisions in
all the building above 1000 sq.m with annual physical verification, while building less
than [000 sq.m. can be monitored on the basis of 10% random survey by competent
authority.
Page 87
111.
v) With regard to open public spaces viz., Parks, playgrounds etc, the implementation of
provision rainwater harvesting may be done with the help of Residents Welfare
Associations, Community Building Organizatin and Non-Governmental Organisations.
vi. The Authority shall ensure earmarking budgetary provision for the creation and
maintenance ofrainwater harvesting structures in public spaces owned and maintained by
them, likeparking spaces, parks, plazas etc.
vii. The practice of incentives and penalties to promote rain water harvesting shall be
formulated by the ULB based on best practices. ULB shall design its own incentive and
penalty systems, considering the water level and scarcity.
(b) Wastewater Recycling (Water Re-use and Recycling); All buildings having
total covered area more than 10,000 square meters OR all buildings having a waste
water discharge of 10,000 litters and above per day shall set up a Sewerage Treatment
Plant (STP), which shall bring sewerage and waste water within the prescribed
parameters as per Indian standards. Recycled water should be used for toilet blocks or
horticultural purpose.
(c) Solid Waste Management: - All buildings having total covered area more than
10,000 square meters shall set up a comprehensive system of collection, transportation
and disposal of municipal solid waste strictly in accordance with the latest version of Solid
Waste Management Rules.
Provision for insurance of building
(a) All the residential buildings having plinth area more than 300 Sq. meters or
above 3 storied’l shall be insured for any natural calamities/fire hazard with an insurance
company registered under the Insurance Company Act prevailing in India.
(b) All the buildings other than residential having 2 storey’s and above shall be
insured for any natural calamities/fire hazard with an insurance company registered under
the Insurance Company Act prevailing in India.
(c) It is the owner’s responsibility to insure the building as per norms and intimate
the local body along with copy of insurance details.
Page 88
Appendix—A
Form for application to erect or re-erect a Hut/Mud Wall.
(Ref. Rule No.104)
To
The Mayor/Chairperson
Municipal Corporation/ Municipal Council/ Nagar Panchayat.
Sir,
I intend to erect/re—erect lalter a hut/mud wall in Ward No. Holding No.
of Road/ village in
Tahasil. | fonNard herewith the following
particulars duly signed by me.
1. Diagrammatic sketch of proposed hut/mud wall (triplicate).
2. General description of work (in triplicate).
3. Proof of ownership of land, Regd. Deed parcha etc.
4 Copy of receipt for payment of application fee.
I hereby undertake to abide by the provisions of Tripura Building Rules, 2004 in all
respect.
I request that the erection/re-erection/alteration may be approved and permission
accorded to me to execute the work.
Signature of owner
Name of owner:
(in Block Letters)
Address:
Page 89
PART-XIII
Miscellaneous
W
(See Rule 5)
Application for approval of a site for a Building
From (Name in full in block letters)
(Address)
To
The Mayor/Chairperson
Municipal Corporation/ Municipal Council/ Nagar Panchayat.
Sir,
INVe hereby give you notice the premises No./Holding No. in
street Ward /Circle
will be used in future as Residential /Commercial / Industrial /Public Building /others (specify)
and | forward herewith.
A site plan in triplicate of the land for your approval as prescribed in Rule 5 of the
Building Rules under the Tripura Municipal Act 1994.
The reports/recommendations of the soil test and for stability of slope as required under
Rule 17 is enclosed.
| request that the site plan may be approved.
Countersigned Yours faithfully
Architect/ Licensed Building Planner. Signature of Owner/Owners
Dated : Address:-
Page 90
Previous and next
Questions people ask
Is rule 103 of TRIPURA BUILDING RULES — 2017 still in force?
No repeal of TRIPURA BUILDING RULES — 2017 is recorded.