Text of regulation 32
Deviation from Norms
32. Deviation from Norms.—Tariff for sale of electricity generated from
a generating station based on renewable energy sources, may also be agreed
between a generating company and a licensee, in deviation from the norms
specified in these regulations subject to the conditions that the levellised tariff
over the useful life of the project on the basis of the norms in deviation does not
exceed the levellised tariff calculated on the basis of the norms specified in
these regulations.
33. Solar Power Banking
(i) The facility of banking of solar power will be provided by Bihar
State Power Holding Co. Ltd. (BSPHCL)/distribution licensee to
solar power generated for captive use, group captive use and for
third party sale
(ii) 2% of the energy fed into the grid for banking by the generator
will be paid as banking charge to BSPHCL/distribution licensee.
(iii) Banking facility will be available for full calendar year. In case
energy fed into the grid for banking is not consumed within the
same calendar year, it cannot be used by the generator or its
user in the subsequent calendar year. However, the
BSPHCL/distribution licensee will pay to the generator for the
unused energy during the calendar year at the average power
17
BIHAR GAZETTE (EXTRA), 24TH OCTOBER 2017
purchase cost of BSPHCL/distribution licensee during that
calendar year.
(iv) Adequate metering facility will be provided by the distribution
licensee to enable measurement of input and consumed energy
at different points of time including provision of check meters of
appropriate accuracy class at consumer's end, calibrated
annually.
(v) In case of third party sale of solar power, the transmission
licensee, distribution licensee and/or SLDC, as the case may
be, will provide open access within 30 days of application on
payment of required open access charges as determined by the
Commission and the generator in addition to 2% banking
charge, will pay to the BSPHCL/ distribution licensee wheeling
and transmission charges and T&D losses as determined by the
Commission for the voltage level at which power is fed into the
grid. However, no cross-subsidy surcharge will be paid.
(vi) Drawal of Banked energy shall not be permitted during the peak
hours.
(vii) Solar Power Developer having no PPA for supply of power to
DISCOM should draw power during shutdown/maintenance of
the plant of the applicable UI rate plus 5% of the maximum UI
rate or applicable rate for purchase of power from renewable
energy source, whichever is higher.
Previous and next
Questions people ask
Is regulation 32 of Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 still in force?
No repeal of Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 is recorded.