Regulation 27, Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017: Technology specific parameters for Non-fossil fuel based Cogeneration Projects. I. Technology Aspect
Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 - Regulation 27
Text of regulation 27
Technology specific parameters for Non-fossil fuel based Cogeneration Projects. I. Technology Aspect
27. Technology specific parameters for Non-fossil fuel based
Cogeneration Projects.
I. Technology Aspect.—A project shall qualify as a non-fossil fuel
based Co-generation project, if it is in accordance with the
eligibility criteria as specified under Regulation 4(c).
II. Capital Cost.—The normative capital cost for the non-fossil fuel
based cogeneration projects shall be Rs. 492.5 Lakh/MW for high
boiler pressure projects for the first year of Control Period (i.e. FY
2017-18), and will remain valid for the entire duration of the
control period unless reviewed earlier by the Commission.
III. Plant Load Factor.—
(1) For the purpose of determining fixed charge, the plant load
factor for non-fossil fuel based cogeneration projects shall be
computed on the basis of plant availability for number of
operating days considering operations during crushing
season and off-season as specified under clause (2) below and
load factor of 92%.
(2) The number of operating days shall be as follows:
IV. Auxiliary Consumption.—The auxiliary power consumption
factor shall be 8.5% for the computation of tariff.
V. Station Heat Rate.—The Station Heat Rate of 3600 kCal / kWh
for power generation component alone shall be considered for
computation of tariff for non-fossil fuel based Cogeneration
projects.
VI. Calorific Value.—The Gross Calorific Value for Bagasse shall be
considered as 2250 kCal/kg. For the use of biomass fuels other
than bagasse, calorific value as specified under Regulation 26
shall be applicable.
VII. Fuel Cost
(1) The price of Bagasse first year of the Control Period (i.e. FY
2017-18) shall be Rs. 1964.71/MT. For each subsequent year
of the Control Period, the normative escalation factor of 5% per
annum shall be applicable at the option of the project
developer or as decided by the Commission.
(2) For use of biomass other than bagasse in co-generation
projects, the biomass prices as specified under Regulation 26
shall be applicable.
VIII. Operation and Maintenance Expenses
(1) Normative O&M expenses during first year of the Control
period (i.e. FY 2017-18) shall be Rs. 21.13 Lakh per MW.
(2) Normative O&M expenses allowed at the commencement of
the Control Period (i.e. FY 2017-18) under these Regulations
shall be escalated at the rate of 5.72% per annum.
Previous and next
Questions people ask
Is regulation 27 of Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 still in force?
No repeal of Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017 is recorded.