Regulation 40, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017: CDM benefits
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 - Regulation 40
Text of regulation 40
CDM benefits
40. CDM benefits.—(1) In case of small hydro projects, the proceeds of carbon credit from
approved CDM project shall be retained by the Small Hydro Project generator and shall not
be adjusted in the tariff.
(2) In case of renewable energy technologies, other than the small hydro projects,
the CDM benefit shall be shared in the following manner, namely:-
(a) 100% of the gross proceeds on account of CDM benefit to be retained by the
project developer for the year in which the project commences its operation and
the first year immediately thereafter;
(b) In the second year i.e. after the expiry of period mentioned in clause (a) above,
the share of the beneficiaries shall be 10% which shall be progressively
increased by 10% every year till it reaches 50%, where after the proceeds shall
be shared in equal proportion, by the generating company and the beneficiaries.
Previous and next
Questions people ask
Is regulation 40 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.