Regulation 39, The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017: Operation and maintenance expenses
The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 - Regulation 39
Text of regulation 39
Operation and maintenance expenses
39. Operation and maintenance expenses.—(1) Normative annual O&M expenses for the
control period shall be as follows:—
Sr.No. Category of Project Annual O&M expenses
Rupees in Lac per MW
(i) Above 100 kW to 2 MW capacity 33
(ii) Above 2 MW to 5 MW capacity 29
(iii) Above 5 MW to 25 MW capacity 24
1[ PART-II]
TECHNOLOGY SPECIFIC PARAMETERS FOR SMALL HYDRO PROJECTS
(APPLICABLE FROM 01.10.2019 To 31.03.2020)]
33-A. Categorisation.—For the purpose of tariff determination, the small hydro projects shall
be categorized as under:—
(i) Above 100 kW to 2 MW capacity
(ii) Above 2 MW but below 5 MW capacity
(iii) 5 MW to 25 MW capacity
1
Ins. consequential amendments in the Regualtions “Part-II” vide not. No. HPERC/428 dated 11th November,
2019, published in R.H.P. dated 18th November, 2019 at p. 7983-7995.
Compendium of HPERC Regulations, March 2021 49
34-A. Normative Capital Cost.—(1) In case of small hydro projects, the normative capital
cost inclusive of all its components as specified in regulation 21-A of these Regulations, for
the control period shall be as under:—
Sr.
No.
Category of small hydro project Rupees (in Lac) per MW
of the installed capacity
(i) Above 100 kW to 2 MW capacity 1000
(ii) Above 2 MW but below 5 MW capacity 1000
(iii) 5 MW to 25 MW capacity 900
(2) The subsidy/grant/budgetary support or incentives provided by the Central/State
Government or their agencies shall be adjusted in accordance with the regulation 22-A of these
Regulations.
35-A. Normative saleable energy.—(1) The normative saleable energy at the
interconnection point for the purpose of generic levellised tariff shall be computed on the
following lines namely:—
(i) the normative annual capacity utilisation factor (CUF) for all the small hydro
projects upto 25 MW shall be 55%. The number of hours in a year for
calculations of CUF shall be 8766;
(ii) the normative annual energy worked out at the normative CUF under
preceding clause (i) for the installed capacity shall be adjusted for the
auxiliaryconsumption, transformation losses and the losses in the project
line(s) at the normative rates as per regulations 37-A and 38-A;
(iii) the energy worked out under preceding clause (ii) shall be further reduced by
the permissible rate of the free power subject to a maximum of 13%, for any
year or part thereof, consistent with the National Hydro Policy, Tariff Policy
and the policy of the State Government for allotment of sites of small hydro
projects in the manner as laid down in regulation 36-A, so as to arrive at the
year wise normative net saleable energy at the interconnection point which
shall be taken into account for working out the generic levellised tariff:
Provided that in case the limit of 13% for the pass through of free
power in the tariff as per the National Hydro Policy/Tariff Policy is revised by the
Central Government, or staggered by the Government, at any stage, the Commission
may review the tariff(s) as per the provisions under regulations 20.
(2) The normative capacity utilization factor (CUF) under clause (i) of sub-
regulation (1) takes into account the impact of mandatory release of water discharge
immediately downstream of diversion structure of the project based on the existing
instructions of the State Government which provide that for the purpose of determination of
minimum discharge, the threshold value not less than 15% of the minimum inflow observed
in the lean season shall be considered.
(3) The normative yearwise net saleable energy for the purpose of project specific
tariff determination shall also be worked out on similar lines given in sub-regulations (1) and
(2) but by taking into account the annual Capacity Utilisation Factor (CUF) in accordance
with clause (ii) of sub-regulation (1) of regulation 15, the normative auxiliary consumption
and transformation losses under regulation 37-A and the energy losses in the project line
under regulation 38-A.
50 Compendium of HPERC Regulations, March 2021
36-A. Free Power.—(1) The Commission shall consider appropriate structure(s) of free
power for determination of generic levellised tariffs for various categories of small hydro
projects, as mentioned in regulation 33-A, duly keeping in view of the provisions of the
State Hydro Policy for allotment of sites for small hydro projects, National Hydro Policy,
Tariff Policy and the limits specified under sub-regulation(3):
Provided that in case the structure of free power actually applicable to a project, duly
curtailed as per sub-regulation (3), is at variance from the structure considered while
determining the generic levellised tariff, such tariff shall be suitably adjusted based on the
structure of free power applicable subject to the limit specified in sub-regulation (3):
Provided further that in cases requiring determination of the project specific tariff,
the Commission shall consider the structure of free power actually applicable to that project
subject to the above and the limits specified in sub-regulation(3).
(2) In case of any change in the structure of free power for a small hydro project
from that considered for the determination of generic levellised tariff or project specific
levellised tariff in accordance with sub-regulation (1) or in cases where the adjustment in
tariff on account of variation in free power has to be allowed as per the specific provisions
contained in these Regulations, including those covered in regulation 17 and sub-regulation
(2) of regulation 20, the distribution licensee shall adjust the tariff as per the following
formula:—
Rate payable for the month for the net saleable Energy (Rs./kWh) = a x (100-b)/(100-c)
Where,—
“a” is the levellised tariff (in Rs./kWh) which is required to be adjusted under this
regulation
“b” is the free power (in percentage) taken into account or deemed as taken into
account forthe month, in “a” in the corresponding month of the tariff period by
reckoning the date of commencement of operation of the project as the starting date
of the tariff period.
“c” is the free power (in percentage) to be allowed in the tariff for the month subject
to maximum limit of 13% free power(energy) and the provisions of sub- regulation
(3)—
Where free power is applicable at different rates for different parts of a month, the
permissible free power (i.e. “c”) shall be determined under this sub-regulation separately for
each such part and weighted average rate for the month as a whole shall be worked out by
considering the total quantum of energy for each day of the month.
(3) The free power (in percentage) to be taken into consideration for the purpose of
determination of tariff under sub-regulation (1) and/or any adjustment under sub-regulation
(2) shall be subject to the following:—
(i) The free energy to be taken into account for any part of the tariff period for
the purposes of sub-regulation (1), or to be allowed for any part of the tariff
period for the purposes of sub-regulation (2), shall not exceed 13% freepower
(energy) which includes 12% free power to home State and 1% additional
free power for Local Area Development Fund, as stipulated in the National
Hydro Policy/Tariff Policy;
Compendium of HPERC Regulations, March 2021 51
(ii) Any quantum of free energy, if committed by the renewable energy generator
over and above the 13% free power (energy) for any period shall not be
factored into the tariff;
(iii) Additional free energy, if any, to be provided by the renewable energy
generator to the State Government, on account of curtailment of waiver
period due to delay in commissioning of project as per provisions of
Implementation Agreement and/or for enhancement of capacity and/or for
any reason attributed to the renewable energy generator shall not be taken
into account even if the total free power for any period, including such
additional free power, does not exceed 13% free power(energy);
(iv) The quantification and adjustment of free energy as well the energy
accounting shall be made with reference to the energy projected/received at
the interconnection point;
(v) The free energy to be allowed for any period for the purpose of sub-
regulation (2) shall in no case be more than that actually deducted for that
period in the energy accounts, out of the total energy received at the
interconnection point.
[
Note.—In case of the deferment of free power by the State Government, the
provisions of the sub-regulation (2) shall not be applicable for the adjustment
in tariff on account of change in the structure of free power to the extent such
change is caused due to deferment of free power by the State Government.
37-A. Auxiliary consumption and transformation losses.—Normative auxiliary
consumption and transformation losses for the small hydro projects shall be 0.5% of the
gross generation and the same for transformation losses at the switchyard linked to the
generating station of the projects shall also be 0.5%:
Provided that for the sake of simplicity, these two factors shall be clubbed together
and accounted for as 1% of the gross generation.
38-A. Energy losses.—The normative energy losses in the project line(s) shall be 0.7% of
the net generation (i.e. after deducting auxiliary consumption and transformation losses, on
normative basis, from the gross generation).
(2) For the project specific levellised tariff, the percentage losses worked out on the
basis of actual length of the project line(s), conductor size and expected power flow shall be
taken into consideration.
39. Operation and maintenance expenses.—(1) Normative annual O&M expenses for the
control period shall be as follows:—
Sr.
No.
Installed capacity of SHP Annual O & M expenses in lac
rupees per MW of installed
capacity
(i) Above 100 kW to 2 MW capacity 37
(ii) Above 2 MW but below 5 MW capacity 32
(iii) 5 MW to 25 MW capacity 27
52 Compendium of HPERC Regulations, March 2021
39-AA. Adjustment for fraction of a MW of the installed capacity.—The installed
capacity shall be rounded to one decimal place by ignoring the fraction of less than 0.05
MW and by considering the fraction of 0.05 MW and above as 0.1 MW.]
1
[PART-III
2[TECHNOLOGY SPECIFIC PARAMETERS FOR SMALL HYDRO PROJECTS
HAVING INSTALLED CAPACITY OF MORE THAN 100 kW]
(APPLICABLE FROM 01-04-2020 TO 30-09-2023)
33-B. Categorisation.—For the purpose of tariff determination,
3
[the small hydro projects
having installed capacity of more than 100 kW] shall be categorized as under:—
i) Above 100 kW to 2 MW capacity
(ii) Above 2 MW but below 5 MW capacity
(iii) 5 MW to 25 MW capacity
34-B. Normative Capital Cost.—(1) In case of small hydro projects, the normative capital
cost, inclusive of all its components as specified in regulation 21-B of these Regulations, for
the control period shall be as under:—
Sl.No. Category of small hydro Project Rupees (in Lac) per MW of
the installed capacity
(i) Above 100 kW to 2 MW capacity 1100
(ii) Above 2 MW but below 5 MW capacity 1100
(iii) 5 MW to 25 MW capacity 1100
(2) The subsidy/grant/budgetary support or incentives etc. provided by the
Central/State Government or their agencies shall be adjusted in accordance with the
regulation 22-B of these Regulations.
35-B. Normative saleable energy.—(1) The normative saleable energy at the
interconnection point for the purpose of generic levellised tariff shall be computed on the
following lines namely:—
(i) the normative annual capacity utilisation factor (CUF), net of 13% free power
[including 1% contribution towards the Local Area Development Fund (LADF)],
shall be 47.85% for all the small hydro projects upto 25 MW. The number of hours
in a year for calculations of CUF shall be 8766;
1 Ins. regulations “33-B to 39-BB of “PART-III TECHNOLOGY SPECIFIC PARAMETERS FOR SMALL
HYDRO PROJECTS (APPLICABLE FROM 01-04-2020 TO 30-09-2023) ” vide not. No. HPERC/428 dated 8
th
September,
2020, published in R.H.P. dated 15
th
September, 2020 at p. 3561-3570.
2
Sub. the word and figure “TECHNOLOGY SPECIFIC PARAMETERS FOR SMALL HYDRO
PROJECTS” for vide not. No. HPERC/428 dated 20th November, 2020, published in R.H.P. dated 24th November, 2020
at p. 5421-5423.
3 Sub. the words and figure “the small hydro projects” for vide not. No. HPERC/428 dated 20th
November, 2020, published in R.H.P. dated 24th November, 2020 at p. 5421-5423.
Compendium of HPERC Regulations, March 2021 53
(ii) the quantum of normative annual saleable energy worked out for the installed
capacity of the project at the normative CUF under preceding clause (i) shall be
reduced by 1.7%, to account for the auxiliary consumption, transformation losses and
the losses in the project line(s) at the normative rates as per regulations 37-B and 38-
B, to arrive at the normative saleable energy at the interconnection point;
(iii) the generic levellised tariff determined on the basis of the normative saleable energy
at the interconnection point as per the preceding clause (ii) shall be deemed to have
accounted for total free power of 13% [including 1% contribution towards the Local
Area Development Fund (LADF)]:
Provided that in case where the generic levellised tariff is to be determined
for a free power structure which is at variance from the above, the net saleable
energy shall be adjusted suitably after taking into account the free power structure
corresponding to which such tariff is to be determined.
(2) The normative capacity utilization factor (CUF) under clause (i) of sub-
regulation (1) takes into account the impact of mandatory release of water discharge
immediately downstream of diversion structure of the project based on the existing
instructions of the State Government which provide that for the purpose of determination of
minimum discharge, the threshold value not less than 15% of the minimum inflow observed
in the lean season shall be considered.
(3) The normative year wise net saleable energy for the purpose of project specific
tariff determination shall also be worked out on similar lines given in sub-regulations (1) and
(2) but by taking into account the annual Capacity Utilisation Factor (CUF) in accordance
with clause (ii) of sub- regulation (1) of regulation 15, the normative auxiliary consumption
and transformation losses under regulation 37-B and the energy losses in the project line
under regulation 38-B.
36-B. Free Power.—(1) The Commission shall consider appropriate structure(s) of free
power for determination of generic levellised tariffs for various categories of small hydro
projects, as mentioned in regulation 33-B, duly keeping in view of the provisions of the State
Hydro Policy for allotment of sites for small hydro projects, National Hydro Policy, Tariff
Policy and the limits specified under sub-regulation(3):
Provided that in case the structure of free power actually applicable to a project, duly
curtailed as per sub-regulation (3), is at variance from the structure considered while
determining the generic levellised tariff, such tariff shall be suitably adjusted based on the
structure of free power applicable subject to the limit specified in sub-regulation(3):
Provided further that in cases requiring determination of the project specific tariff,
the Commission shall consider the structure of free power actually applicable to that project
subject to the above and the limits specified in sub-regulation(3).
(2) In case of any change in the structure of free power for a small hydro project
from that considered for the determination of generic levellised tariff or project specific
levellised tariff in accordance with sub-regulation (1) or in cases where the adjustment in
tariff on account of variation in free power has to be allowed as per the specific provisions
contained in these Regulations, including those covered in regulation 17 and sub-regulation
(2) of regulation 20, the
54 Compendium of HPERC Regulations, March 2021
distribution licensee shall adjust the tariff as per the following formula:—
Rate payable for the month for the
net saleable Energy (Rs/kWh)
= a x (100-b)/(100-c)
Where,-
“a” is the levellised tariff (in Rs/kWh) which is required to be adjusted under this regulation
“b” is the free power (in percentage) taken into account or deemed as taken into account for
the month, in “a” in the corresponding month of the tariff period by reckoning the date of
commencement of operation of the project as the starting date of the tariff period.
“c” is the free power (in percentage) to be allowed in the tariff for the month subject to
maximum limit of 13% free power(energy) and the provisions of sub- regulation (3)-
Where free power is applicable at different rates for different parts of a month, the
permissible free power (i.e. “c”) shall be determined under this sub-regulation separately for
each such part and weighted average rate for the month as a whole shall be worked out by
considering the total quantum of energy for each day of the month.
(3) The free power (in percentage) to be taken into consideration for the purpose of
determination of tariff under sub-regulation (1) and/or any adjustment under sub-regulation
(2) shall be subject to the following:—
(i) The free energy to be taken into account for any part of the tariff period for
the purposes of sub-regulation (1), or to be allowed for any part of the tariff
period for the purposes of sub-regulation (2), shall not exceed 13% free
power (energy) which includes 12% free power to home State and 1%
additional free power for Local Area Development Fund, as stipulated in the
National Hydro Policy/ Tariff Policy;
(ii) Any quantum of free energy, if committed by the renewable energy generator
over and above the 13% free power (energy) for any period shall not be
factored into the tariff;
(iii) Additional free energy, if any, to be provided by the renewable energy
generator to the State Government, on account of curtailment of waiver
period due to delay in commissioning of project as per provisions of
Implementation Agreement and/or for enhancement of capacity and/or for
any reason attributed to the renewable energy generator shall not be taken
into account even if the total free power for any period, including such
additional free power, does not exceed 13% free power(energy);
(iv) The quantification and adjustment of free energy as well the energy
accounting shall be made with reference to the energy projected/ received at
the interconnection point;
Compendium of HPERC Regulations, March 2021 55
(v) The free energy to be allowed for any period for the purpose of sub-
regulation (2) shall in no case be more than that actually deducted for that
period in the energy accounts, out of the total energy received at the
interconnection point.
37-B. Auxiliary consumption and transformation losses.—Normative auxiliary
consumption and transformation losses for the small hydro projects shall be 0.5% of the
gross generation and the same for transformation losses at the switchyard linked to the
generating station of the projects shall also be 0.5%:
Provided that for the sake of simplicity, these two factors shall be clubbed together
and accounted for as 1% of the gross generation.
38-B. Energy losses.—(1) The normative energy losses in the project line(s) shall be 0.7%
of the gross generation.
(2) For the project specific levellised tariff, the percentage losses worked out on the
basis of actual length of the project line(s), conductor size and expected power flow shall be
taken into consideration.
No.
Installed capacity of SHP Annual O&M expenses in Rupees (in
Lac) per MW of installed capacity
(i) Above 100 kW to 2 MW capacity 41.78
(ii) Above 2 MW but below 5 MW
capacity
41.78
(iii) 5 MW to 25 MW capacity 31.34
39-BB. Adjustment for fraction of a MW of the installed capacity.—The installed
capacity shall be rounded to one decimal place by ignoring the fraction of less than 0.05
MW and by considering the fraction of 0.05 MW and above as 0.1 MW.]
1
[39-BBB. The norms specified under this chapter shall be applicable only for small hydro
projects having installed capacity of more than 100 kW and the same for the small hydro
projects with installed capacity upto 100 kW shall be fixed in the relevant orders issued
under Regulations 14 of these Regulations.]
1
Ins. Regulation 39-BBB vide not. No. HPERC/428 dated 20
th
November, 2020, published in R.H.P. dated
24
th
November, 2020 at p. 5421-5423.
56 Compendium of HPERC Regulations, March 2021
CHAPTER-VI
OTHER PARAMETERS
Previous and next
Questions people ask
Is regulation 39 of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017 is recorded.