Regulation 29, Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017: Supply and installation of meters and circuit breakers
Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 - Regulation 29
Text of regulation 29
Supply and installation of meters and circuit breakers
29. Supply and installation of meters and circuit breakers:-
(1) Check meters and stand-by meters shall be installed wherever necessary in accordance with the provisions
in the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, as amended
from time to time.
(2) The consumer shall provide a lockable and weather proof compartment or enclosure of a design approved
by the Licensee to house the meter and associated equipment including Current Transformer (CT) and
Potential Transformer (PT) etc.
82 DELHI GAZETTE : EXTRAORDINARY PART III]
(3) The consumer shall provide suitable and adequate space for installation of the meter, either at entry point
or outside the premises, in such a manner that it is always accessible to the Licensee or his representatives
without the need of meter reader to get the premises unlocked or opened for this purpose.
(4) In the case of multi-storey buildings, the meters shall be fixed on the ground floor having proper
ventilation and adequate illumination.
(5) The point of supply and the location for installation of meter and other associated equipment shall be
decided in consultation with the consumer so that such locations are easily accessible for their installation,
commissioning, inspection, reading, recording and maintenance, with minimal inconvenience or
infringement upon privacy to the owner or occupier of the premises or to his business.
(6) All HT and EHT consumers shall provide independent entry to the meter or metering cubicle.
(7) The height of meter display and location for permanent connection shall be as per the standards notified
by the ‘Bureau of Indian Standards (BIS) for testing, evaluation, installation and maintenance of A.C.
electricity meters – Code of practice’.
(8) The Licensee shall install the meter, within the time specified for release of new connection, in the
presence of the applicant/consumer or his authorized representative after giving advance notice. The
consumer or his representative shall also be entitled to witness the sealing or removing of seals and sign
on the sealing certificate.
(9) At the time of installation of any meter, the Licensee shall record the particulars of the meters in a format
(meter particular sheet) approved by the Commission.
(10) The Licensee shall give, a copy of the meter particular sheet, duly signed by the Licensee and the
consumer or their authorized representatives, and retain one such copy as acknowledgment.
(11) Whenever a new meter is installed, either for a new connection or for replacement, it shall be sealed in the
presence of the consumer or his authorized representative.
(12) The seal, name plates and distinguishing numbers or marks affixed on the said equipment or apparatus
shall not in any way be broken, erased or altered by the consumer or his employee or any person acting on
his behalf.
(13) Treatment of meter seals shall be in accordance with the Central Electricity Authority (Installation and
Operation of Meters) Regulations, 2006, as amended from time to time.
(14) The consumer shall be responsible for safe custody of meter, if the same is installed within the premises
of the consumer.
(15) The consumer shall promptly intimate the Licensee about any fault, accident or abnormality noticed with
the meter.
(16) It shall be the responsibility of the Licensee to maintain the meter and keep it in good working condition
at all times.
(17) In all such cases of permanent connection where the metering unit is installed on any structure such as a
pole or a distribution pillar etc., outside the premises of the consumer, the Licensee shall provide a display
unit at the premises of the consumer and the responsibility of safe custody of the metering unit shall rest
with the Licensee and safe custody of display unit shall rest with the consumer.
Previous and next
Questions people ask
Is regulation 29 of Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 still in force?
No repeal of Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 is recorded.