APPENDIX A-7
APPENDIX A-7
[See rule 21]
JOINT DECLARATION BY THE ARCIIllECT, STRUCTURAL
ENGINEER/ENGINEERANDOWNERFOROBTAINING
COMPLETION CERTIFICATE
( On completion of a building and before occupation the Architect and the
Structural Engineer along with owner will jointly inspect the building and
submit a report of completion of the building to the agency stating that the
work is done as per approved plans and design).
Declaration: The following declaration is to be made at the time of
obtaining Completion Certificate from the agency by the builder/owner or
authorized signatory:-
1. Certified that the building has been constructed according to
the Sanctioned Plan and Structural design ( one set of building
and Structural drawings as executed is enclosed) which
incorporates the provisions of structural safety as specified in
relevant prevailing IS Codes/Standard.
2. It is also certified that the construction has been done under our
supervision and guidance adheres to the drawings submitted
and the records of supervision have been maintained by us.
3. Any subsequent change in the drawings will be responsibility
of the owner.
Signature of Owner/
Builder with date, name
and address
Signature of Architect
with date, name and
address
Signature of Engineer/
Structural Engineer with
date, name and address
Previous and next
All provisions of MP Investment Region Development and Management Rules 2016
Questions people ask
Is appendix A-7 of MP Investment Region Development and Management Rules 2016 still in force?
No repeal of MP Investment Region Development and Management Rules 2016 is recorded.