LawGrids logoLAWGRIDS.ORG

Annexure XI, .lharkhand Building Bye-laws 2016: ANNEXURE-XI

.lharkhand Building Bye-laws 2016 - Annexure XI

Text of annexure XI

ANNEXURE-XI

ANNEXURE-XI Checklist of Occupancy between 3. All materials are of specified brand and grade B. During Concreting I. Mixing of concrete has been done as spcci ficd 2.Slump and other tests carried out as specified 3.Slump and other tests carried out as specified 4. Required number of Samples have been taken for carrying out slump tests, cube tests etc C. Post Concretinz I Concreting has been done as per speci fled line and level 2 Curing has been done as specified 3 Compaction has been done Properly 4 Remedial measures taken for removal of defects 3) ANTI TERMITE TREATMENT (ATT) 1 Chemicals for ATT are as per Specifications 2 Chemicals in use are within the expiry date. 3 Sufficient quantities of chemicals are available at site for A TT. 4 Safety precautions have been taken for carrying out ATT and storage of Chemicals 5 Record of consumption maintained at site 4) BACKFILLING I. Filling material/ earth is as ncr soccification 2 Anti-termite treatment has been carried out before commencement of backfilling 3 Filling has been done in layers of 300 mm, watered and compacted as oer soecitications 4 Proper compaction method has been adopted 5 Filling has been done to the required levels 5) REINFORCED CEMENT CONCRETE WORKS A. Pre-concreting I All specified materials available at site 2 Cement is of the required grade and not more than three months old. 3 Shuttering checked for Staging & Propping , line & level, dimensions cleaning etc and its oualitv approved 4 Application of oil & grease carried out 5 Mixer/Vibrator as specified available at site with adequate means to run them during concreting 6 Cut-out & Sleeves/Inserted 7 Surface of reinforcement is clean and free from rust 8 Bars have been provided as per structural drawings 9 Lap length & dowels provided as ner coda! provisions 10 Pin bars & chairs/cover blocks provided as per requirements I I Tying of bars has been done Correctly 12 Service lines(Electrical, Plumbing, Others) if any, provided before commencement of concrete B. General Arrnnzement I. Availability/ Arrangement of pumps etc, proper access & walkway checked '") ~ - 142 - yl'/_;J.() 2 Adequacy of vibrators/ needle including diesel vibrator 3 Slump cone & test cubes made 4 Safety and health measure taken before commencement C. Durinz Cuncrcrlnz 1 All necessary precaution taken I before commencement of concreting 2 Samples of taken for slump, cube tests etc for each batch 3 Proper Compaction done and checks on Staging & Scaffolding carried out 4 Covering of green concrete carried out 5 Surface finish checked 6 Construction joints provided 0. Post Concreting I De-shuttering started on Vertical faces I Other faces carried out as per coda! provisions 2 Proper curing of concrete carried Out 3 Lme& Level of surface checked for correctness 4 Defects, notified and removed 5 Cube and other test results will be intimated to the engineer in charge for further action 6) MASONRY, MORTAR AND PLASTER A. Pre-Masonry Work I Availability of material as per daily requirement checked 2 Quality check for bricks/ blocks/sand/ cement carried out 3 Provisions kept for electrical and other services B.During masonry work I Checking for line/ level/ right angle carried out 2 Mortar checked for mix proportion 3 Proper raking of joints 4 Seismic bands provided as per zonal requirements C. Post masonry Check cleaning of dead mortar and broken bricks/ blocks etc. 2 Curing carried out as per requirements 0. Plastering/Pointing I Mortar for plastering as specified for each side of wall 2 Quality of cement and sand checked 3 Curing work done as per requirement 4 Preparation of surface E. During Plnstcrtna I Mortar mixing in tray 2 Addition of water proofing compound 3 Proper roughing of first coat 4 Check for collection of mortar Spills 5 Cleaning of dead mortar 6 Check of waviness 7 Check for grooves/ drip moulds "' ~ - 143 - //lr?!!-t) - 144 - 8 Application of cement slurry on concrete surface F. After Plastering I Curing 2 Check for hollowness 3 Check for cracks 4 Check for diagonal 5 Lime wash after 3 days (withins days in case of neeru application) 6 Safety and health measures 7) WATER PROOFING I Surface for waterproofing has been prepared and cleaned 2 Safety measures/ precautions taken before commencement of works 3 Specified type of water proofing Used 4 Specified material used for waterproofing 5 The material used was as per specification 6 Work has been carried out as per specifications by the department/ specialized agency 8) JPS/TILE fLOORING AND DADO I Layout of floor checked and proper slopes for draining water are maintamed specially in bath room and toilet. 2 Thickness bases at GL checked of different floor 3 Check for proper back filling under floor done 4 Metal/glass strips laid properly in IPS flooring 5 Curing of IPS Flooring done as per requirements 6 Dado provided as per required height I 7 Cleaning and finishing done 9) PLlJMBING & WATER SUPPLY I GI/Cl/1-IDPE pipes etc. confirms to relevant IS codes 2 Pipes of required diameter and their fittings used 3 Plumbing and Water Supply work earned out through a licensed plumber 4 Works clone as per specification - 145 - 5 Plumbing and Water Supply works tested on completion - 6 Defects rec ti ficd 10) INTERNAL ELECTRICAL WORKS A.GENERAL I Layout plans: howing the po ition of L.T Panels/ distribution board, lighting fixture , lighting distribution, cheme, receptacles, etc available before commencement of work 2 All the following items are as per specification and or approved makes LT Panels/ Distribution Board Lighting Fixtures onduits, including accessorie Receptacles Junction Boxes Cables/Wire Anv other item 8. SURFACE CONDUIT WIRING I CONCEALED CONDUIT WIRING I Conduit and accessories are of specified make, gauge and diameter 2 Proper installation of all conduit wiring and concealed wiring. C. CHECK LIST FOR EARTHING I Earth electrode provided as specified. B. SURFACE CONDUIT WIRING I CONCEALED CONDUIT WIRING I Conduit and accessories are of pecified make, gauge and diameter 2 Proper installation of all conduit wiring and concealed wiring. C. CHECK LIST FOR EARTHING I Earth electrode provided a specified B. SURFACE CONDUIT WIRING I CONCEALED CONDUIT WIRJNG l Conduit and accessories are of specified make, gauge and diameter 2 Proper instnllntion of all conduit wiring and concealed wiring. C. CHECK LIST FOR EARTHING I Earth electrode provided as specified. CHECK LIST FOR EXTERNAL ELECTRICAL WORKS A. CHECK LIST FOR O.H. LINES I Poles used arc of approved make as specified and conform to relevant BIS codes 2 Test certificate as applicable. 3 Pole embedded below ground level as specified. 4 Metallic poles are adequately earthed with specified size of earth conductor. ·' r - 146 - 5 Strays struts, insulators, conductors used conform to relevant BIS Code., 6 Earth wire conductor used as specified 7 Lightning arrestors used as specified B. CABLE LA YING l Trenches of specified dimensions excavated and prepared 2 Required quantity of sand cushioning provided; cable laid; another layer of sand and brick protective covering provided. Refilling done earth ramming and dressing done 3 Cables entry point in building or crossing roads path protected by providing Hume pipes or PVC pipe 4 Cable tested before and after laying and before emerging C. CHECK LIST FOR EARTHING I Earth electrode provided as specified 2 Types and size of main/ sub main and circuit earthing conductors provided as specified. 11) DRAINAGE WORKS I Excavation for drains carried out as per the approved lay-out 2 Bed Concrete laid as per specifications with proper slopes and cuttings 3 All pipes procured and laid as per requirement 4 Jointing of pipes done as per specifications 5 Manholes provided as per design 6 Materials for construction of manhole as specified 7 End of the pipes plugged 8 Drainage line tested before nutting to use 13) OTHERS I Whether the provision for adequate ventilation and natural lighting has been made as per National Building code? 2 Whether facility for storage in terms of Almirah/ Shelves I Lofts I Platform has been made ? 3 Whether Sanitary fittings have been provided? - ') ~~ r71~0 -147- Area Development Authority, Gram Panchayat areas covered under Development Plan or Planning 1 ~ o \ 'I, ff' -£')_.__-/ ~ ~ I/We hereby apply for permission to undertake development of land in respect of plot No.(CS) Plot No(MSP) Village/Mauza Khata o .. under Municipal Corporation/Municipal Council/Nagar Panchayat/Municipality/Notified Area Committee/ Regional Development Authorities/Industrial Area Development Authorities/Mineral Madam/Sir, To Email id .. Tel o/ Mobile No . Signature of Authorised Person Date .. (in Block letters) Regd o . 1 ame and address for office use only From APPLICATION FOR DEVELOPMENT /RE-DEVELOPMENT OF LAND FOR OBTAINNG DEVELOPMENT PERMIT Application No .. APPICATION FOR LAND DEVELOPMENT

Previous and next

All provisions of .lharkhand Building Bye-laws 2016

Questions people ask

Is annexure XI of .lharkhand Building Bye-laws 2016 still in force?

No repeal of .lharkhand Building Bye-laws 2016 is recorded.