Form AT FOR FEASIBILITY STUDY REPORT, TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARD REGULATIONS 2013: FORMAT FOR FEASIBILITY STUDY REPORT
TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARD REGULATIONS 2013 - Form AT FOR FEASIBILITY STUDY REPORT
Text of form AT FOR FEASIBILITY STUDY REPORT
FORMAT FOR FEASIBILITY STUDY REPORT
FORMAT FOR FEASIBILITY STUDY REPORT
(see regulation 8)
1. Executive Summary
Part A: Feasibility Assessment
2. Project background
3. Strategic needs assessment, demand
assessment and project scoping
4. Service standard — output and services
5. Market assessment
6. Technical feasibility
7. Financial feasibility including IRR and ERR
8. Environment impact
9. Legal framework
10. Stakeholder consultation findings and public
interest evaluation
11. Public sector comparator, value for money
assessment and recommendations
12. Conclusion and recommendations on feasibility
assessment
Part B: Structuring
13. Risk assessment
14. Key commercial principles and payment
mechanisms
15. Evaluation criteria for selection of the private
entity (preliminary indication)
16. Implementation plan(preliminary indication)
17. Project resource requirement
18. Conclusion and recommendations on
structuring
Appendixes
(other supporting documents)
The content of the Feasibility Study report is
discussed in detail below
1. Executive summary:
This summary should provide of the following
information —
(a) Current service provision, if applicable and
future requirements;
17
(b) A summary of the full list of options;
(c) A summary of the options selection
procedure and the options chosen for
detailed examination;
(d) A summary of the comparative findings
and justification for the preferred
option; and
(e) Highlights of the implementation plan.
Part A: Feasibility Assessment
2. Project Background:
This section should provide a background
on the project location, type of
infrastructure, the Contracting Authority,
previous studies undertaken, and previous
approvals received etc.
3. Strategic Needs Assessment, Demand Assessment and Project Scoping:
This section will analyse current and future
needs. An analysis of the user's needs
should be included. The following issues
should be addressed:
(a) Existing or envisioned service gaps;
(b) Key stakeholders and their requirements;
and
(c) Consultation plan with key stakeholders to
ensure that the Project remains relevant.
Assessment of demand should also be
included in this section. Project scoping
Component should determine and define the
scope of the Project, outlining the services to
be delivered.
4. Service Standard — Output and Services:
This section will translate the needs
identified in the previous step into specific
outputs. The following issues should be
addressed:
(a) Impact of the proposed Project on the
service gaps identified above and overall
objectives the Project aims to achieve;
(b) Outputs expected from the Project, stated
in measurable and quantifiable terms as
far as possible;
(c) Support service outputs (the outputs
that are not the key drivers of the
Projects, but have potential to enhance
the Project's value for money); and
18
(d) Relevance of the Project to the
Contracting Authority's long-term
strategic goals and overall national
development plan.
5. Market Assessment:
Once the project outputs have been specified,
assessment of the market potential can
commence. The purpose of market
assessment study is to assist the Contracting
Authority in deciding how to design, and
deliver the Public-Private Partnership Project.
The study may address the following elements:
(a) Description of the industry;
(b) Current market analysis (current offerings,
market players and their capability and
appetite);
(c) Competition (alternative service and product
offerings);
(d) Anticipated future market potential;
(e) Potential market players and sources of
revenues; and
(f) Demand projections.
6. Technical Feasibility:
This component details how the Project can be
delivered (i.e., outline technical solution). The
study should address the following elements:
(a) Field surveys of the project site, which may
include (depending on the Project)
mapping, topographical and geotechnical
surveys;
(b) A preliminary technical design of facilities
required to provide the project outputs.
This should consider alternative design
options, taking into account uncertainty in
the demand projections and other site-
related uncertainties;
(c) Materials and other inputs requirements;
(d) Alternatives (such as those involving usage
of existing assets for the Project, rather
than creating new ones; or achieving the
desired outputs by some means other than
the proposed solution) and their
assessment in relation to the possibility of
achieving the targets of the Project; and
(e) Capital expenditure cost assessment and
operating and maintenance cost
assessment based on the components of the
19
preliminary technical design.
7. Financial Feasibility:
This component provides an estimate of
project costs based on recommended
technical solution and identifies possible
financing solutions. The study should address
the following elements:
(a) Project costs (initial and replacement capex,
cost of upgrades, opex);
(b) Start-up capital:
(c) Sources of financing;
(d) Potential revenues;
(e) Estimated returns; and
(f) Consulting costs.
8. Environment Impact:
This section should examine environmental
considerations, including details of any
environment impact study conducted.
9. Legal Framework:
This component examines the suitability of
existing legislative environment for the
execution and running of the Project, as well as
any licences or requirements that potential
service providers need to comply with. The
study should address the following elements:
(a) Appraisal of current legislative environment
in relation to requirements of the Project;
(b) Assessment of required amendments to the
current legislation;
(c) Legal requirements for the proposed market
and organisational structure; and
(d) Other legal issues that may inhibit /
prevent the development of the Project.
10. Stakeholder consultation findings and public interest evaluation:
This component should state the findings of the
consultation process with the various
stakeholders including but not limited to:
(a) Users;
(b) Developers;
(c) Community participants;
(d) Citizens likely to be affected;
(e) Financers; and
20
(f) Other relevant Government authorities.
11. The Public Sector Comparator (PSC), Value for Money and recommendations:
This section should state the reference project
and detail the computation of the Public Sector
Comparator and resultant Value for Money for
the Public Agency.
12. Conclusion and Recommendations on Feasibility Assessment:
This component should detail the key
conclusions and recommendations on the
Feasibility Assessment.
Part B: Structuring:
13. Risk Assessment:
This section should identify all material
risks associated with the Project,
specifying the external and project
development risks for the Contracting
Authority, the project risks to be allocated to
the private entity in the case of Public-Private
Partnership s and those to be retained by the
Contracting Authority.
14. Key Commercial Principles including Payment Mechanisms:
This section should detail the key
commercial principles for the Project. These
commercial principles would include
among other principles, the payment
mechanisms, relief, compensation and
force majeure events, default events,
termination payments, the Contracting
Authoirty's step-in, cure rights, insurance
etc.
15. Evaluation Criteria for selection of the private entity:
This section should explain the options
regarding the evaluation criteria for selection
of the private entity. This would be
preliminary and subject to finalization of the
RFP.
16. Implementation Plan:
This section should detail the activities and
timelines during the Project development
period. It should also state the person or
entity responsible for each activity.
21
17. Project Resource Requirement:
This section should detail the resources
required during and after the Project
development period.
18. Conclusion and Recommendations on Structuring
This section should detail the key
conclusions and recommendations on the
project structuring.
Appendixes (other supporting documents)
Any supporting documents should be
included in the section like detailed
projected financial statements, detailed
environment impact assessment study,
detailed technical report, detailed review of
legal framework, etc.
***
22
Previous and next
All provisions of TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARD REGULATIONS 2013
Questions people ask
Is form AT FOR FEASIBILITY STUDY REPORT of TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARD REGULATIONS 2013 still in force?
No repeal of TAMIL NADU INFRASTRUCTURE DEVELOPMENT BOARD REGULATIONS 2013 is recorded.