Regulation 18, The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012: Differential Costs
The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 - Regulation 18
Text of regulation 18
Differential Costs
18. Differential Costs.- (1) The distribution licensee shall recover the expenses
and/or charges for giving electricity connections to the applicants as per the provisions of
these Regulations and any other additional expenses, as are not recoverable from the
applicants under any Regulations or Law, shall be met out of the approved financial
provisions of the capital expenditure plan.
(2) In cases where the cost of certain works is to be recovered from the applicant or
group of applicants initially on the basis of estimate and such recovery is subject to
adjustment as per actual as per the provisions of these regulations, the following provisions
shall apply:-
(a) the estimate shall be prepared on the basis of the standard cost data as per
sub regulation (2) of Regulation 13; and
the licensee shall, within ninety days of commissioning of the works, render to the
applicant/consumer, the account of expenditure showing the excess or deficit in relation to
the initial estimated amount giving details of item wise estimation and actual expenditure
alongwith the item wise figures of variance to the extent possible and if applicant requires
any additional information, the distribution licensee shall furnish the same within ten days
of receipt of such requisition.
Compendium of HPERC Regulations, March 2021 17
(3) The distribution licensee shall recover or refund, as the case may be, the difference
between the actual expenditure and the estimated cost within 60 days from the submission
of account and the unrefunded or unrecovered amounts, as the case may be, shall attract
simple interest @ 12% per annum for the period beyond the said limit of 60 days.
Previous and next
Questions people ask
Is regulation 18 of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 is recorded.