Regulation 17, The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012: Execution of works
The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 - Regulation 17
Text of regulation 17
Execution of works
17. Execution of works.- The service lines and other works required for supplying
power to the applicant(s) shall normally be executed by the distribution licensee:
Provided that the applicant or the consumer, as the case may be, may, with the prior
approval of the distribution licensee which shall ordinarily not be refused, execute the
service line through an electrical contractor licensed by the Electrical Inspector, and in
such cases, the following provisions shall apply-
(i) all the requisite clearances under various laws shall be obtained by the
applicant;
(ii) the applicant shall be liable to pay the departmental charges @ 6.25% of the
estimated cost for the specific works or of the corresponding amount worked
out by accounting for the average/normative rates, if approved by the
Commission under regulation 4, whichever is higher;
(iii) such option shall be available to the applicant only for the service line to be
executed exclusively for the applicant; and
(iv) works other than service line shall be executed by the distribution licensee
unless mutually agreed otherwise by the distribution licensee with the applicant,
on mutually agreed terms and conditions.
Note: The provisions under the first proviso to this regulation shall also apply for
execution of service lines to be executed exclusively for a group of applicants
or consumers, as the case may be, if all the members of such group enter into an
agreement amongst themselves and nominate their representative who shall
then deal with the distribution licensee for such matters.
Previous and next
Questions people ask
Is regulation 17 of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 is recorded.