Regulation 9, The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012: Withdrawal of application before release of connection
The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 - Regulation 9
Text of regulation 9
Withdrawal of application before release of connection
9. Withdrawal of application before release of connection.- In case of withdrawal,
or deemed withdrawal, of an application by the applicant for supply of power before actual
release of connection, the expenses actually incurred for the works for providing supply
under regulations 4, 5, 6 and 7 for permanent supply and under regulation 8 for temporary
supply, shall be adjusted as per the provisions of the Supply Code:
Provided that for the purpose of such adjustment, actual expenditure for the works
under regulations 4, 5, 6 and 7 for permanent supply and under regulation 8 for temporary
supply shall be computed as under :-
(i) the actual expenditure (including departmental charges) incurred on the service
lines and other works under regulation 4 shall be considered in addition to the
expenses determined as per the succeeding clauses of this proviso;
(ii) in cases involving works under sub-regulation (3) of regulation 5, the actual
expenditure (including departmental charges) of such works or 10% of the
infrastructural development charges at the normative rates under sub-
regulation(2) of regulation 5, whichever of the two is higher, shall be
considered in addition to the expenditure mentioned in the preceding clause (i)
of this proviso;
Compendium of HPERC Regulations, March 2021 11
(iii) in cases where the works under sub-regulation (3) of regulation 5 are not
involved, an amount equal to 10% of the amount of infrastructural development
charges worked out at the rates fixed by the Commission pursuant to sub-
regulation (2) of regulation 5 shall also be considered as the actual expenses in
addition to the expenditure mentioned in clause (i) of this proviso;
(iv) in cases involving exclusive work(s) for faciliting supply of power as per the
fifth proviso to sub-regulation (2) of the regulation 5, the actual expenditure on
such exclusive works shall also be considered in addition to preceding clauses
(i), (ii) and (iii) of this proviso;
(v) in cases of applications for additional connected loads or contract demands
under regulation 7 of these Regulations, the computations and adjustments shall
be done separately for the respective works falling under regulation 4 and
regulation 5 or regulation 6, based on the demand notice issued pursuant to the
provisions of regulation 7; and
(vi) in case of temporary supplies, including for additional connected loads/ contract
demands for temporary supplies, under regulation 8, the actual expenditure on
the works required to be executed for giving such supply or additional connected
loads/contract demands shall be considered.
Previous and next
Questions people ask
Is regulation 9 of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012 is recorded.