Regulation 11, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011: Operational Norms
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 - Regulation 11
Text of regulation 11
Operational Norms
11. Operational Norms.-Normative Annual Transmission System Availability
Factor (NATAF): The target availability for recovery of full transmission charges during
the control period shall be as under: -
(a) the alternating current (AC) System: 98%
(b) the high voltage direct current (HVDC) bi-pole links: 92%
(c) the high voltage direct current (HVDC) back-to-back stations: 95%.
PART-III
PRINCIPLES FOR DETERMINATION OF
AGGREGATE REVENUE REQUIREMENT (ARR)
Previous and next
Questions people ask
Is regulation 11 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 is recorded.