Regulation 27, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011: Unscheduled Interchange (UI) Charges
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 - Regulation 27
Text of regulation 27
Unscheduled Interchange (UI) Charges
27. Unscheduled Interchange (UI) Charges .- The generating station may be entitled
to receive or shall be required to bear, as the case may be, the charges for deviations
between energy sent-out corresponding to scheduled generation and actual energy sent-out
shall be accounted for through Unscheduled Interchange (UI) charges, as per the rate
approved by the Appropriate Commission.
Previous and next
Questions people ask
Is regulation 27 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 is recorded.