Regulation 23, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011: Operational Norms
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 - Regulation 23
Text of regulation 23
Operational Norms
23. Operational Norms .– (1) The norms of operation for hydro generating stations
shall be as under-
(a) Normative Annual Plant Availability Factor (NAPAF) for hydro
generating stations shall be determined by the Commission as per the
following criteria:-
(i) storage and pondage type plants with head variation between Full Reservoir
Level (FRL) and Minimum Draw Down Level (MDDL) of up to 8%, and
where plant availability is not affected by silt : 90%
(ii) storage and pondage type plants with head variation between FRL and
MDDL of more than 8%, where plant availability is not affected by silt:
Plant-specific allowance to be provided in NAPAF for reduction in MW
output capability as reservoir level falls over the months. As a general
guideline the allowance on this account in terms of a multiplying factor may
be worked out from the projection of annual average of net head, applying
the formula:
(Average head / Rated head) + 0.02
Alternatively in case of a difficulty in making such projection, the multiplying
factor may be determined as:
(Head at MDDL/Rated head) x 0.5 + 0.52
(iii) pondage type plants where plant availability is significantly affected by silt
: 85%
(iv) run-of-river type plants: NAPAF to be determined plant-wise, based on 10-
day design energy data, moderated by past experience where
available/relevant;
(b) Auxiliary Energy Consumption:
Surface hydro electric
power generating
station
With rotating exciters mounted on
the generator shaft
0.7%
With static excitation system 1%
1
Add. vide Not. No. HPERC-F(1)-2/2018 dated 22
nd
November, 2018 published in the R.H.P. 27
th
November, 2018 at p. 6249-6255.
22 Compendium of HPERC Regulations, March 2021
Underground hydro
electric power
generating station
With rotating exciters mounted on
the generator shaft
0.9%
With static excitation system 1.2%
Provided that the Commission, may for sufficient reasons to be recorded in writing,
after exercising due diligence and applying prudency check, deviate from the above ceiling
norm.
(2) A further allowance may be made by the Commission in NAPAF determination
under special circumstances, e.g. abnormal silt problem or other operating conditions, and
known plant limitations.
(3) In case of a new hydro electric project the developer shall have the option of
approaching the Commission in advance for fixation of NAPAF based on the principles
enumerated in clause (a) of sub-regulation of this regulation.
(4) The Commission may lay down relaxed operational norms including the norms
of NAPAF and auxiliary consumption contained in these regulations for a generating
station, and these relaxed norms shall be applicable for determination of tariff for such
generating station during the control period.
(5) The norms of operation under these regulations shall be ceiling norms and shall
not preclude generating companies and the beneficiaries from agreeing to improve norms
of the operation. If the PPA stipulates better norms of operation then such norms provided
in the PPA shall be considered.
(6) In case of renovation and modernisation, de-rating or re-rating of the generating
station, norms of operation shall be reviewed and modified accordingly.
Previous and next
Questions people ask
Is regulation 23 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 is recorded.