Regulation 19, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011: Interest on Working Capital
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 - Regulation 19
Text of regulation 19
Interest on Working Capital
[19. Interest on Working Capital.—Rate of interest on working capital to be
computed as provided hereinafter in these regulations shall be on normative basis and shall
be equal one (1) Year State Bank of India (SBI) MCLR / any replacement thereof as
notified by RBI for the time being in effect applicable for one (1) Year period, as may be
applicable as on 1
st
April of the Financial Year in which the Petition is filed plus 300 basis
points. The interest on working capital shall be payable on normative basis
notwithstanding that the generating company has not taken working capital loan from any
outside agency or has exceeded the working capital loan based on the normative figures.]
1 Sub. vide Not. No. HPERC-F(1)-2/2018 dated 22
nd
November, 2018 published in the R.H.P.
27
th
November, 2018 at p. 6249-6255. Before its substitution it read as under:
“(5) The generating station shall make every effort to refinance the loan as long as it results in net benefit to the
beneficiaries. The costs associated with such refinancing shall be borne by the beneficiaries and any benefit on account of
refinancing of loan and interest on loan shall be passed on to the beneficiaries. Refinancing may also include restructuring of
debt.”
2
Sub. vide Not. No. HPERC-F(1)-2/2018 dated 22
nd
November, 2018 published in the R.H.P. 27
th
November, 2018 at p. 6249-6255. Before its substitution it read as under:
“19. Interest on Working Capital .- Rate of interest on working capital shall be on normative basis and shall be equal to
the 2[average Base Rate of State Bank of India for the last six months prior to the filing of the MYT petition plus
350 basis points]. The interest on working capital shall be payable on normative basis notwithstanding that the
generating station has not taken working capital loan from any outside agency or has exceeded the working capital loan
based on the normative figures.”
Compendium of HPERC Regulations, March 2021 17
Previous and next
Questions people ask
Is regulation 19 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 is recorded.