18. Working Capital.- The Commission shall calculate the working capital
requirement for hydro electric power stations containing the following components: -
(a) Operation & Maintenance (O&M) expenses for 1 month;
(b) maintenance spares equivalent to 15% of O&M specified in regulations;
(c) receivables equivalent to two months of fixed cost.
2
Previous and next
Questions people ask
Is regulation 18 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 is recorded.