Regulation 13, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011: Additional Capitalisation
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 - Regulation 13
Text of regulation 13
Additional Capitalisation
13. Additional Capitalisation .- (1) The capital expenditure incurred or projected to
be incurred, on the following counts within the original scope of work, after the date of
commercial operation and up to the cut-off date, may be admitted by the Commission,
subject to prudence check,:-
(a) Un-discharged liabilities;
(b) Works deferred for execution;
(c) Procurement of initial capital spares within the original scope of work, subject
to the provisions of regulation;
(d) Liabilities to meet award of arbitration or for compliance of the order or decree
of a court; and
(e) Change in law:
Provided that the details of works included in the original scope of work, along
with estimates of expenditure, un-discharged liabilities and the works deferred for
execution, shall be submitted along with the application for determination of tariff.
1
Subs. for “01.04.2011” vide Not No. HPERC/F(5)(3)(1) (Gen.) dated 1
st
Nov., 2013 published in
the R H.P. dated 4
th
November, 2013 at p. 4599-4606.
Compendium of HPERC Regulations, March 2021 13
1[(2) The capital expenditure incurred on the following counts after the cutoff date
may, in its discretion, be admitted by the Commission, subject to prudence check:—
(a) liabilities to meet award of arbitration or for compliance of the order or
decree of a court;
(b) change in law;
(c) any expenditure which has become necessary on account of damage caused
by natural calamities (but not due to flooding of power house attributable to
the negligence of the generating company) including due to geological
reasons after adjusting for proceeds from any insurance scheme, and
expenditure incurred due to any additional work which has become
necessary for successful and efficient plant operation:
(d) any expenses to be incurred on account of need for higher security and
safety of the capital asset as advised or directed by appropriate Government
agencies or statutory authorities responsible for national security/internal
security;
(e) any liability for works executed prior to the Cut-off Date, after prudence
check of the details of such undischarged liability, total estimated cost of
package, reasons for such withholding of payment and release of such
payments etc.;
(f) any liability for works admitted by the Commission after the Cut-off Date
to the extent of discharge of such liabilities by actual payments; ‘
(g) any additional capital expenditure, which has become necessary for
efficient operation of the plant. The claim shall be substantiated with the
technical justification duly supported by the documentary evidence like test
results carried out by an independent agency in case of deterioration of
assets, report of an independent agency in case of damage caused by natural
calamities, obsolescence of technology etc.:
Provided that in any expenditure on acquiring the minor items or the assets like
tools and tackles, furniture, air-conditioners, voltage stabilizers, refrigerators, coolers, fans,
washing machines, heat convectors, mattresses, carpets etc. bought after the cut-off date
shall not be considered for additional capitalisation for determination of tariff.]
Previous and next
Questions people ask
Is regulation 13 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 is recorded.