Regulation 12, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011: Initial Spares
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 - Regulation 12
Text of regulation 12
Initial Spares
12. Initial Spares.- For hydro generating stations, initial spares shall be capitalised as a
percentage of the original project cost, subject to the ceiling norm of 1.5%:
Provided that the Commission, may for sufficient reasons to be recorded in writing,
after exercising due diligence and applying prudency check, deviate from the above ceiling
norm.
Previous and next
Questions people ask
Is regulation 12 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 is recorded.