Regulation 17, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011: Operation and Maintenance (O&M) Expenses
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011 - Regulation 17
Text of regulation 17
Operation and Maintenance (O&M) Expenses
17. Operation and Maintenance (O&M) Expenses.- (1) Operation and Maintenance
(O&M) expenses shall include: -
(a) salaries, wages, pension contribution and other employee costs;
(b) administrative and general expenses;
(c) repairs and maintenance expenses; and
(d) other miscellaneous expenses, statutory levies and taxes (except corporate
income tax).
1
[(1-a) O&M Norms -
(i) The licensee shall propose separate trajectories of norms for each of the
components of O&M expenses viz., employee cost, R&M expense and A&G
expense;
(ii) Norms shall be defined in terms of combination of number of personnel for
various activities such as per 1000 consumers and number of personnel per
substation, line length alongwith annual expenses per personnel for Employee
expenses combination of A&G expense per personnel and A&G expense per
1000 consumers for A&G expenses and R&M expense as percentage of gross
fixed assets for estimation of R&M expenses;
1 Ins. vide Not. No. HPERC/F(5)(3)(1)(Retail) dated 1st November, 2013 published in the R. H.P. dated 4th
November, 2013 at p. 4539-4596.
Compendium of HPERC Regulations, March 2021 21
(iii) One-time expenses such as expense due to change in accounting policy,
arrears paid due to pay commissions and interim relief etc., shall be excluded
from the norms in the trajectory;
(iv) The expenses beyond the control of the distribution licensee such as dearness
allowance, pension liabilities and terminal benefits in Employee cost etc.,
shall be excluded from the norms in the trajectory;
(v) The One-time expenses and the expenses beyond the control of the
Distribution Licensee as per sub-regulations (c) and (d) above shall be
allowed by the Commission over and above normative Operation &
Maintenance Expenses after prudence check;
(vi) The norms in the trajectory shall be proposed over the control period with
due consideration to productivity improvements and commercial viability;
(vii) The norms shall be proposed at constant prices of base year and escalation on
account of inflation shall be over and above the baseline;
(viii) The Distribution Licensee shall also carry out absolute and relative analysis
while proposing the norms;
(ix) In absolute analysis, Distribution Licensee’s audited accounts of operations
for last three years, expenses claimed for control period, historically approved
cost, and prudence check shall be used by the Commission to estimate values
of norms;
(x) In relative analysis, performance parameters of other Distribution Licensees
within the same state or in other states shall be considered by the commission
to estimate norms:
Provided that other Distribution Licensees so chosen shall have similar
profile as that of the Distribution Licensee under consideration in terms of
consumer mix, type of license area (city, state, etc.) type of distribution
networks, viz, underground/overhead, HT-LT ratio, etc;
(xi) Suitable average of outcomes of absolute and relative analysis may be taken
by the licensee while proposal the norms over the control period for the
distribution licensee;
(xii) Based on the proposal submitted by the licensee, the Commission shall fix
the norms for the said purposes which shall be taken into account for
determining the trajectories for various components of O&M expenses for the
remaining years of the control period;
(xiii) Till such time the norms are fixed by the Commission, the trajectories of
various components of O&M expenses shall be submitted by the licensee and
determined by the Commission on the basis of the actual costs for the
previous years in accordance with the provisions of these regulations.
(2) The distribution licensee shall submit the O&M expenses for the control period as
laid down in the multiyear tariff filing procedure. The O&M expenses for the base year
shall be approved by the Commission taking into account the latest available audited
accounts, business plan filed by the distribution licensee, estimates of the actuals for the
base year, prudence check and any other factors considered appropriate by the
Commission.
22 Compendium of HPERC Regulations, March 2021
1
[(3) The O&M expenses for the n
th
year of the control period shall be approved based
on the formula given as follows:-
O&Mn = R&Mn + EMPn + A&Gn :
Where -
R&Mn = K x GFA n-1 ;
EMPn = [(EMPn-1) x (1+Gn) x (CPIinflation)] + Provision(Emp) ;
A&Gn = [(A&Gn-1) x (WPIinflation)] + Provision (A&G) ;
‘K’ is a constant (could be expressed in %). Value of K for each year of the control
period shall be determined by the Commission in the MYT Tariff order based on
licensee’s filing, benchmarking of R&M expenses, approved R&M expenses vis-à-
vis GFA approved by the Commission in past and any other factor considered
appropriate by the Commission;
CPIinflation – is the average increase in the Consumer Price Index (CPI) for
immediately preceding three or five years before the base year, whichever is higher;
WPIinflation – is the average increase in the Wholesale Price Index (CPI) for
immediately preceding three or five years before the base year, whichever is higher;
EMPn-1 & EMPn – employee costs of the distribution licensee for the (n-1)
th
and n
th
year; (employee cost for the base year would be adjusted for provisions for (n-1)
th
year for the items corresponding to clauses (iii), (iv) and (v) of sub-regulation (1-a)
of regulation 17);
1
Subs. vide Not. No. HPERC/F(5)(3)(1)(Retail) dated 1
st
November, 2013 published in the R.H.P.
dated 4
th
November, 2013 at p. 4579 - 4596 and before its substitution sub-regulation(3) read as under:
“(3) The O&M expenses for the n
th
year of the control period shall be approved based on the
formula given below:-
O&Mn = R&Mn + EMPn + A&Gn
Where -
R&Mn = K*GFA n-1
EMPn = (EMPn-1)* (1+Gn) * (CPIinflation)
A&Gn = (A&Gn-1)*(WPIinflation)
‘K’ is a constant (could be expressed in %). Value of K for each year of the control period shall
be determined by the Commission in the MYT Tariff order based on licensee’s filing,
benchmarking of R&M Expenses, approved R&M Expenses vis-à-vis GFA approved by the
Commission in past and any other factor considered appropriate by the Commission;
CPIinflation – is the average increase in the Consumer Price Index (CPI) for immediately
preceding three years before the base year;
WPIinflation – is the average increase in the Wholesale Price Index (CPI) for immediately
preceding three years before the base year;
EMPn – employee costs of the distribution licensee for the nth year;
A&Gn – administrative and general costs of the distribution licensee for the nth year;
R&Mn – repair and maintenance costs of the distribution licensee for the nth year;
GFAn-1 – Gross Fixed Asset of the distribution licensee for the n-1th year;
Gn is a growth factor for the nth year. Value of Gn shall be determined by the Commission in
the MYT tariff order for meeting the additional manpower requirement based on licensee’s
filings, benchmarking, approved cost by the Commission in past and any other factor that the
Commission feels appropriate:
Provided that R&M expenses determined shall be utilised towards R&M works only.”
Compendium of HPERC Regulations, March 2021 23
Provision(Emp): Provision corresponding to clauses (iii), (iv) and (v) of sub-regulation
(1-a) of regulation 17, duly projected for relevant year for expenses beyond control
of the distribution licensee and expected one-time expenses as specified above;
A&Gn-1 & A&Gn – administrative and general costs of the distribution licensee for
the (n-1)
th
and n
th
year;
Provision (A&G): Cost for initiatives or other one-time expenses as proposed by the
distribution licensee and validated by the Commission;
R&Mn-1 R&Mn – repair and maintenance costs of the distribution licensee for the (n-
1)
th
and n
th
year;
GFAn-1 – Gross Fixed Asset of the distribution licensee for the (n-1)
th
year;
Gn is a growth factor for the nth year. Value of Gn shall be determined by the
Commission in the MYT tariff order for meeting the additional manpower
requirement based on licensee’s filings, benchmarking, and approved cost by the
Commission in past and any other factor that the Commission feels appropriate:
Provided that, R&M expenses determined shall be utilised towards R&M works
only;
Note: After the fixation of norms of various components of O&M expenses as per
these regulations, the above formulae shall be suitably modified in line with
the provisions.]
1
[(4) The distribution licensee shall submit the detail of sharing of the terminal
benefits including pension of its employees as per the Himachal Pradesh Electricity
Regulatory Commission (Terms and Conditions for Sharing of Cost of Terminal Benefits
of Personnel of the Erstwhile Himachal Pradesh State Electricity Board and Successor
Entities) Regulations, 2015.]
Previous and next