Regulation 33, The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010: Redressal Mechanism
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 - Regulation 33
Text of regulation 33
Redressal Mechanism
33. Redressal Mechanism.- All disputes arising out of or under these regulations shall
be decided by the Commission on an application made in this behalf by the person
aggrieved.
2
[CHAPTER-7-A
SPECIAL PROVISIONS FOR OPEN ACCESS IN DISTRIBUTION SYSTEM FOR THE
CONSUMERS
33-A. General.- In case of the consumers the provisions contained in this Chapter shall be
applicable for connectivity and long/medium term open access to the distribution system.
33- B. Open access to existing consumers.-The existing consumers, who are getting
supply of electricity for their own use from the distribution licensee under the standard
supply agreements and are eligible for open access to the distribution system as per
regulation 3A, shall be provided connectivity and open access to the distribution system to
the extent of their sanctioned contract demand:
Provided that such consumers shall arrange their electricity requirements (power and
energy) for their consumption, including the corresponding energy losses for the various
power systems involved in the open access which shall be borne in kind, with the
concerned supplier(s) and shall so inform all the concerned agencies well in advance:
Provided further that where inter–state transmission system is involved in
conveyance of power from the source of power to the consumer premises, the requisite
permissions shall be obtained in accordance with the procedures laid down by the Central
Electricity Regulatory Commission in their open access Regulations:
Provided further that such existing consumers shall enter into suitable separate
agreements with licensee (s) for availing such open access well before the intended date of
availing open access:
Provided further that, if there is no increase in contract demand-
(i) such existing consumers shall not be required to pay any application fee for
connectivity,
(ii) such consumers shall pay the application fee for medium term and long-term
open access at rate equivalent to 25% of the rate specified in regulation 6:
Provided further that such existing consumers shall also clear their dues against their
existing electricity supply connections before availing such open access.
1
Ins. vide Not. No. HPERC/ 418 dated 7
th
December 2012, published in the R H.P. dated 10
th
December 2012 at p. 5409-5415.
2
Chapter 7-A inserted vide Not. No. HPERC/ 418 dated 7
th
December, 2012 published in theR.H.P.
dated 10
th
December, 2012 at p. 5409-5415.
18 Compendium of HPERC Regulations, March 2021
33-C. Connectivity and Open Access to the prospective consumers.- In case of
prospective consumers seeking connectivity and long/medium term open access from the
distribution licensee for receiving electricity for their own use or the existing consumers
seeking increase in the existing sanctioned contract demand, the terms and conditions as
applicable to the prospective consumers or the existing consumers, as the case may be, under
the Supply Code, the Himachal Pradesh Electricity Regulatory Commission (Recovery of
Expenditure of Supply of Electricity) Regulations, 2012 and the Himachal Pradesh
Electricity Regulatory Commission (Licensee’s Duty for Supply of Electricity on Request)
Regulations, 2004 shall be applicable.
33-D. Restrictions on delivery of power.-In case of any operational constraints in the
transmission system and/or distribution system, the distribution licensee may restrict/stagger
the delivery of the electricity to the open access consumers in the same manner as applicable
to other HT consumers in the area and such consumers shall restrict their drawl of electricity
accordingly:
Provided that a distribution licensee shall not restrict the delivery of electricity due to
the reasons of energy shortage in cases where the open access consumer-
(i) is connected to the distribution system through a dedicated feeder emanating
from the control sub-station of the licensee; and
(ii) the day ahead scheduling is being done for drawl of electricity by the consumer
in accordance with the regulation 33-G and the required quantum of electricity is
being injected to the distribution system in the relevant time blocks for delivery
to the consumer for his own use.
33-E. Arrangements for standby power.- The consumers availing open access shall also
tie up the supply of standby power under various eventualities such as non-scheduling of
power from the generation source due to any reasons, including outages at the generation
source which may be of planned, forced or emergent nature, and constraints in transmission
system(s):
Provided that such open access consumers may get such standby power from the
distribution licensee at mutually agreed terms and conditions:
Provided further that in case of supply of the standby power by the distribution
licensee, the rate (inclusive of wheeling charges, cross subsidy surcharge, additional
surcharge and energy losses) for supply of such power at consumer’s premises shall not
exceed 125% of the overall average rate, worked out by adopting load factor of 60%, under
temporary supply tariff approved by the Commission for supply of power to the other HT
consumers in the area.
33-F. Violation in sanctioned contract demand.- The consumer availing open access
shall not exceed the contract demand sanctioned in his favour at any time and in case of any
violations in any time block the distribution licensee shall be entitled to recover the violation
charges as may be fixed by the distribution licensee without prejudice to its rights to
disconnect electricity of such consumers.
33-G. Scheduling.-(1) Subject to the provisions of sub-regulations (2), scheduling on day
ahead basis shall be done by the State Load Despatch Centre in accordance with the
applicable Grid Code for the consumers availing open access.
Compendium of HPERC Regulations, March 2021 19
(2) In case the inter-state transmission system in not involved in providing open
access to a consumer and the sanctioned contract demand of the consumer does not exceed
5.5 MVA or such other limit as may be fixed by the Commission, day ahead scheduling
shall not be done for such consumers and in such cases the distribution licensee and the open
access consumer shall mutually agree on terms and conditions as well as the procedures for
settlement of time differentiated energy accounts on the basis of weekly data:
Provided that the distribution licensee shall adopt uniform principles for the purpose
of evolving such terms and conditions and procedures and shall include the same in the
detailed procedure as per Regulation 26:
Provided further that the generating station from which such open access consumer
has contracted power shall be subjected to scheduling requirements as per the applicable
Grid Code.
(3) In cases where day ahead scheduling is not done in accordance with sub-
regulations(2), the concerned parties shall also mutually agree about the procedures for
accounting of applicable energy losses and reactive energy.
33-H. Renewable power purchase obligations.- Each consumer availing open access shall
fulfill its Renewable Power Purchase Obligation (RPPO) as per the Himachal Pradesh
Electricity Regulatory Commission (Renewable Power Purchase Obligation and its
Compliance) Regulations, 2010.
33-I. Metering.- (1) In cases where day ahead scheduling is to be done for any of the time
block(s) in accordance with regulation 33-G, the metering arrangements shall be compatible
to the requirements of such scheduling and also have the features of the special energy
meters as per Annexure-II of the Grid Code.
(2) In cases where the day ahead scheduling is not to be done for any of the time
block(s) in accordance of regulation 33-G, the metering arrangements shall be compatible
with the requirements as per the arrangements tied up by the consumers for purchase of
power and for delivery of power to them.
33-J. Applicability of Codes.- The consumers availing open access shall also be governed
by the provisions applicable to the consumers under the Supply Code, Grid Code and
Distribution Code.
33-K. Multiple source of Power.- In case the consumer ties up his power requirement
from more than one sources, the energy accounting etc. and other adjustments shall be done
in accordance with the principles to be incorporated in the detailed procedure.
33-L Overriding effect.- In case of any conflict of provisions contained in this Chapter
with the general provisions contained in other Chapters of these regulations, the special
provisions contained in this Chapter shall have overriding effect in the matters relating to
connectivity and open access to the consumers in the distribution system. ]
CHAPTER - 8
INFORMATION SYSTEM
Previous and next
Questions people ask
Is regulation 33 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.