Regulation 32, The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010: Interface Energy Meters
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 - Regulation 32
Text of regulation 32
Interface Energy Meters
32. Interface Energy Meters.- (1) Interface Energy Meters shall be installed and
maintained by the State Transmission Utility for open access in transmission
1
[and ] by the
distribution licensee for open access in distribution at the cost of the open access customers.
1
Subs. for “HPERC (Terms and Conditions for Determination of Transmission Tariff) Regulations,
2007”, vide Not. No. HPERC/ 418 dated 7
th
December, 2012, published in the R H.P. dated 10
th
December,
2012 at p.5409-5415.
2
The words “as estimated by the State Load Despatch Centre and applied” omitted vide Not. No.
HPERC/ 418 dated 7
th
December 2012 , published in the R.H.P. dated 10
th
December 2012 at p. 5409-5415.
3
Ins. vide Not. No. HPERC/ 418 dated 7
th
December 2012, published in the R H.P. dated 10
th
December 2012 at p. 5409-5415.
Compendium of HPERC Regulations, March 2021 17
(2) Interface Energy Meters installed shall be in accordance with Annexure-2 to the
Grid Code.
(3) Interface Energy Meters for the open access customer shall be open for inspection
by any person authorized by the State Transmission Utility/ Distribution Licensee or the
State Load Despatch Centre.
Previous and next
Questions people ask
Is regulation 32 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.