Regulation 25, The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010: Curtailment priority

The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 - Regulation 25

Text of regulation 25

Curtailment priority

25. Curtailment priority.- When because of operational constraints, force majeure events, grid security or otherwise it becomes necessary to curtail the transmission/ distribution service of the open access customers, the curtailment priority shall in the reverse order of the priority specified in regulation 10: Provided that the amongst the open access customers of a particular category, curtailment shall be carried out on pro-rata basis.

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010

Questions people ask

Is regulation 25 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.