Regulation 24, The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010: Curtailment
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 - Regulation 24
Text of regulation 24
Curtailment
24. Curtailment.- (1) When for the reason of operational constraints or in the interest of
grid security, it becomes necessary to curtail power flow on a transmission/distribution
Compendium of HPERC Regulations, March 2021 13
corridor, the transactions already scheduled may be curtailed by the State Load Despatch
Centre.
(2) In case of curtailment of the approved schedule by the State Load Despatch
Centre, transmission/distribution charges shall be payable pro-rata in accordance with the
curtailed schedule:
Provided that operating charges shall not be revised in case of such curtailment.
Explanation. – For the purpose of this regulation, the expression “operational constraints”
shall include the availability of the adequate capacity in the transmission/distribution system,
appropriate metering and energy accounting system where the electricity to be transmitted/
wheeled can be correctly measured and accounted for and such other factors which may have
an impact on the licensee’s business of supplying electricity to consumers in the area of
supply.
Previous and next
Questions people ask
Is regulation 24 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.