Text of regulation 9

Criteria for long-term and medium-term open access

9. Criteria for long-term and medium-term open access.- (1) Before awarding long- term access, the nodal agency shall have due regard to the augmentation of intra-State transmission/distribution system in accordance with the perspective transmission/ distribution plans developed by the State Transmission Utility/ licensee. (2) Medium-term open access shall be granted if the resultant power flow can be accommodated in the existing transmission/distribution system or the transmission/ distribution system under execution: Provided that no augmentation shall be carried out to the transmission/distribution system for the sole purpose of granting medium-term open access: Provided further that construction of dedicated transmission/distribution line shall not be construed as augmentation of the transmission/distribution system for the purpose of this regulation.

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010

Questions people ask

Is regulation 9 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.