Regulation 9, The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010: Criteria for long-term and medium-term open access
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 - Regulation 9
Text of regulation 9
Criteria for long-term and medium-term open access
9. Criteria for long-term and medium-term open access.- (1) Before awarding long-
term access, the nodal agency shall have due regard to the augmentation of intra-State
transmission/distribution system in accordance with the perspective transmission/
distribution plans developed by the State Transmission Utility/ licensee.
(2) Medium-term open access shall be granted if the resultant power flow can be
accommodated in the existing transmission/distribution system or the transmission/
distribution system under execution:
Provided that no augmentation shall be carried out to the transmission/distribution
system for the sole purpose of granting medium-term open access:
Provided further that construction of dedicated transmission/distribution line shall
not be construed as augmentation of the transmission/distribution system for the purpose of
this regulation.
Previous and next
Questions people ask
Is regulation 9 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.