Text of regulation 6

Application fee

6. Application fee.- 1 [Subject to regulation 33-B, the application] shall be accompanied by a non-refundable application fee specified hereunder, payable in the name and in the manner to be laid down by the nodal agency in the detailed procedure- S. No Quantum of power to be injected/off taken into/from State transmission system/ distribution system Application fee (Rs. in lakhs) For connectivity Medium-term open access Long-term open access 1. Upto 5 MW 2 1 2 2. More than 5 MW upto 10 MW 4 2 4 3. More than 10 MW 6 3 6 2 [Note.- In cases where two or more intra State systems are involved, the application fee shall be equally apportioned between them by the nodal agency.]

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010

Questions people ask

Is regulation 6 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.