Regulation 5, The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010: Filing of application
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 - Regulation 5
Text of regulation 5
Filing of application
5. Filing of application.- The application for grant of connectivity or long-term open
access or medium-term open access shall be made to the nodal agency :
Provided that an application for connectivity is not required to be made by any
transmission/distribution licensee, since transmission/distribution system planning is carried
out in co-ordinated manner by the State Transmission Utility and the Central Electricity
Authority:
Provided; further that the transmission licensee other than the State Transmission
Utility, the distribution licensee, nevertheless shall sign a connection agreement with the
State Transmission Utility or the intra-State transmission licensee as provided for in sub-
regulation (5) of regulation 8 of these regulations.
Previous and next
Questions people ask
Is regulation 5 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.