Text of regulation 9
Consequences of default
9. Consequences of default.- (1) Where the obligated entity does not fulfil the
renewable purchase obligation as provided in these regulations during any year and also
does not purchase the certificates, the Commission may direct the obligated entity to deposit
into a separate fund, to be created and maintained by such obligated entity, such amount as
1
Sub. vide Not. No. HPERC/438 dated 6
th
December, 2017 published in R.H.P. dated 13
th
December, 2017 at p. 8758-8761 and regulation 8 has been stood as under:-
“8. Captive and Open Access User(s)/ Consumer(s).- (1)The quantum of RPPO inclusive of transmission and distribution
losses mentioned in [sub-regulation (2) of regulation 4], shall be applicable to captive and open access user(s)/ consumer(s)
from the date as would be notified by the Commission in the Official Gazette.
(2) Every Captive and Open access consumer(s)/ user(s) shall have to submit necessary details regarding total
consumption of electricity and power purchase from Renewable Energy sources for fulfillment of RPPO on yearly basis on
or before the 30th April to the State Agency.
(3) Captive and Open Access Consumer(s)/ User(s) shall purchase renewable energy as stated in the Table below
regulation 4. If the Captive user(s) and Open Access consumer(s) are unable to fulfill the criteria, the shortfall of the
targeted quantum would attract payment of compensation as per regulation 9 of these regulations.
(4) Captive/Open Access consumer(s)/ User(s) may fulfill its RPPO through the renewable energy certificate as
provided in regulation 5 of these regulations.”
Compendium of HPERC Regulations, March 2021 9
the Commission may determine on the basis of the shortfall in units of RPPO and the
1
[floor
price] decided by the Central Commission:
Provided that the fund so created shall be utilised, as may be directed by the
Commission partly for purchase of the certificates and partly for development of
transmission/sub transmission infrastructure for evacuation of power from generating
stations based on renewable energy sources:
Provided further that the obligated entities shall not be authorized to use the fund
created in pursuance of regulation without prior approval of the Commission:
Provided further that the Commission may empower an officer of the State Agency
to procure from the Power Exchange the required number of certificates to the extent of the
shortfall in the fulfillment of the obligations, out of the amount in the fund:
Provided further that the distribution licensee shall be in breach of its licence
conditions if it fails to deposit the amount directed by the Commission within 15 days of the
communication of the direction.
2
[(2) Where any obligated entity fails to furnish requisite information, as provided
under regulation 7, or fails to comply with the obligation to purchase the required percentage
of power from renewable energy sources as provided under these regulations or fails to
purchase the renewable energy certificates, it shall also be liable for penalty as may be
imposed by the Commission under Section 142 of the Act:
Provided that in case of genuine difficulty in complying with the renewable power
purchase obligation because of non-availability of certificates, the obligated entity can
approach the Commission to carry forward the compliance requirement to the next year:
Provided further that where the Commission has consented to carry forward of
compliance requirement, the provisions of sub-regulation (1) or the provisions of section 142
of the Act shall not be invoked.]
Previous and next
Questions people ask
Is regulation 9 of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 is recorded.